# US 2023/0392341 A1 · Underwater concrete block structure and construction method therefor

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2023/0392341 A1
- Document ID: US20230392341A1
- Status: Published application
- Kind: A1
- Application number: 18/235,143
- Filed: 2023-08-17
- Published: 2023-12-07
- Earliest claimed: 2021-02-25
- Assignees: Yujoo Co., Ltd.
- Applicants: Yujoo Co., Ltd.
- Inventors: Sangki KIM
- Web page: https://patentgrep.com/patent/US20230392341A1

## CPC

- E02D 25/00: Joining caissons, sinkers, or other units to each other under water
- E02D 27/52: Submerged foundations {, i.e. submerged in open water (E02D27/12 - E02D27/24 take precedence)}
- E02B 3/06: Moles; Piers; Quays; Quay walls; Groynes; Breakwaters {; Wave dissipating walls; Quay equipment}
- E02D 2250/0061: for working underwater
- E02D 2600/20: comprising details of connection between elements
- Y02A 10/11: Hard structures, e.g. dams, dykes or breakwaters
- E02D: FOUNDATIONS; EXCAVATIONS; EMBANKMENTS (specially adapted for hydraulic engineering E02B); UNDERGROUND OR UNDERWATER STRUCTURES {(tunnels, tunnelling, mining E21)}
- E02B: HYDRAULIC ENGINEERING (ship-lifting E02C; dredging E02F)
- Y02A: TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE

## Abstract

A constructing method of an underwater concrete block structure, includes: a first concrete block fabrication step, a guide pole installation step, a first concrete block installation step, a second concrete block fabrication step, a second concrete block installation step, a drainage step, a guide pole removal step, and a concrete column formation step. A concrete column and a first concrete block is firmly coupled to each other via a column rebar assembly.

## Claims

### Claim 1

A method of constructing an underwater concrete block structure, the method comprising:
a first concrete block fabrication step of fabricating a first concrete block comprising a first concrete block body, a column rebar assembly which extends vertically upward from a lower end part thereof connected to the inside of the first concrete block body and protrudes upward from the upper surface of the first concrete block body, and a first watertight packing disposed on the upper surface of the first concrete block body in a form surrounding the column rebar assembly;
a guide pole installation step of installing a guide pole on the first concrete block after the first concrete block fabrication step, wherein the guide pole comprises a guide pipe having a shape of a pipe extending vertically to insert the column rebar assembly along the inside of the guide pipe and a upper insertion guide part formed at the upper end of the guide pipe and having an upwardly tapered shape;
a first concrete block installation step of installing the first concrete block underwater after the guide pole installation step;
a second concrete block fabrication step of fabricating a second concrete block comprising a second concrete block body having a through hole extending vertically;
a second concrete block installation step of installing the second concrete block such that a concrete block assembly is formed by installing the second concrete block on the first concrete block so that the guide pole is inserted into the through hole of the second concrete block after the second concrete block fabrication step and the first concrete block installation step, wherein a concrete-column through hole having a closed lower end is formed in the concrete block assembly by the through hole of the second concrete block and the first concrete block, and the first watertight packing is located between the first concrete block and the second concrete block to prevent water from being introduced into the concrete-column through hole from the outside;
a drainage step of removing water contained inside the concrete-column through hole after the second concrete block installation step;
a guide pole removal step of removing the guide pole after the drainage step; and
a concrete column formation step of forming a concrete column by pouring concrete into the concrete-column through hole after the drainage step, wherein the concrete column comprises the column rebar assembly and the poured concrete integrated with each other and is coupled to the first concrete block body via the column rebar assembly.

### Claim 2 (depends on 1)

The method of claim 1, wherein the column rebar assembly has a length to pass through the concrete-column through hole and protrudes from the top of the concrete-column through hole, and a cap concrete formation step of forming a cap concrete on the concrete block assembly after the concrete column formation step so that an upper end of the column rebar assembly is connected to the inside of the cap concrete is comprised.

### Claim 3 (depends on 1)

The method of claim 1, wherein a block-side coupler is provided in the first concrete block body in a form surrounding the column rebar assembly,
the guide pole comprises a pipe-side coupler at a lower end part of the guide pipe to be coupled detachably to the block-side coupler and a third watertight packing provided on the lower end part of the guide pipe to prevent water from being introduced into the inside of the guide pipe from the outside by being in close contact with the first concrete block when the pipe-side coupler of the guide pipe is coupled to the block-side coupler, and
at the guide pole installation step, the block-side coupler of the guide pole is coupled detachably to the block-side coupler of the first concrete block.

### Claim 4 (depends on 3)

The method of claim 3, wherein a drain pipe of which a lower end communicates with the outside through a drain hole formed in the lower end part of the guide pipe extends vertically inside the guide pole,
the water contained inside the concrete-column hole is removed using the drain pipe at the drainage step, and
the guide pole removal step is performed after the drainage step.

### Claim 5 (depends on 1)

The method of claim 1, wherein a second watertight packing is disposed on an upper surface of the second concrete block body in a form surrounding the through hole; and
at the second concrete block installation step, a plurality of second concrete blocks are installed in multiple layers on the first concrete block, and the second watertight packing is located between the second concrete blocks installed to be vertically adjacent to each other so that water is prevented from being introduced into the concrete-column through hole from the outside.

### Claim 6

An underwater concrete block structure comprising:
a concrete block assembly comprising: a first concrete block having a first concrete block body, a column rebar assembly which extends vertically upward from a lower end part thereof connected to the inside of the first concrete block body and protrudes upward from the upper surface of the first concrete block body, and a block-side coupler provided in the first concrete block body in a form surrounding the column rebar assembly,
a second concrete block having a second concrete block body with a through hole extending vertically and installed on the first concrete block so that the column rebar assembly of the first concrete block is inserted into the through hole of the second concrete block,
a concrete-column through hole which has a closed lower end and is formed by the through hole of the second concrete block and the first concrete block, and
a first watertight packing which is located between the first concrete block and the second concrete block and prevents water from being introduced into the concrete-column through hole from the outside; and
a concrete column formed in such a manner that concrete poured into the concrete-column through hole is integrated with the column rebar assembly and coupled to the first concrete block body via the column rebar assembly.

### Claim 7 (depends on 6)

The underwater concrete block structure of claim 6, wherein the column rebar assembly has a length to pass through the concrete-column through hole and protrudes from the top of the concrete-column through hole, a cap concrete is formed on the concrete block assembly, and an upper end of the column rebar assembly is connected to the inside of the cap concrete.

### Claim 8 (depends on 6)

The underwater concrete block structure of claim 6, wherein the concrete block assembly comprises a plurality of second concrete blocks which are installed in multiple layers on the first concrete block and the second watertight packing which is located between the second concrete blocks installed to be vertically adjacent to each other so that water is prevented from being introduced into the concrete-column through hole from the outside.