# US 2023/0411948 A1 · Fault logic based operating system for one or more disconnects in a circuit breaker, with provision of limited automatic self-reset and/or reset by software application

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2023/0411948 A1
- Document ID: US20230411948A1
- Status: Published application
- Kind: A1
- Application number: 18/210,933
- Filed: 2023-06-16
- Published: 2023-12-21
- Earliest claimed: 2022-06-17
- Assignees: Eaton Intelligent Power Limited
- Applicants: Eaton Intelligent Power Limited
- Inventors: Sandy Omar Jimenez Gonzalez; Nicholas David Reynolds; Karthik Satyanarayanan; Harish Gode; Tejal Sheth
- Web page: https://patentgrep.com/patent/US20230411948A1

## CPC

- H02H 3/04: with warning or supervision in addition to disconnection, e.g. for indicating that protective apparatus has functioned {(watching of pilot wires H02H1/0084; protection of protective arrangements H02H7/008; indication of the state of electronic switches H03K17/18)}
- H01H 71/04: Means for indicating condition of the switching device {(by means of an auxiliary contact H01H71/46)}
- H02H 1/0007: {concerning the detecting means (in general G01R or other subclasses of G01; reed switches H01H71/2445)}
- H02H 3/066: {Reconnection being a consequence of eliminating the fault which caused disconnection}
- H02H 3/093: with timing means {(in general H02H3/027; thermal delay H02H3/085; timing means for undervoltage protection H02H3/247)}
- H02H 3/335: {the main function being self testing of the device}
- H02H 3/32: involving comparison of the voltage or current values at corresponding points in different conductors of a single system, e.g. of currents in go and return conductors
- H02H: EMERGENCY PROTECTIVE CIRCUIT ARRANGEMENTS (indicating or signalling undesired working conditions G01R, e.g. G01R31/00, G08B; locating faults along lines G01R31/08; emergency protective devices H01H)
- H01H: ELECTRIC SWITCHES; RELAYS; SELECTORS; EMERGENCY PROTECTIVE DEVICES (contact cables H01B7/10; electrolytic self-interrupters H01G9/18; emergency protective circuit arrangements H02H; switching by electronic means without contact-making H03K17/00)

## Abstract

A circuit breaker with at least one disconnect mechanism and a smart monitoring system implements nuanced fault logic in order to minimize disruption to operation of the circuit breaker under a fault condition, and enables the circuit breaker to address nuisance or low severity faults separately from load switching. Under low severity or nuisance fault conditions, the smart monitoring system temporarily disconnects affected loads from the power supply rather than tripping the entire circuit breaker so that the loads can be reconnected to the power supply if the fault condition resolves within a short amount of time. In addition, the disconnect mechanism(s) that are used to temporarily disconnect the load(s) are configured to be re-closed after opening without requiring manual intervention. In high severity fault conditions, the smart monitoring system actuates tripping of the entire breaker, requiring manual re-closing of the circuit breaker.

## Claims

### Claim 1

A circuit breaker, the circuit breaker comprising:
a number of pole assemblies, each pole assembly comprising:
a line conductor structured to be connected between a power source and a load;
a primary disconnect device disposed along the line conductor;
a primary disconnect trip system configured to actuate the primary disconnect device between an open state and a closed state;
a secondary disconnect device disposed in series with the primary disconnect device along the line conductor;
secondary disconnect driving circuitry configured to actuate the secondary disconnect device between an open state and a closed state; and
a number of monitoring devices configured to monitor operating conditions in the pole assembly; and
a controller,
wherein, for each pole assembly:
the controller is configured to receive input from the number of monitoring devices, to communicate with a remote user communication device, and to communicate with the primary disconnect trip system and with the secondary disconnect driving circuitry,
the primary disconnect device and the secondary disconnect device must be closed in order for the load to receive power from the power source,
the controller is configured to determine when a fault condition exists in the circuit breaker based on the input from the number of monitoring devices and to determine a severity level of the fault condition,
when the controller determines that the fault condition severity level is minor, the controller is configured to actuate the secondary disconnect driving circuitry to open the secondary disconnect device, wait for a delay time, assess the fault condition multiple times during the delay time, and determine if the fault condition has resolved within the delay time, and
when the fault condition has resolved within the delay time, the controller is configured to actuate the secondary disconnect driving circuitry to close the secondary disconnect device without manual intervention.

### Claim 2 (depends on 1)

The circuit breaker of claim 1,
wherein, for each pole assembly, the controller is configured to automatically actuate the secondary disconnect driving circuitry to close the secondary disconnect device after the fault condition has resolved.

### Claim 3 (depends on 1)

The circuit breaker of claim 1,
wherein, for each pole assembly, the controller is configured to actuate the secondary disconnect driving circuitry to close the secondary disconnect device after receiving remote user instructions once the fault condition has resolved.

### Claim 4 (depends on 3)

The circuit breaker of claim 3,
wherein, for each pole assembly:
the controller is configured to communicate with either a mobile phone app or a human machine interface, and
the controller is configured to receive instructions input by a user to the mobile phone app or to the human machine interface to actuate the secondary disconnect driving circuitry to close the secondary disconnect device.

### Claim 5 (depends on 1)

The circuit breaker of claim 1,
wherein, for each pole assembly, when the fault condition has not resolved within the delay time, the controller is configured to actuate the primary disconnect trip system to trip open the primary disconnect device.

### Claim 6 (depends on 5)

The circuit breaker of claim 5,
wherein, for each pole assembly, closing the primary disconnect device after the primary disconnect device has been tripped open requires manual intervention.

### Claim 7 (depends on 1)

The circuit breaker of claim 1,
wherein, for each pole assembly, when the controller determines that the fault condition severity level is high severity, the controller is configured to actuate the primary disconnect trip system to trip open the primary disconnect device.

### Claim 8 (depends on 7)

The circuit breaker of claim 7,
wherein, for each pole assembly, closing the primary disconnect device after the primary disconnect device has been tripped open requires manual intervention.

### Claim 9

A circuit breaker, the circuit breaker comprising:
a number of pole assemblies, each pole assembly comprising:
a line conductor structured to be connected between a power source and a load;
a primary disconnect device disposed along the line conductor;
a primary disconnect trip system configured to actuate the primary disconnect device between a first open state and a first closed state;
a primary disconnect open/close system configured to actuate the primary disconnect between a second open state and a second closed state; and
a number of monitoring devices configured to monitor operating conditions in the circuit breaker; and
a controller,
wherein, for each pole assembly:
the controller is configured to receive input from the number of monitoring devices, to communicate with a remote user communication device, and to communicate with the primary disconnect trip system and with the primary disconnect open/close system,
the primary disconnect device must be closed in order for the load to receive power from the power source,
the controller is configured to determine when a fault condition exists in the circuit breaker based on the input from the number of monitoring devices and to determine a severity level of the fault condition,
when the controller determines that the fault condition severity level is minor, the controller is configured to actuate the primary disconnect open/close system to open the primary disconnect device, wait for a delay time, assess the fault condition multiple times during the delay time, and determine if the fault condition has resolved within the delay time, and
when the fault condition has resolved within the delay time, the controller is configured to actuate the primary disconnect open/close system to close the primary disconnect device without manual intervention.

### Claim 10 (depends on 9)

The circuit breaker of claim 9,
wherein, for each pole assembly, the controller is configured to automatically actuate the primary disconnect open/close system to close the primary disconnect device after the fault condition has resolved.

### Claim 11 (depends on 9)

The circuit breaker of claim 9,
wherein, for each pole assembly, the controller is configured to actuate the primary disconnect open/close system to close the primary disconnect device after receiving remote user instructions once the fault condition has resolved.

### Claim 12 (depends on 11)

The circuit breaker of claim 11,
wherein, for each pole assembly:
the controller is configured to communicate with either a mobile phone app or a human machine interface, and
the controller is configured to receive instructions input by a user to the mobile phone app or to the human machine interface to actuate the primary disconnect open/close system to close the primary disconnect device.

### Claim 13 (depends on 9)

The circuit breaker of claim 9,
wherein, for each pole assembly, when the fault condition has not resolved within the delay time, the controller is configured to instruct the primary disconnect trip system to trip the primary disconnect device to a trip state.

### Claim 14 (depends on 13)

The circuit breaker of claim 13,
wherein, for each pole assembly, closing the primary disconnect device once the primary disconnect device is in the trip state requires manual intervention.

### Claim 15 (depends on 9)

The circuit breaker of claim 9,
wherein, for each pole assembly, when the controller determines that the fault condition severity level is high severity, the controller is configured to instruct the primary disconnect trip system to trip the primary disconnect device to the open state.

### Claim 16 (depends on 15)

The circuit breaker of claim 15,
wherein, for each pole assembly, closing the primary disconnect device after the primary disconnect device has been tripped to the open state requires manual intervention.

### Claim 17

A method of handling faults in a pole assembly of a circuit breaker, the method comprising:
providing a first disconnect device along a line conductor of the pole assembly between a power source and a load;
monitoring operating conditions in the pole assembly with a number of monitoring devices;
detecting a fault condition with a controller based on input to the controller from the number of monitoring devices;
determining with the controller if a severity level of the fault condition is minor or high severity; and
when the fault condition is minor:
actuating the first disconnect device to open with the controller;
waiting for a delay time;
assessing the fault condition with the controller multiple times during the delay time;
determining with the controller whether the fault condition has resolved within the delay time; and
when the fault condition has resolved within the delay time, actuating closing of the first disconnect device without manual intervention.

### Claim 18 (depends on 17)

The method of claim 17, further comprising:
within each pole assembly, providing a second disconnect device along the line conductor in series with the first disconnect device,
wherein the second disconnect device remains closed during the delay time.

### Claim 19 (depends on 18)

The method of claim 18, further comprising:
within each pole assembly, when the controller determines that the fault condition has not resolved within the delay time, actuating the second disconnect device to open with the controller.

### Claim 20 (depends on 17)

The method of claim 17, further comprising: