# US 2023/0297039 A1 · Production plan optimization apparatus, method, non-transitory computer readable medium storing program, and control apparatus

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2023/0297039 A1
- Document ID: US20230297039A1
- Status: Published application
- Kind: A1
- Application number: 18/017,242
- Filed: 2020-07-31
- Published: 2023-09-21
- Earliest claimed: 2020-07-31
- Assignees: NEC Corporation; NEC Platforms, Ltd.
- Applicants: NEC Corporation; NEC Platforms, Ltd.
- Inventors: Hiroshi Chishima; Masayo Kaida
- Web page: https://patentgrep.com/patent/US20230297039A1

## CPC

- G05B 13/04: involving the use of models or simulators
- G05B 19/41865: {characterised by job scheduling, process planning, material flow}
- G06Q 10/04: Forecasting or optimisation specially adapted for administrative or management purposes, e.g. linear programming or "cutting stock problem" (market predictions or forecasting for commercial activities G06Q30/0202)
- G06Q 10/047: Optimisation of routes or paths, e.g. travelling salesman problem
- G06Q 50/04: Manufacturing
- G05B 2219/32064: Production change over
- G05B 2219/32254: Work sequence, alternative sequence
- Y02P 90/30: Computing systems specially adapted for manufacturing
- G05B: CONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS (systems for controlling or regulating non-electric variables G05D; systems for regulating electric or magnetic variables G05F; control devices or systems insofar as characterised by mechanical features only G05G)
- G06Q: INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- Y02P: CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS

## Abstract

A production plan optimization apparatus includes a traveling salesman problem formulation unit for formulating a problem regarding determining a sequence in which a plurality of workpieces are processed as a traveling salesman problem that satisfies a delivery date constraint based on a delivery date specified for at least one of the plurality of workpieces and a sequence constraint specified for at least one of combinations of the plurality of workpieces and also minimizes a sum of changeover times associated with switching of the workpieces and a processing sequence determination unit for calculating a solution to the traveling salesman problem, by using an annealing processing unit for searching for an optimal solution to a combinatorial optimization problem by simulated annealing or quantum annealing, and determining the sequence in which the plurality of workpieces are processed based on a result of the calculation.

## Claims

### Claim 1

A production plan optimization apparatus comprising:
at least one memory storing instructions; and
at least one processor configured to execute the instructions to:
formulate a problem regarding determining a sequence in which a plurality of workpieces are processed as a traveling salesman problem that satisfies a delivery date constraint based on a delivery date specified for at least one of the plurality of workpieces and a sequence constraint specified for at least one of combinations of the plurality of workpieces and also minimizes a sum of changeover times associated with switching of the workpieces; and
calculate a solution to the traveling salesman problem, by using annealing processing machine for searching for an optimal solution to a combinatorial optimization problem by simulated annealing or quantum annealing, and determine the sequence in which the plurality of workpieces are processed based on a result of the calculation.

### Claim 2 (depends on 1)

The production plan optimization apparatus according to claim 1, wherein
the plurality of workpieces are classified into a plurality of groups so that a combination of the workpieces having a short changeover time belongs to the same group, and
the at least one processor is further configured to execute the instructions to:
determine a sequence in which the plurality of groups are processed as a group sequence, and
formulate the problem as the traveling salesman problem that satisfies the delivery date constraint and the sequence constraint including a constraint based on the group sequence and also minimizes the sum.

### Claim 3 (depends on 1)

The production plan optimization apparatus according to claim 1, wherein
the changeover time between the workpieces belonging to different groups includes a group preparation time required for preparing production of the group to which the workpiece to be switched belongs, and
the at least one processor is further configured to execute the instructions to:
formulate a jobshop problem that minimizes a sum of waiting times in a processing apparatus when processing of the group for which the preparation for the production is made is started in the processing apparatus after the preparation for the production has been made outside the processing apparatus, and
use the annealing processing machine to calculate a solution to the jobshop problem and determine the group sequence based on a result of the calculation.

### Claim 4 (depends on 3)

The production plan optimization apparatus according to claim 3, wherein
the plurality of workpieces are selected from among a plurality of ordered workpieces, and
each of the plurality of ordered workpieces is classified into the plurality of groups, and
the at least one processor is further configured to execute the instructions to:
generate one or a plurality of blocks combining the ordered workpieces classified into the group for each of the plurality of groups;
calculate, for each of the plurality of blocks, a block processing time required for processing the ordered workpieces included in the block and set a larger one of the block processing time and a predetermined preparation time as the block processing time of the block;
formulate a knapsack problem in which a plurality of processing blocks to be processed are selected from the plurality of blocks so that a sum of the block processing times becomes large within a range of a predetermined operation time or less; and
calculate a solution to the knapsack problem by using the annealing processing machine, select the plurality of processing blocks based on a result of the calculation, and select
the plurality of ordered workpieces according to a result of the selection.

### Claim 5 (depends on 4)

The production plan optimization apparatus according to claim 4, wherein
the delivery date is set for each of the plurality of ordered workpieces, and
the at least one processor is further configured to execute the instructions to:
formulate the knapsack problem so that the ordered workpiece whose delivery date is a predetermined date is included in one of the plurality of processing blocks.

### Claim 6 (depends on 4)

The production plan optimization apparatus according to claim 4, wherein
the at least one processor is further configured to execute the instructions to:
formulate the knapsack problem so that the number of groups to which the plurality of ordered workpieces belong becomes small.

### Claim 7 (depends on 4)

The production plan optimization apparatus according to claim 4, wherein
the at least one processor is further configured to execute the instructions to:
formulate the knapsack problem so that a sum of preparation waiting times based on a difference between the predetermined preparation time and the block processing time becomes small.

### Claim 8 (depends on 4)

The production plan optimization apparatus according to claim 4, wherein
the at least one processor is further configured to execute the instructions to:
formulate the knapsack problem so that blocks with long changeover times are less likely to be selected.

### Claim 9

A production plan optimization method for causing a computer to execute:
formulating a problem regarding determining a sequence in which a plurality of workpieces are processed as a traveling salesman problem that satisfies a delivery date constraint based on a delivery date specified for at least one of the plurality of workpieces and a sequence constraint specified for at least one of combinations of the plurality of workpieces and also minimizes a sum of changeover times associated with switching of the workpieces; and
calculating a solution to the traveling salesman problem, by using annealing processing machine for searching for an optimal solution to a combinatorial optimization problem by simulated annealing or quantum annealing, and determining the sequence in which the plurality of workpieces are processed based on a result of the calculation.

### Claim 10

A non-transitory computer readable medium storing a production plan optimization program for causing a computer to execute:
processing of formulating a problem regarding determining a sequence in which a plurality of workpieces are processed as a traveling salesman problem that satisfies a delivery date constraint based on a delivery date specified for at least one of the plurality of workpieces and a sequence constraint specified for at least one of combinations of the plurality of workpieces and also minimizes a sum of changeover times associated with switching of the workpieces; and
processing of calculating a solution to the traveling salesman problem, by using annealing processing machine for searching for an optimal solution to a combinatorial optimization problem, and determining the sequence in which the plurality of workpieces are processed based on a result of the calculation.

### Claim at position 11

11-19. (canceled)