# US 2023/0410011 A1 · Systems, Devices, and/or Methods for Managing Projects

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2023/0410011 A1
- Document ID: US20230410011A1
- Status: Published application
- Kind: A1
- Application number: 17/836,951
- Filed: 2022-06-09
- Published: 2023-12-21
- Earliest claimed: 2022-06-09
- Assignees: Abductive Services LLC
- Applicants: Abductive Services LLC
- Inventors: Chijioke Kingsley Ofoche
- Web page: https://patentgrep.com/patent/US20230410011A1

## CPC

- G06Q 10/06: Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q 10/0635: Risk analysis of enterprise or organisation activities
- G06Q 10/06312: {Adjustment or analysis of established resource schedule, e.g. resource or task levelling, or dynamic rescheduling}
- G06Q 10/103: {Workflow collaboration or project management}
- G06Q 2220/00: Business processing using cryptography
- G06Q: INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR

## Abstract

Certain exemplary embodiments can provide a method, which comprises, via a set of machine instructions: representing an activity of a project as a node of a graph; representing a relationship of the project as an edge of the graph; utilizing a normal distribution and associated p-values to obtain a first probability of completing the activity in a predetermined time period; and rendering a first user interface that indicates the probability of completing the activity in a predetermined time period.

## Claims

### Claim 1

A method comprising:
via a set of machine instructions:
representing an activity of a project as a node of a graph;
representing a relationship of the project as an edge of the graph;
utilizing a normal distribution and associated p-values to obtain a first probability of completing the activity in a first predetermined time period; and
rendering a first user interface that indicates the first probability of completing the activity in the first predetermined time period.

### Claim 2 (depends on 1)

The method of claim 1, further comprising:
utilizing the normal distribution and associated p-values to obtain a second probability of completing the activity within a specified budget.

### Claim 3 (depends on 1)

The method of claim 1, further comprising:
defining one or more relationships between predecessor and successor activities on the graph comprising at least one of:
Finish-to-Start;
Start-to-Start;
Finish-to-Finish; and
Start-to-Finish.

### Claim 4 (depends on 1)

The method of claim 1, further comprising:
utilizing at least one of a lag and a lead via the machine instructions.

### Claim 5 (depends on 1)

The method of claim 1, further comprising:
rendering a second user interface showing a critical path for the project.

### Claim 6 (depends on 1)

The method of claim 1, further comprising:
rendering a second user interface showing a level of risk for the project.

### Claim 7 (depends on 1)

The method of claim 1, further comprising:
rendering a second user interface showing a probability of achieving a milestone for the project.

### Claim 8 (depends on 1)

The method of claim 1, further comprising:
rendering a second user interface showing a probability of achieving budget target for the project.

### Claim 9 (depends on 1)

The method of claim 1, further comprising:
recommending a resource allocation for the project.

### Claim 10 (depends on 1)

The method of claim 1, further comprising:
automatically determining a schedule risk at a predetermined confidence level.

### Claim 11 (depends on 1)

The method of claim 1, further comprising:
automatically determining a cost risk at a predetermined confidence level.

### Claim 12 (depends on 1)

The method of claim 1, further comprising:
plotting a chart indicative of uncertainty levels along a path of the project.

### Claim 13 (depends on 1)

The method of claim 1, wherein:
the set of machine instructions is executed on a Neo4j graph database management system.

### Claim 14 (depends on 1)

The method of claim 1, wherein:
a second probability of completing the activity of the project in a second predetermined time period is determined responsive to machine learning.

### Claim 15 (depends on 1)

The method of claim 1, wherein:
the node of the graph is an interactive node via which the activity of the project is controlled.

### Claim 16 (depends on 1)

The method of claim 1, wherein:
the first user interface is rendered responsive to at least one of:
betweenness centrality;
graph traversals;
pattern matching;
distance and path algorithms;
closeness;
node importance; and
historical graph evolution tracking; and prediction.

### Claim 17 (depends on 1)

The method of claim 1, further comprising:
automatically determining a joint schedule risk and a cost risk at a predetermined joint confidence level.

### Claim 18 (depends on 1)

The method of claim 1, further comprising:
changing or defining a relationship type to adjust a schedule of the project.

### Claim 19 (depends on 1)

The method of claim 1, further comprising:
updating a schedule of the project over time.

### Claim 20 (depends on 1)

The method of claim 1, further comprising:
rendering an indicator of project performance via Earned Value Management based on computations derived from a PERT methodology.

### Claim 21 (depends on 1)

The method of claim 1, further comprising:
representing resources as nodes to allow renderings and analysis both labor and non-labor resource allocation.

### Claim 22 (depends on 1)

The method of claim 1, further comprising:
rendering a schedule of the project, the schedule based upon forward and backward passes between graph nodes to determine an: Early Start, Early Finish, Late Start, Late Finish, Total Float (Slack), and Free Float.

### Claim 23 (depends on 1)

The method of claim 1, further comprising:
conducting quality checks or evaluating a “health” of a schedule of the project based on user-defined criteria.