# US 2023/0332338 A1 · Method of power control for a textile machine, power control unit and spinning machine

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2023/0332338 A1
- Document ID: US20230332338A1
- Status: Published application
- Kind: A1
- Application number: 18/298,609
- Filed: 2023-04-11
- Published: 2023-10-19
- Earliest claimed: 2022-04-13
- Assignees: Saurer Spinning Solutions GmbH & Co. KG
- Applicants: Saurer Spinning Solutions GmbH & Co. KG
- Inventors: Michael SPITZER; Robert GEISLER
- Web page: https://patentgrep.com/patent/US20230332338A1

## CPC

- D01H 4/44: in rotor spinning
- D01H 13/32: Counting, measuring, recording or registering devices
- D01H 4/14: Rotor driven by an electric motor
- G05B 19/4155: characterised by program execution, i.e. part program or machine function execution, e.g. selection of a program
- H02J 3/003: {Load forecast, e.g. methods or systems for forecasting future load demand}
- G05B 2219/45196: Textile, embroidery, stitching machine
- D01H: SPINNING OR TWISTING (twisting oakum D01G35/00; crimping or curling of fibres, filaments, or yarns D02G1/00)
- G05B: CONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS (systems for controlling or regulating non-electric variables G05D; systems for regulating electric or magnetic variables G05F; control devices or systems insofar as characterised by mechanical features only G05G)
- H02J: ELECTRIC POWER NETWORKS; CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY

## Abstract

A method of power control for a textile machine with simultaneously operated workstations and with at least one power supply unit for jointly powering the workstations, a power control unit and a spinning machine. The method enables rapid run-up of the textile machine and minimise delays and downtimes. The method comprises steps that initially involve determining the required electrical power output of each of the workstations, then determining the simultaneously executable operations on the basis of the determined required power and a maximum power output of the power supply unit. Optimised operating data of the several workstations powered jointly by a power supply unit can be obtained in order to make the best possible use of the maximum power output of a power supply unit, wherein the required electrical power output and/or the simultaneously executable operations are determined, and/or optimised operating data is obtained taking into consideration current batch data.

## Claims

### Claim at position 1

1-12. (canceled)

### Claim 13

A method of power control for a textile machine with a plurality of simultaneously operated workstations and with at least one power supply unit for joint power supply of the plurality of simultaneously operated workstations, the method comprising:
determining of a required electrical power of each of the plurality of simultaneously operated workstations;
determining simultaneously executable operations based on the determined required electrical power and a maximum power output of the at least one power supply unit; and
obtaining optimised operating data of the plurality of simultaneously operated workstations powered jointly by the at least one power supply unit in order to make a best possible use of the maximum power output of the at least one power supply unit;
wherein the step of determining of the required electrical power and/or the step of obtaining optimised operating data is obtained taking into consideration current batch data.

### Claim 14 (depends on 13)

The method of power control according to claim 13, wherein the current batch data includes a nature, composition and/or dimensions of material used to manufacture the textile machine, a speed of a drive motor and/or of a spinning rotor and/or an acceleration of the drive motor when each of the plurality of simultaneously operated workstations start up.

### Claim 15 (depends on 13)

The method of power control according to claim 13, wherein a required electrical power output of each of the plurality of simultaneously operated workstations is determined by a test start and/or test operation of each of the plurality of simultaneously operated workstations with the current batch data.

### Claim 16 (depends on 13)

The method of power control according to claim 13, wherein the required electrical power of each of the plurality of simultaneously operated workstations is determined by monitoring a run-up and/or regular operation of a respective one of the plurality of simultaneously operated workstations workstation with the current batch data.

### Claim 17 (depends on 13)

The method of power control according to claim 13, wherein the optimised operating data is stored in a database linked to the current batch data in order to enable the optimised operating data to be obtained from the database.

### Claim 18 (depends on 13)

The method of power control according to claim 13, wherein a power forecast is prepared for a planned operating sequence based on the current batch data and/or respective machine settings as well as data on a required electrical power stored in a database, and in a context of obtaining optimised operating data the power forecast is checked to determine whether the at least one power supply unit is able to provide sufficient power in order to allow a further operation at the same time.

### Claim 19 (depends on 13)

The method of power control according to claim 13, wherein the required electrical power of each of the plurality of simultaneously operated workstations is determined on a basis of data for similar batch data stored in a database.

### Claim 20 (depends on 18)

The method of power control according to claim 18, further including optimizing the power control by recording an actual electrical power output of the at least one power supply unit during operation of the textile machine with the optimised operating data and subsequently by a comparison with the determined required electrical power and/or with a result of the power forecast, as well as by storing correction data in a database and/or correcting further optimised operating data when the further optimised operating data is obtained.

### Claim 21 (depends on 13)

The method of power control according to claim 13, wherein, during operation of the textile machine with the optimised operating data, still available power output of the at least one power supply unit is drawn and subsequently taken into account in further optimisation of operating parameters, wherein the further optimisation of operating parameters is checked whether a further workstation is permitted to be run up and/or can be operated.

### Claim 22 (depends on 13)

The method of power control according to claim 13, wherein, during operation of the textile machine with the optimised operating data, actual power consumption is continuously monitored and if a value of a power forecast and/or of a set maximum power output is exceeded, the optimised operating data is adjusted and/or at least one of the plurality of simultaneously operated workstations is slowed or shut down.

### Claim 23

A power control unit for a textile machine with a plurality of simultaneously operated workstations and with at least one power supply unit for joint power supply of the plurality of simultaneously operated workstations, wherein the power control unit:
determines a required electrical power of each of the plurality of simultaneously operated workstations;
determines a simultaneously executable operations based on the determined required power as well as on a maximum power output of the at least one power supply unit; and
obtains optimised operating data of the plurality of simultaneously operated workstations powered jointly by the at least one power supply unit in order to make a best possible use of the maximum power output of the at least one power supply unit;
wherein the required electrical power is determined and/or optimised operating data is obtained taking into consideration current batch data.

### Claim 24 (depends on 23)

A spinning machine with the power control unit according to claim 23, wherein each of the plurality of simultaneously operated workstations each of which has a spinning rotor, the at least one power supply unit jointly powers the plurality of simultaneously operated workstations, the at least one power control unit is provided such that the at least one power control unit determines the required electrical power of each of the plurality of simultaneously operated workstations, determines the spinning rotors to be simultaneously run up and/or operated on a basis of the determined required power as well as of a maximum power output of the at least one power supply unit, and obtains optimised operating data on the plurality of simultaneously operated workstations supplied jointly by the at least one power supply unit, in order to make a best possible use of the maximum power output of the at least one power supply unit, wherein the required power is determined and/or optimised operating data is obtained taking into consideration the current batch data.