# US 2023/0416012 A1 · System and method for conveyor system configuration

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2023/0416012 A1
- Document ID: US20230416012A1
- Status: Published application
- Kind: A1
- Application number: 18/340,104
- Filed: 2023-06-23
- Published: 2023-12-28
- Earliest claimed: 2022-06-23
- Applicants: ATS Corporation
- Inventors: Lucas BEYAK; Anton DOLGOVYKH; Graham Richard KNAP; Javan Kenneth TAYLOR; Patrick WOJCIK; Simon DREXLER; Ben HOPE
- Web page: https://patentgrep.com/patent/US20230416012A1

## CPC

- B65G 43/10: Sequence control of conveyors operating in combination
- G05B 19/41885: {characterised by modeling, simulation of the manufacturing system}
- B65G: TRANSPORT OR STORAGE DEVICES, e.g. CONVEYORS FOR LOADING OR TIPPING, SHOP CONVEYOR SYSTEMS OR PNEUMATIC TUBE CONVEYORS (packaging B65B; handling thin or filamentary materials, e.g. paper sheets or thread, B65H; cranes B66C; portable mobile or lifting or hauling appliances, e.g. hoists, B66D; devices for lifting or lowering goods for loading or unloading purposes, e.g. fork-lift trucks, B66F9/00; emptying bottles, jars, casks, barrels or similar containers, not otherwise provided for, B67C9/00; delivering or transferring liquids B67D; filling or discharging vessels for liquefied, solidified or compressed gases F17C; pipe-line systems for fluids F17D)
- G05B: CONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS (systems for controlling or regulating non-electric variables G05D; systems for regulating electric or magnetic variables G05F; control devices or systems insofar as characterised by mechanical features only G05G)

## Abstract

A method for automatic target configuration in a conveyor system, the method including: perform a pallet-flow analysis for a station; generate target and move configurations for the station; determine if there are more stations and perform the pallet flow analysis and the generate target and move configurations until all stations are completed; finalize routing targets' configurations; and finalize exit move configurations. A system for automatic target configuration in a conveyor system, the system including: a processor; a processor readable memory storing computer instructions, which, when executed by the processor, cause the processor to: perform a pallet-flow analysis for a station; generate target and move configurations for the station; determine if there are more stations and perform the pallet flow analysis and the generate target and move configurations until all stations are completed; finalize routing targets' configurations; and finalize exit move configurations.

## Claims

### Claim 1

A method for automatic target configuration in a conveyor system, the method comprising:
perform a pallet-flow analysis for a station;
generate target and move configurations for the station;
determine if there are more stations and perform the pallet flow analysis and the generate target and move configurations until all stations are completed;
finalize routing targets' configurations; and
finalize exit move configurations.

### Claim 2 (depends on 1)

A method according to claim 1, wherein the pallet-flow analysis comprises:
determine operation points within the station;
determine if there are any pallets in-process at the station;
if there are pallets in-process, calculate a required move distance by calculating a distance from the most downstream operation point to the most downstream unprocessed part and move in-process pallets forward by the calculated required move distance;
determine if all operation points at the current station have been utilized, if no, add new pallets;
mark processed parts by updating the processed status of parts that are currently at manufacturing operation points; and
determine if all parts have been processed and if not, return to check on pallets in process, otherwise end the method.

### Claim 3 (depends on 2)

A method according to claim 2, wherein the calculate a required move distance comprises calculating a pallet offset.

### Claim 4 (depends on 1)

A method according to claim 1, wherein the generate target and move configurations comprises:
determine the most downstream and upstream pallet locations for the current station;
configure a routing target and place the routing target upstream of the current station;
determine if there is a new unique target set size, if yes, use the new targets and, if no, use the existing targets;
determine if there are more processing steps, if yes, return to determine if there is a new unique target set size;
determine if there are more substations; if yes, return to determine if there is a new unique target set size;
configure pallet entry routings;
configure in-station routings; and
perform any additional routing target configuration.

### Claim 5 (depends on 3)

A method according to claim 3, wherein the configure pallet entry routings comprises configuring pallet offsets.

### Claim 6 (depends on 1)

A method according to claim 1, wherein the finalize routing targets' configurations comprises:
setting a routing target between the current station and the upstream neighboring station; or
setting a conditional hover-routing target at a most upstream target of the current station.

### Claim 7 (depends on 1)

A method according to claim 1, wherein the finalize exit move configurations comprises:
setting the destination target to be the most upstream pallet target for the subsequent station.

### Claim 8

A system for target configuration in a conveyor system, the system comprising:
a processor;
a processor readable memory storing computer instructions, which, when executed by the processor, cause the processor to:
perform a pallet-flow analysis for a station;
generate target and move configurations for the station;
determine if there are more stations and perform the pallet flow analysis and the generate target and move configurations until all stations are completed;
finalize routing targets' configurations; and
finalize exit move configurations.

### Claim 9 (depends on 8)

A system according to claim 8, wherein the pallet-flow analysis comprises computer instructions, which, when executed by the processor, cause the processor to:
determine operation points within the station;
determine if there are any pallets in-process at the station;
if there are pallets in-process, calculate a required move distance by calculating a distance from the most downstream operation point to the most downstream unprocessed part and move in-process pallets forward by the calculated required move distance;
determine if all operation points at the current station have been utilized, if no, add new pallets;
mark processed parts by updating the processed status of parts that are currently at manufacturing operation points; and
determine if all parts have been processed and if not, return to check on pallets in process, otherwise end the method.

### Claim 10 (depends on 9)

A system according to claim 9, wherein the calculate a required move distance comprises calculating a pallet offset.

### Claim 11 (depends on 8)

A system according to claim 8, wherein the generate target and move configurations comprises computer instructions, which, when executed by the processor, cause the processor to:
determine the most downstream and upstream pallet locations for the current station;
configure a routing target and place the routing target upstream of the current station;
determine if there is a new unique target set size, if yes, use the new targets and, if no, use the existing targets;
determine if there are more processing steps, if yes, return to determine if there is a new unique target set size;
determine if there are more substations; if yes, return to determine if there is a new unique target set size;
configure pallet entry routings;
configure in-station routings; and
perform any additional routing target configuration.

### Claim 12 (depends on 11)

A system according to claim 11, wherein the configure pallet entry routings comprises configuring pallet offsets.

### Claim 13 (depends on 8)

A system according to claim 8, wherein the finalize routing targets' configurations comprises:
setting a routing target between the current station and the upstream neighboring station; or
setting a conditional hover-routing target at a most upstream target of the current station.

### Claim 14 (depends on 8)

A system according to claim 8, wherein the finalize exit move configurations comprises:
setting the destination target to be the most upstream pallet target for the subsequent station.