# US 2024/0004373 A1 · Information management system and method for autonomous control of manufacturing process and service

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2024/0004373 A1
- Document ID: US20240004373A1
- Status: Published application
- Kind: A1
- Application number: 18/469,321
- Filed: 2023-09-18
- Published: 2024-01-04
- Earliest claimed: 2021-03-19
- Assignees: Kabushiki Kaisha Toshiba; Toshiba Digital Solutions Corporation; Toshiba Carrier Corporation
- Applicants: Kabushiki Kaisha Toshiba; Toshiba Digital Solutions Corporation; Toshiba Carrier Corporation
- Inventors: Takafumi KOZAKAI; Yasutaka IYADOMI; Tatsuki SHIRAISHI; Shinsuke IUCHI; Sachiko KAJIMURA
- Web page: https://patentgrep.com/patent/US20240004373A1

## CPC

- G05B 19/418: Total factory control, i.e. centrally controlling a plurality of machines, e.g. direct or distributed numerical control [DNC], flexible manufacturing systems [FMS], integrated manufacturing systems [IMS] or computer integrated manufacturing [CIM]
- G05B 19/41835: {characterised by program execution}
- G05B 17/02: electric
- G06Q 10/04: Forecasting or optimisation specially adapted for administrative or management purposes, e.g. linear programming or "cutting stock problem" (market predictions or forecasting for commercial activities G06Q30/0202)
- G06Q 10/06: Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q 10/08: Logistics, e.g. warehousing, loading or distribution; Inventory or stock management
- G06Q 10/10: Office automation; Time management
- G06Q 30/0201: Market modelling; Market analysis; Collecting market data
- G06Q 30/04: Billing or invoicing
- G06Q 40/00: Finance; Insurance; Tax strategies; Processing of corporate or income taxes
- G06Q 50/04: Manufacturing
- G06Q 50/10: Services
- G16Y 10/25: Manufacturing
- G16Y 40/20: Analytics; Diagnosis
- G05B 2219/31372: Mes manufacturing execution system
- G05B 2219/32366: Line performance evaluation
- G06Q 2220/00: Business processing using cryptography
- G05B: CONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS (systems for controlling or regulating non-electric variables G05D; systems for regulating electric or magnetic variables G05F; control devices or systems insofar as characterised by mechanical features only G05G)
- G06Q: INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G16Y: INFORMATION AND COMMUNICATION TECHNOLOGY SPECIALLY ADAPTED FOR THE INTERNET OF THINGS [IoT]

## Abstract

According to one embodiment, an information management system that autonomously controls a manufacturing process and equipment by diversifying a feedback loop in a CPS is provided. The embodiment is applied to an information management system that autonomously controls a manufacturing process and a service. A loop connection section connects a feedback loop of the cyber-physical system. An information acquisition section acquires specific information necessary for the manufacturing process and the service from the feedback loop. An information analytics section analyzes the specific information. An autonomous operation control section autonomously performs the operation control based on an analytics result from the information analytics section.

## Claims

### Claim 1

An information management system that autonomously performs operation control in a manufacturing process and a service, the information management system comprising:
a loop connection section that constructs a first feedback loop of a cyber-physical system;
an information acquisition section that acquires specific information necessary for the manufacturing process from the first feedback loop;
an information analytics section that analyzes the specific information;
an autonomous operation control section that autonomously performs the operation control based on an analytics result acquired by the information analytics section; and
a loop cooperation control section that forms a new second feedback loop constructed by cooperation of the loop connection section and the autonomous operation control section, in response to the analytics result that is new.

### Claim 2 (depends on 1)

The information management system according to claim 1, wherein the new second feedback loop is a restarted feedback loop that has existed so far but has not been used.

### Claim 3 (depends on 1)

The information management system according to claim 1, wherein the new second feedback loop is a feedback loop in which a new feedback loop that has not existed so far is formed.

### Claim 4 (depends on 1)

The information management system according to claim 1, wherein the new second feedback loop is a feedback loop formed by bundling a plurality of feedback loops.

### Claim 5 (depends on 1)

The information management system according to claim 1, wherein the plurality of feedback loops are any one of a bundle of an existing feedback loop and a new feedback loop, a bundle of a plurality of existing second feedback loops, or a bundle of a plurality of new feedback loops.

### Claim 6 (depends on 1)

The information management system according to claim 1, wherein
the information analytics section and the autonomous operation control section construct the first feedback loop as a first control loop for controlling a first control target that is the manufacturing process, and the information analytics section and the loop cooperation control section construct the second feedback loop as a second control loop for further controlling the first control target.

### Claim 7 (depends on 6)

The information management system according to claim 6, wherein
the information analytics section and the autonomous operation control section construct the first feedback loop as a first control loop for controlling a first control target that is the manufacturing process, and the information analytics section and the loop cooperation control section construct the second feedback loop as a second control loop for further controlling a second control target.

### Claim 8 (depends on 6)

The information management system according to claim 6, wherein
the information analytics section and the autonomous operation control section bundle and continue the second control loop of the second feedback loop together with the first control loop of the first feedback loop.

### Claim 9 (depends on 6)

The information management system according to claim 6, wherein
the information analytics section and the autonomous operation control section temporarily bundle and continue the second control loop of the second feedback loop together with the first control loop of the first feedback loop, and release the second control loop of the second feedback loop under a predetermined condition.

### Claim 10 (depends on 6)

The information management system according to claim 6, wherein
the information analytics section and the autonomous operation control section construct the first feedback loop as a first control loop for controlling a first control target that is the manufacturing process, and the information analytics section and the loop cooperation control section construct the second feedback loop as a second control loop for controlling a second control target different from the manufacturing process.

### Claim 11 (depends on 8)

The information management system according to claim 8, wherein the information analytics section and the loop cooperation control section release the second feedback loop in a case where a control purpose of the second feedback loop is completed.

### Claim 12 (depends on 1)

The information management system according to claim 1, wherein the information analytics section and the loop cooperation control section analyze a result of control by the second feedback loop, and further construct a third feedback loop as a third control loop for controlling a third control target different from the control targets of the first control loop and the second control loop according to a content of the analytics.

### Claim 13 (depends on 1)

The information management system according to claim 1, wherein loop cooperation control by at least the first feedback loop and the second feedback loop is applied to a control system that performs equipment management of a building.

### Claim 14 (depends on 1)

The information management system according to claim 1, wherein loop cooperation control by at least the first feedback loop and the second feedback loop is applied to a control system that controls a robot.

### Claim 15 (depends on 1)

The information management system according to claim 1, wherein in loop control by at least the first feedback loop and the second feedback loop, the second feedback loop uses information from a user domain using a product produced in a factory.

### Claim 16 (depends on 1)

The information management system according to claim 1, wherein loop cooperation control by at least the first feedback loop and the second feedback loop is applied to a robot control system that performs storing, unstoring, sorting, conveying, and panning of freights in a distribution center.

### Claim 17 (depends on 1)

The information management system according to claim 1, wherein loop cooperation control by at least the first feedback loop and the second feedback loop is applied to a control system that calculates power consumption of a plurality of business entities and requests cooperation for an amount of the power consumption.

### Claim 18 (depends on 1)

The information management system according to claim 1, wherein loop cooperation control by at least the first feedback loop and the second feedback loop is applied to a control system for a plurality of pieces of power transmission and distribution equipment.

### Claim 19 (depends on 1)

The information management system according to claim 1, wherein loop cooperation control by at least the first feedback loop and the second feedback loop is also applied to a control section that detects a difference in version of software used by a first factory and a second factory.

### Claim 20 (depends on 1)

The information management system according to claim 1, wherein loop cooperation control by at least the first feedback loop and the second feedback loop is also applied to a control section that determines whether or not at least one of a recyclable part or a reusable part is used in a manufacturing factory.

### Claim 21 (depends on 1)

The information management system according to claim 1, wherein loop cooperation control by at least the first feedback loop and the second feedback loop is applied to a control section, in which
a manufacturing line of a manufacturing factory comprises a plurality of manufacturing steps from upstream to downstream, and the control section performs control in such a way that each intermediate product in any manufacturing step is receivable in a manufacturing step suitable for the intermediate product.

### Claim 22 (depends on 1)

The information management system according to claim 1, wherein loop cooperation control by at least the first feedback loop and the second feedback loop is applied to a control section that controls the manufacturing lines in a factory having a first manufacturing line and a second manufacturing line, and
the control section performs control to distribute a first product and a second product conveyed on a common conveying path to the first manufacturing line and the second manufacturing line.

### Claim 23 (depends on 1)

The information management system according to claim 1, wherein loop cooperation control by at least the first feedback loop and the second feedback loop is applied to a power generation control system of a power plant.

### Claim 24 (depends on 1)

The information management system according to claim 1, wherein loop cooperation control by at least the first feedback loop and the second feedback loop is applied to a control system of any one of a car and a home appliance.

### Claim 25 (depends on 1)

The information management system according to claim 1, wherein the specific information includes human five-sense information.

### Claim 26 (depends on 1)

The information management system according to claim 1, wherein the specific information is generated by analyzing data acquired from a biological sensor attached to a human.

### Claim 27 (depends on 1)

The information management system according to claim 1, wherein the specific information includes at least one of renewable energy production information, consumption information, or environmental load information.

### Claim 28 (depends on 1)

The information management system according to claim 1, wherein at least one of the loop connection section or the loop cooperation control section
changes a configuration of a program of an apparatus to be controlled or replaces the program.

### Claim 29 (depends on 28)

The information management system according to claim 28, wherein the apparatus to be controlled is a control apparatus of a power plant, a control apparatus of a factory, a car, or a home appliance.

### Claim 30 (depends on 1)

The information management system according to claim 1, wherein
the cyber-physical system forms a plurality of cyber-physical systems,
each of the plurality of cyber-physical systems grasps data indicating an energy use amount of a business managed by each of the plurality of cyber-physical systems, and
an integration control section generates display data obtained by visualizing the data indicating the energy use amount for each business type.

### Claim 31

An information management method for forming an apparatus that forms a cyberspace of a cyber-physical system, the information management method comprising:
connecting a first feedback loop of the cyber-physical system;
acquiring specific information necessary for a manufacturing process from the first feedback loop;
analyzing the specific information;
autonomously performing the operation control based on an analytics result acquired by the information analytics section; and
constructing a new second feedback loop in response to a new analytics result by cooperation between the loop connection section and the autonomous operation control section.