# US 2023/0358473 A1 · Method for heating a blank and heating system

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2023/0358473 A1
- Document ID: US20230358473A1
- Status: Published application
- Kind: A1
- Application number: 18/222,412
- Filed: 2023-07-14
- Published: 2023-11-09
- Earliest claimed: 2016-12-22
- Assignees: Autotech Engineering S.L.
- Applicants: Autotech Engineering, S.L.
- Inventors: Manuel LÓPEZ LAGE; Jordi CASTILLA MORENO; Daniel MERINO FERNÁNDEZ
- Web page: https://patentgrep.com/patent/US20230358473A1

## CPC

- C21D 1/34: Methods of heating (C21D1/06 takes precedence)
- F27B 9/24: being carried by a conveyor
- C21D 9/0068: {for particular articles not mentioned below}
- C21D 9/46: for sheet metals
- F27B 9/202: {Conveyor mechanisms therefor}
- F27B 9/2407: {the conveyor being constituted by rollers (roller hearth furnace)}
- F27D 3/026: {transport or conveyor rolls for furnaces; roller rails}
- C21D 2221/00: Treating localised areas of an article
- C21D: MODIFYING THE PHYSICAL STRUCTURE OF FERROUS METALS; GENERAL DEVICES FOR HEAT TREATMENT OF FERROUS OR NON-FERROUS METALS OR ALLOYS; MAKING METAL MALLEABLE, e.g. BY DECARBURISATION OR TEMPERING (surface treatment of metallic material involving at least one process provided for in class C23 and at least one process covered by this subclass C23F17/00; unidirectional solidification of eutectic materials or unidirectional demixing of eutectoid materials C30B)
- F27B: FURNACES, KILNS, OVENS OR RETORTS IN GENERAL; OPEN SINTERING OR LIKE APPARATUS
- F27D: DETAILS OR ACCESSORIES OF FURNACES, KILNS, OVENS OR RETORTS, IN SO FAR AS THEY ARE OF KINDS OCCURRING IN MORE THAN ONE KIND OF FURNACE

## Abstract

A method for manufacturing a steel component from a blank is provided. Firstly, a blank is placed in a conveyor system. Then, at least a preselected zone of the blank is preheated while the blank is retained at a predetermined preheating location. Finally, the blank is conveyed through a furnace. A preheating system for heating blanks in a production line is also provided.

## Claims

### Claim at position 1

-15. (canceled)

### Claim 16

A method for manufacturing a steel component from a blank, the method comprising:
placing a blank on a conveyor system, the blank comprising a first zone made from a first material and a second zone made from a second material, different than the first material; followed by
preheating the blank by performing a preheating process comprising (1) directing heat at the first zone and not the second zone; or (2) applying heat to both the first and second zones such that the second zone is heated to a temperature different than a temperature of the first zone; and after completion of the preheating,
conveying the preheated blank through a furnace having a furnace temperature at or above an Ac3 temperature of the first zone or the second zone of the blank for heating the blank to a temperature equal to or above the Ac3 temperature of the first zone or the second zone, and wherein the preheating comprises retaining the blank at a predetermined preheating location upstream of the furnace.

### Claim 17

A method for manufacturing a steel component from a blank, the method comprising:
placing a blank on a conveyor system, the blank comprising multiple zones, at least two of which have a different thickness or are made from a different material;
preheating the blank by a preheating system by performing a preheating process comprising (1) directing heat to at least one of the zones and not to at least one other zone; or (2) heating at least two zones to different temperatures, the temperatures being below an Ac3 temperature of the at least two zones of the blank; and
conveying the preheated blank through a furnace, positioned downstream from the preheating system and having a furnace temperature at or above the Ac3 temperature of the at least two zones of the blank for heating the blank to a temperature equal to or above the Ac3 temperature of the at least two zones.