- Number: US 2023/0390939 A1
- Document ID: US20230390939A1
- Status: Published application
- Kind: A1
- Application number: 18/034,261
- Filed: 2021-10-19
- Published: 2023-12-07
- Earliest claimed: 2020-10-30
- Assignees: Kawasaki Jukogyo Kabushiki Kaisha
- Applicants: Kawasaki Jukogyo Kabushiki Kaisha
- Inventors: Yasuhiko HASHIMOTO
- Web page: https://patentgrep.com/patent/US20230390939A1

## CPC

- B25J 11/008: {Manipulators for service tasks}
- B25J 5/00: Manipulators mounted on wheels or on carriages (B25J1/00 takes precedence; program-controlled manipulators B25J9/00)
- B25J 9/0084: {comprising a plurality of manipulators}
- B25J 9/0087: {Dual arms (double SCARA arms B25J9/043)}
- B64D 1/02: Dropping, ejecting, or releasing articles (jettisonable fuel reservoirs B64D37/12)
- B64D 1/22: Taking-up articles from earth's surface
- B64U 10/17: Helicopters (flying platforms B64U10/13)
- B64U 20/00: Constructional aspects of UAVs (of lift-producing means B64U30/00)
- H02G 1/02: for overhead lines or cables
- B25J 13/06: Control stands, e.g. consoles, switchboards
- B64C 27/06: with single rotor
- B64U 2101/30: for imaging, photography or videography
- B64U 2101/60: for transporting passengers; for transporting goods other than weapons
- B64U 2101/67: the UAVs comprising tethers for lowering the goods
- B25J: MANIPULATORS; CHAMBERS PROVIDED WITH MANIPULATION DEVICES ({manipulators specially adapted for use in surgery A61B34/70; manipulators used in cleaning hollow articles B08B9/04}; manipulators associated with rolling mills B21B39/20; manipulators associated with forging machines B21J13/10; {manipulators associated with picking-up and placing mechanisms B23P19/007}; means for holding wheels or parts thereof B60B30/00; {vehicles with ground-engaging propulsion means, e.g. walking members B62D57/02, B62D57/032; devices for picking-up and depositing articles or materials between conveyors B65G47/90, B65G47/91; manipulators with gripping or holding means for transferring packages B65H67/065}; cranes B66C; {manipulators used in the protection or supervision of pipe-line installations F17D5/00; walking equipment adapted for nuclear steam-generators F22B37/006}; manipulators specially adapted for, or associated with, nuclear reactors G21C; {apparatus used for handling wafers during manufacture or treatment of semiconductor H10P72/50})
- B64D: EQUIPMENT FOR FITTING IN OR TO AIRCRAFT; FLIGHT SUITS; PARACHUTES; ARRANGEMENT OR MOUNTING OF POWER PLANTS OR PROPULSION TRANSMISSIONS IN AIRCRAFT
- B64U: UNMANNED AERIAL VEHICLES [UAV]; EQUIPMENT THEREFOR
- H02G: INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- B64C: AEROPLANES; HELICOPTERS

## Abstract

A work system which performs a work to a structure, and includes an aircraft, and a robot which performs the work to the structure. After the aircraft conveys the robot to the structure while holding the robot, the aircraft releases the robot after the aircraft lowers the robot onto the structure. The robot is released from the aircraft, and then performs the work to the structure.

## Claims

### Claim 1

A work system that performs a work to a structure, comprising:
an aircraft; and
a robot that performs the work to the structure,
wherein, after the aircraft conveys the robot to the structure while holding the robot, the aircraft releases the robot after the aircraft lowers the robot onto the structure, and
wherein the robot is released from the aircraft, and then performs the work to the structure.

### Claim 2 (depends on 1)

The work system of claim 1, wherein the robot includes a robot body and a fixing device that fixes the robot body to the structure, and
wherein the aircraft releases the robot on the structure after the robot is fixed to the structure by the fixing device.

### Claim 3 (depends on 2)

The work system of claim 2, wherein the robot body includes a base, a first robotic arm attached at a base-end part thereof to the base, and a first robot hand that is provided to a tip end of the first robotic arm and performs the work to the structure, and
wherein the fixing device is provided to the base.

### Claim 4 (depends on 2)

The work system of claim 2, wherein the fixing device includes a second robotic arm attached at a base-end part thereof to the base, and a second robot hand provided to a tip end of the second robotic arm, and
wherein the fixing device fixes the robot body to the structure by holding a part of the structure by the second robot hand.

### Claim 5 (depends on 3)

The work system of claim 3, wherein the robot is movable on the structure by repeating operation in which, after the robot holds a part of the structure by the first robot hand, the robot changes a posture of the first robotic arm and holds another part of the structure by the first robot hand.

### Claim 6 (depends on 3)

The work system of claim 3, wherein, by the base being constituted as a travel cart, the robot is travelable on the structure by itself.

### Claim 7 (depends on 1)

The work system of claim 1, further comprising an interface for an operator to remotely operate the aircraft and the robot,
wherein the operator remotely performs, using the interface, at least one of that the aircraft lowers the robot onto the structure and that the robot performs the work to the structure.

### Claim 8 (depends on 7)

The work system of claim 7, wherein the robot includes a plurality of robots, and
wherein the operator remotely performs, using the interface, that the plurality of robots perform the work to the structure, while switching the robot to be remotely operated among the plurality of robots.

### Claim 9 (depends on 1)

The work system of claim 1, wherein the aircraft includes a storage device that stores the robot, and conveys the robot to the structure while storing the robot inside the storage device.

### Claim 10 (depends on 1)

The work system of claim 1, wherein the aircraft is a drone.

### Claim 11 (depends on 1)

The work system of claim 1, wherein the robot includes three assembly units comprised of the first robotic arm, the base, and a mobile part that moves the robot, and
wherein the first robotic arm is attached to an upper surface of the base, and the mobile part is attached to a side surface of the base.

### Claim 12 (depends on 11)

The work system of claim 11, wherein the base is configured so that:
a third robotic arm including a torso part extending perpendicularly from an upper surface of the base, and the first robotic arm that is directly attached to the upper surface of the base and is extendable near and along the upper surface of the base, are selectively attached to the upper surface, and
a traveling part that propels the robot, and the second robotic arm that makes the robot walk at a high location, are selectively attached to the side surface.

### Claim 13

A work method that performs a work to a structure, comprising the steps of:
a first step in which an aircraft and a robot that performs the work to the structure are prepared;
a second step in which, after performing the first step, the robot is held by the aircraft;
a third step in which, after performing the first and second steps, the robot is conveyed to the structure by the aircraft;
a fourth step in which, after performing the first to third steps, the robot is lowered onto the structure from the aircraft;
a fifth step in which, after performing the first to fourth steps, the robot is released from the aircraft; and
a sixth step in which, after performing the first to fifth steps, the work is performed to the structure by the robot.