# US 2024/0003107 A1 · Movable water-permeable pile spur dike and operation method thereof

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2024/0003107 A1
- Document ID: US20240003107A1
- Status: Published application
- Kind: A1
- Application number: 17/778,718
- Filed: 2021-03-02
- Published: 2024-01-04
- Earliest claimed: 2020-09-17
- Assignees: China Three Gorges Corporation; Hohai University
- Applicants: China Three Gorges Corporation; Hohai University
- Inventors: Huichao DAI; Jinqiao MAO; Hanmei LI; Yiqing GONG; Jie DAI
- Web page: https://patentgrep.com/patent/US20240003107A1

## CPC

- E02B 3/06: Moles; Piers; Quays; Quay walls; Groynes; Breakwaters {; Wave dissipating walls; Quay equipment}
- E02B 3/02: Stream regulation, e.g. breaking up subaqueous rock, cleaning the beds of waterways, directing the water flow ({harvesting water plants A01D44/00; underwater loosening of soil or rocks for foundation construction E02D17/16}; dredging or scraping devices E02F5/28)
- E02B: HYDRAULIC ENGINEERING (ship-lifting E02C; dredging E02F)

## Abstract

The present invention has disclosed a movable water-permeable pile spur dike and an operation method thereof. The pile spur dike includes a fixed rail, a plurality of movable rails, a plurality of movable water-permeable piles, pressure sensors, flow meters and a control platform, wherein the plurality of movable water-permeable piles are arranged on the fixed rail and the plurality of movable rails, the pressure sensor and the flow meter are arranged at each monitoring point on the outer side wall of each movable water-permeable pile, the control platform is used for analysis and calculation according to the monitoring data from each pressure sensor and each flow meter and adjusts the positions of each movable rail and each movable water-permeable pile, so that the water flow velocity and spur dike's pressure at each monitoring point are less than a corresponding flow velocity threshold value and pressure threshold value.

## Claims

### Claim 1

A movable water-permeable pile spur dike, comprising a fixed rail (2), a plurality of movable rails (3), a plurality of movable water-permeable piles (1), pressure sensors (11), flow meters (12) and a control platform (4),
wherein one end of each movable rail (3) is slidably connected to one side of the downstream face of said fixed rail (2), and can move relatively in the extending direction of said fixed rail (2);
said plurality of movable water-permeable piles (1) are arranged on said fixed rail (2) and said plurality of movable rails (3);
said pressure sensors (11) and said flow meter (12) are arranged at each monitoring point on the outer side wall of each movable water-permeable pile (1) and respectively used to monitor the changes in the water pressure on each monitoring point and the changes in the water flow velocity about it;
said plurality of movable rail (3), said plurality of movable water-permeable pile (1), each of said pressure sensors (11) and each flow meter (12) are respectively connected to said control platform (4) in a communication mode, which is used for analysis and calculation according to the monitoring data from each of said pressure sensors (11) and each flow meter (12) and adjusts the positions of each movable rail (3) and each movable water-permeable pile (1), so that the water flow velocity and spur dike's pressure at each monitoring point are both less than a corresponding flow velocity threshold value and pressure threshold value, and the spur dike's water permeability falls within a setting range.

### Claim 2 (depends on 1)

The movable water-permeable pile spur dike according to claim 1, wherein each movable water-permeable pile (1) comprises a hollow cylinder, of said hollow cylinder, the upstream face is provided with a plurality of upstream face permeable holes (14) whose diameters increase from top to bottom, and the downstream face is provided with a plurality of downstream face permeable holes (15) whose diameters decrease from top to bottom, each upstream face permeable hole (14) and each downstream face permeable hole (15) penetrate through said water-permeable pile to its hollow, and said upstream face permeable holes (14) and said downstream face permeable holes (15) are completely alternately arranged in the vertical direction.

### Claim 3 (depends on 1)

The movable water-permeable pile spur dike according to claim 1, wherein the upper surfaces of said fixed rail (2) and said plurality of movable rail (3) are provided with two or more than two pile-sliding grooves (21) arranged in parallel, two sides of each pile-sliding groove (21) are provided with tooth-shaped grooves (2101);
the bottom of each water-movable permeable pile (1) is provided with two or more than two rows of pile roller groups, each of which corresponds to one pile-sliding groove (21), and each of which comprises one or more than one pile roller unit, each pile roller unit comprises a connector, a pile roller (61) and an electromagnetic group (6301), of said connector, the top is embedded inside said mobile water-permeable pile (1), the middle part is a hollow connecting block (6203), and the two ends of the bottom extend downwards to form connecting pieces (6202), both of which are connected by a connecting rod (6201), said connecting rod (6201) passes through the center of said pile roller (61), a pile-fixing clamp (63) is sleeved on said connecting rod (6201), said electromagnetic group (6301) is arranged in the hollow connecting block (6203) of said connector, said pile roller (61) and said electromagnetic group (6301) are connected with said control platform (4) in a communication mode, so as to be rolled and magnetically adsorb said pile-fixing clamp (63) under the control of said control platform (4), respectively;
in the case that said electromagnetic group (6301) has not magnetically adsorbed said pile-fixing clamp (63), said pile-fixing clamp (63) is embedded in said tooth-shaped grooves (2101) of its rail under the action of gravity, in the case that said electromagnetic group (6301) has magnetically adsorbed said pile-fixing clamp (63), said pile-fixing clamp (63) leaves said tooth-shaped grooves (2101).

### Claim 4 (depends on 3)

The movable water-permeable pile spur dike according to claim 3, wherein said pile-fixing clamp (63) comprises 2 U-shaped bent iron sheets (6302), the two ends of each U-shaped bent iron sheet (6302) are respectively sleeved on said connecting rod (6201), and can rotate around said connecting rod (6201), in the case that said electromagnetic group (6301) has not magnetically adsorbed said pile-fixing clamp (63), said two U-shaped bent iron sheets (6302), under the action of gravity, respectively, are embedded in said tooth-shaped grooves (2101) of their rails in the opposite direction.

### Claim 5 (depends on 4)

The movable water-permeable pile spur dike according to claim 4, wherein the sides of the two straight ends of each U-shaped bent iron sheet (6302) are fan-shaped.

### Claim 6 (depends on 4)

The movable water-permeable pile spur dike according to claim 4, wherein said 2 U-shaped bent iron sheets (6302) are connected with each other through a telescopic chain net, said telescopic chain net (6303) is made from elastic wear-resistant material, in the case that said electromagnetic group (6301) has magnetically adsorbed said 2 U-shaped bent iron sheets (6302), said telescopic chain net (6303) shrinks, in the case that said electromagnetic group (6301) has not magnetically adsorbed said 2 U-shaped bent iron sheets (6302), said telescopic chain net (6303) spreads out and covers the surface of said pile roller (61) after its both ends being stretched.

### Claim 7 (depends on 1)

The movable water-permeable pile spur dike according to claim 1, wherein said fixed rail (2) is an irregular curved rail, or a broken-line rail formed by splicing multiple segments of straight sub-rails.

### Claim 8 (depends on 1)

The movable water-permeable pile spur dike according to claim 1, wherein the lower surface of said fixed rail (2) is provided with one or more than one four-sided hollowed-out pyramid (22) sinking in the river bed, the quadrilateral bottom surface of said four-sided hollowed-out pyramid (22) is embedded in the lower surface of said fixed rail (2), and has a pyramided outer frame formed by metal wires, each hollowed out surface also has a plurality of metal wires wound across its edges, said plurality of four-sided hollowed-out pyramids (22) are arranged along such three straight lines, as the edges of the corresponding fixed rail and the central axis of the long end, and the four-sided hollowed-out pyramids along the two adjacent straight lines are alternated with each other.

### Claim 9 (depends on 1)

The movable water-permeable pile spur dike according to claim 1, wherein one side of the downstream face of said fixed rail (2) is provided with a groove (2201) whose inside is provided with a movable rail groove (2202), one end connecting each movable rail (3) to said fixed rail (2) is provided with a moving slider (33), and the bottom of one end away from said fixed rail is provided with a movable rail roller (31), which is inlaid into said movable rail groove (2202) inside said groove (2201), said movable rail roller (31) is connected with said control platform (4) in a communication mode, and can roll along the matched convex single rail (32) fixed on the river bed under the control of said control platform, thereby driving said moving slider (33) to slide, so as to adjust the position of the corresponding movable rail (3).

### Claim 10 (depends on 1)

An operation method of the movable water-permeable pile spur dike according to claim 1, comprising the following steps:
(S1) performing statistical analysis based on each interannual or annual data results of rivers, setting the water permeability range of said movable water-permeable pile spur dike and the initial position of said plurality of movable water-permeable piles (1) and said plurality of movable rails (3), arranging said control platform (4) according to the initial position, and controlling and adjusting said plurality of movable water-permeable piles (1) and said plurality of movable rails (3) to form said movable water-permeable pile spur dike in its initial state;
(S2) each flow meter (12) monitoring the flow velocity of water flow that comprises longitudinal flow velocity ux and lateral flow velocity uy, at its monitoring point of the spur dike in real time; of each flow meter, a sampling interval period being denoted by Δt, a monitoring period being denoted by T, an average longitudinal flow velocity value within said monitoring period T being denoted by Ux, and an average transverse flow velocity value being denoted by as Uy; each flow meter (12) sending Ux and Uy to said control platform (4) as monitoring data; each of said pressure sensors (11) monitoring the pressure borne by it that comprises hydrostatic pressure P1 and hydrodynamic pressure P2, at its monitoring point of the spur dike in real time; of each pressure sensor, a sampling interval period also being denoted by Δt, a monitoring period also being denoted by T, an average value of the sum of the hydrostatic pressure and the hydrodynamic pressure within said monitoring period T being denoted by P; each of said pressure sensors (11) sending P to said control platform (4) as monitoring data;
(S3) said control platform (4) calculating the real-time water permeability of said movable water-permeable spur dike based on the real-time monitoring data from each pressure sensor (11) and each flow meter (12) according to Formula (1):
a
=
θ
×
P
×
K
a
×
Σ
⁢
L
i
D
1
⁢
U
wherein, a is the water permeability of the spur dike; Ka is an error-correcting function, which is required to be determined by model tests and prototype observations; ΣLi is the sum of the water-permeable pile's spacing; U is the average water flow velocity of each monitoring point, which is calculated from the data collected by each flow meter, within each monitoring period; P is the average value, which is calculated from the data collected by each pressure sensor, of the sum of the hydrostatic pressure and the hydrodynamic pressure of the spur dike within each monitoring period; D1 is the total length of the spur dike; θ is the water permeability of the water-permeable pile; and
(S4) based on said real-time water permeability, said real-time monitoring data of each flow meter (12), and said real-time monitoring data of each pressure sensor (11), the control platform (4) adjusting the positional arrangement of said multiple movable water-permeable piles (1) and said plurality of movable rails (3), specifically including:
judging whether the water flow velocity U at each monitoring point and the pressure P borne by the spur dike within the current monitoring period are both less than a preset threshold;
if both are less than said preset threshold and said real-time permeability is within the water permeability range, keeping the spacing between said water-permeable piles unchanged, that is, the water permeability of the spur dike attaining the stability of the spur dike and having a good response mechanism to water flow;
if the flow velocity U or the spur dike's pressure P at one or more monitoring points within the current monitoring period is more than said preset threshold value, having a disadvantage to stabilize the spur dike, a simulation being done to gradually increase the spacing of the movable water-permeable piles (1) at the corresponding monitoring point until the water flow velocity U and the spur dike's pressure P at each monitoring point are less than the corresponding preset threshold value and the water permeability calculated by simulation falls within said water permeability range, then making an adjustment according to the final simulation results; if the flow velocity U or the spur dike's pressure P at each monitoring point is less than said preset threshold value, but the water permeability of the spur dike exceeds said water permeability range, said control platform (4) making the whole spur dike denser to reduce the water permeability through an adjustment to the positions of each movable rail (3) and said movable water-permeable piles (1) thereon, including decreasing the distance between said movable rails (3), that is, moving said movable water-permeable piles (1) on each movable rail (3) close to said fixed rail (2) to decrease the spacing of said water-permeable movable piles (1) on two movable rails, or increasing the number of said movable water-permeable piles (1) in the spur dike.

### Claim 11 (depends on 2)

The movable water-permeable pile spur dike according to claim 2, wherein the upper surfaces of said fixed rail (2) and said plurality of movable rail (3) are provided with two or more than two pile-sliding grooves (21) arranged in parallel, two sides of each pile-sliding groove (21) are provided with tooth-shaped grooves (2101);
the bottom of each water-movable permeable pile (1) is provided with two or more than two rows of pile roller groups, each of which corresponds to one pile-sliding groove (21), and each of which comprises one or more than one pile roller unit, each pile roller unit comprises the connector, the pile roller (61) and the electromagnetic group (6301), of said connector, the top is embedded inside said mobile water-permeable pile (1), the middle part is a hollow connecting block (6203), and the two ends of the bottom extend downwards to form connecting pieces (6202), both of which are connected by a connecting rod (6201), said connecting rod (6201) passes through the center of said pile roller (61), a pile-fixing clamp (63) is sleeved on said connecting rod (6201), said electromagnetic group (6301) is arranged in the hollow connecting block (6203) of said connector, said pile roller (61) and said electromagnetic group (6301) are connected with said control platform (4) in the communication mode, so as to be rolled and magnetically adsorb said pile-fixing clamp (63) under the control of said control platform (4), respectively;
in the case that said electromagnetic group (6301) has not magnetically adsorbed said pile-fixing clamp (63), said pile-fixing clamp (63) is embedded in said tooth-shaped grooves (2101) of its rail under the action of gravity, in the case that said electromagnetic group (6301) has magnetically adsorbed said pile-fixing clamp (63), said pile-fixing clamp (63) leaves said tooth-shaped grooves (2101).

### Claim 12 (depends on 10)

The method of claim 10, wherein each movable water-permeable pile (1) comprises the hollow cylinder, of said hollow cylinder, the upstream face is provided with the plurality of upstream face permeable holes (14) whose diameters increase from top to bottom, and the downstream face is provided with the plurality of downstream face permeable holes (15) whose diameters decrease from top to bottom, each upstream face permeable hole (14) and each downstream face permeable hole (15) penetrate through said water-permeable pile to its hollow, and said upstream face permeable holes (14) and said downstream face permeable holes (15) are completely alternately arranged in the vertical direction.

### Claim 13 (depends on 10)

The method of claim 10 wherein the upper surfaces of said fixed rail (2) and said plurality of movable rail (3) are provided with two or more than two pile-sliding grooves (21) arranged in parallel, two sides of each pile-sliding groove (21) are provided with tooth-shaped grooves (2101);
the bottom of each water-movable permeable pile (1) is provided with two or more than two rows of pile roller groups, each of which corresponds to one pile-sliding groove (21), and each of which comprises one or more than one pile roller unit, each pile roller unit comprises the connector, the pile roller (61) and the electromagnetic group (6301), of said connector, the top is embedded inside said mobile water-permeable pile (1), the middle part is a hollow connecting block (6203), and the two ends of the bottom extend downwards to form connecting pieces (6202), both of which are connected by a connecting rod (6201), said connecting rod (6201) passes through the center of said pile roller (61), a pile-fixing clamp (63) is sleeved on said connecting rod (6201), said electromagnetic group (6301) is arranged in the hollow connecting block (6203) of said connector, said pile roller (61) and said electromagnetic group (6301) are connected with said control platform (4) in a communication mode, so as to be rolled and magnetically adsorb said pile-fixing clamp (63) under the control of said control platform (4), respectively;
in the case that said electromagnetic group (6301) has not magnetically adsorbed said pile-fixing clamp (63), said pile-fixing clamp (63) is embedded in said tooth-shaped grooves (2101) of its rail under the action of gravity, in the case that said electromagnetic group (6301) has magnetically adsorbed said pile-fixing clamp (63), said pile-fixing clamp (63) leaves said tooth-shaped grooves (2101).

### Claim 14 (depends on 13)

The method of claim 13 wherein said pile-fixing clamp (63) comprises 2 U-shaped bent iron sheets (6302), the two ends of each U-shaped bent iron sheet (6302) are respectively sleeved on said connecting rod (6201), and can rotate around said connecting rod (6201), in the case that said electromagnetic group (6301) has not magnetically adsorbed said pile-fixing clamp (63), said two U-shaped bent iron sheets (6302), under the action of gravity, respectively, are embedded in said tooth-shaped grooves (2101) of their rails in the opposite direction.

### Claim 15 (depends on 14)

The method of claim 14 wherein the sides of the two straight ends of each U-shaped bent iron sheet (6302) are fan-shaped.

### Claim 16 (depends on 14)

The method of claim 14 wherein said 2 U-shaped bent iron sheets (6302) are connected with each other through a telescopic chain net, said telescopic chain net (6303) is made from elastic wear-resistant material, in the case that said electromagnetic group (6301) has magnetically adsorbed said 2 U-shaped bent iron sheets (6302), said telescopic chain net (6303) shrinks, in the case that said electromagnetic group (6301) has not magnetically adsorbed said 2 U-shaped bent iron sheets (6302), said telescopic chain net (6303) spreads out and covers the surface of said pile roller (61) after its both ends being stretched.

### Claim 17 (depends on 10)

The method of claim 10 wherein said fixed rail (2) is the irregular curved rail, or the broken-line rail formed by splicing multiple segments of straight sub-rails.

### Claim 18 (depends on 10)

The method of claim 10, wherein the lower surface of said fixed rail (2) is provided with one or more than one four-sided hollowed-out pyramid (22) sinking in the river bed, the quadrilateral bottom surface of said four-sided hollowed-out pyramid (22) is embedded in the lower surface of said fixed rail (2), and has a pyramided outer frame formed by metal wires, each hollowed out surface also has a plurality of metal wires wound across its edges, said plurality of four-sided hollowed-out pyramids (22) are arranged along such three straight lines, as the edges of the corresponding fixed rail and the central axis of the long end, and the four-sided hollowed-out pyramids along the two adjacent straight lines are alternated with each other.

### Claim 19 (depends on 10)

The method of claim 10, wherein one side of the downstream face of said fixed rail (2) is provided with the groove (2201) whose inside is provided with the movable rail groove (2202), one end connecting each movable rail (3) to said fixed rail (2) is provided with the moving slider (33), and the bottom of one end away from said fixed rail is provided with the movable rail roller (31), which is inlaid into said movable rail groove (2202) inside said groove (2201), said movable rail roller (31) is connected with said control platform (4) in a communication mode, and can roll along the matched convex single rail (32) fixed on the river bed under the control of said control platform, thereby driving said moving slider (33) to slide, so as to adjust the position of the corresponding movable rail (3).