# US 2023/0274207 A1 · Work plan prediction

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2023/0274207 A1
- Document ID: US20230274207A1
- Status: Published application
- Kind: A1
- Application number: 17/652,831
- Filed: 2022-02-28
- Published: 2023-08-31
- Earliest claimed: 2022-02-28
- Assignees: BMC Software Israel Ltd
- Applicants: BMC Software Israel Ltd
- Inventors: Amos Uzan
- Web page: https://patentgrep.com/patent/US20230274207A1

## CPC

- G06Q 10/063118: {Staff planning in a project environment}
- G06Q 10/063114: {Status monitoring or status determination for a person or group}
- G06Q 10/06312: {Adjustment or analysis of established resource schedule, e.g. resource or task levelling, or dynamic rescheduling}
- G06Q: INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR

## Abstract

In some aspects, the system and techniques include collecting from a database completed tasks data for ended sprints of a team and planned tasks data for future sprints by the team. The completed tasks data for ended sprints includes actual resource capacity and completed plan data, and the planned tasks data for future sprints includes expected resource capacity and future plan data. A velocity for the team is calculated using the completed tasks data for ended sprints. A story point prediction for the future sprints by the team is calculated using the velocity and the expected resource capacity from the planned tasks data for future sprints. A visualization of the story point prediction for the future sprints by the team is generated and output to a display.

## Claims

### Claim 1

A computer-implemented method comprising:
collecting, by a computing device, from a database completed tasks data for ended sprints of a team and planned tasks data for future sprints by the team, wherein:
the completed tasks data for ended sprints includes actual resource capacity and completed plan data, and
the planned tasks data for future sprints includes expected resource capacity and future plan data;
calculating, by the computing device, a velocity for the team using the completed tasks data for ended sprints;
calculating, by the computing device, a story point prediction for the future sprints by the team using the velocity and the expected resource capacity from the planned tasks data for future sprints; and
generating and outputting to a display, by the computing device, a visualization of the story point prediction for the future sprints by the team.

### Claim 2 (depends on 1)

The computer-implemented method as in claim 1, further comprising:
receiving an input via a graphical user interface (GUI) for a number of ended sprints to include in the velocity, and
wherein calculating the velocity includes calculating, by the computing device, the velocity for the team using the input received via the GUI for the number of ended sprints.

### Claim 3 (depends on 2)

The computer-implemented method as in claim 2, further comprising:
receiving a new input via the GUI for a different number of ended sprints to include in the velocity;
updating, by the computing device, the velocity for the team using the new input received via the GUI for the different number of ended sprints;
calculating, by the computing device, an updated story point prediction for the future sprints by the team using the updated velocity and the expected resource capacity from the planned tasks data for future sprints; and
generating and outputting to the display, by the computing device, an updated visualization of the updated story point prediction for the future sprints by the team.

### Claim 4 (depends on 1)

The computer-implemented method as in claim 1, wherein calculating the velocity includes:
summing story points from the completed plan data;
summing workdays for the team from the actual resource capacity; and
dividing the summed story points by the summed workdays to arrive at the velocity for the team.

### Claim 5 (depends on 1)

The computer-implemented method as in claim 1, wherein calculating the story point prediction includes multiplying the expected resource capacity by the velocity.

### Claim 6 (depends on 1)

The computer-implemented method as in claim 1, wherein generating and outputting the visualization includes generating and outputting to the display, by the computing device, the visualization of the story point prediction and the future plan data for the future sprints by the team.

### Claim 7 (depends on 1)

The computer-implemented method as in claim 1, wherein:
the actual resource capacity and the expected resource capacity is measured in workdays; and
the completed plan data and the future planned data is measured in story points.

### Claim 8

A computer program product, the computer program product being tangibly embodied on a non-transitory computer-readable medium and including executable code that, when executed, causes a computing device to:
collect completed tasks data for ended sprints by a team and planned tasks data for future sprints by the team from a database, wherein:
the completed tasks data for ended sprints includes actual resource capacity and completed plan data, and
the planned tasks data for future sprints includes expected resource capacity and future plan data;
calculate a velocity for the team using the completed tasks data for ended sprints;
calculate a story point prediction for the future sprints by the team using the velocity and the expected resource capacity from the planned tasks data for future sprints; and
generate and output to a display a visualization of the story point prediction for the future sprints by the team.

### Claim 9 (depends on 8)

The computer program product of claim 8, further comprising executable code that, when executed, causes the computing device to:
receive an input via a graphical user interface (GUI) for a number of ended sprints to include in the velocity, and
wherein the executable code that, when executed, causes the computing device to calculate the velocity for the team using the input received via the GUI for the number of ended sprints.

### Claim 10 (depends on 9)

The computer program product of claim 9, further comprising executable code that, when executed, causes the computing device to:
receive a new input via the GUI for a different number of ended sprints to include in the velocity;
update the velocity for the team using the new input received via the GUI for the different number of ended sprints;
calculate an updated story point prediction for the future sprints by the team using the updated velocity and the expected resource capacity from the planned tasks data for future sprints; and
generate and output to the display an updated visualization of the updated story point prediction for the future sprints by the team.

### Claim 11 (depends on 8)

The computer program product of claim 8, wherein the executable code that, when executed, causes the computing device to calculate the velocity includes executable code that, when executed, causes the computing device to:
sum story points from the completed plan data;
sum workdays for the team from the actual resource capacity; and
divide the summed story points by the summed workdays to arrive at the velocity for the team.

### Claim 12 (depends on 8)

The computer program product of claim 8, wherein the executable code that, when executed, causes the computing device to calculate the story point prediction by multiplying the expected resource capacity by the velocity.

### Claim 13 (depends on 8)

The computer program product of claim 8, wherein the executable code that, when executed, causes the computing device to generate and output to the display the visualization of the story point prediction and the future plan data for the future sprints by the team.

### Claim 14 (depends on 8)

The computer program product of claim 8, wherein:
the actual resource capacity and the expected resource capacity is measured in workdays; and
the completed plan data and the future planned data is measured in story points.

### Claim 15

A system comprising:
at least one processor; and
a non-transitory computer-readable medium comprising instructions that, when executed by the at least one processor, cause the system to:
collect from a database completed tasks data for ended sprints by a team and planned tasks data for future sprints by the team, wherein:
the completed tasks data for ended sprints includes actual resource capacity and completed plan data, and
the planned tasks data for future sprints includes expected resource capacity and future plan data;
calculate a velocity for the team using the completed tasks data for ended sprints;
calculate a story point prediction for the future sprints by the team using the velocity and the expected resource capacity from the planned tasks data for future sprints; and
generate and output to a display a visualization of the story point prediction for the future sprints by the team.

### Claim 16 (depends on 15)

The system of claim 15, further comprising instructions that, when executed by the at least one processor, cause the system to:
receive an input via a graphical user interface (GUI) for a number of ended sprints to include in the velocity, and
wherein the instructions that, when executed by the at least one processor, cause the system to calculate the velocity for the team using the input received via the GUI for the number of ended sprints.

### Claim 17 (depends on 16)

The system of claim 16, further comprising instructions that, when executed by the at least one processor, cause the system to:
receive a new input via the GUI for a different number of ended sprints to include in the velocity;
update the velocity for the team using the new input received via the GUI for the different number of ended sprints;
calculate an updated story point prediction for the future sprints by the team using the updated velocity and the expected resource capacity from the planned tasks data for future sprints; and
generate and output to the display an updated visualization of the updated story point prediction for the future sprints by the team.

### Claim 18 (depends on 15)

The system of claim 15, wherein the instructions that, when executed by the at least one processor calculate the velocity by causing the system to:
sum story points from the completed plan data;
sum workdays for the team from the actual resource capacity; and
divide the summed story points by the summed workdays to arrive at the velocity for the team.

### Claim 19 (depends on 15)

The system of claim 15, wherein the instructions that, when executed by the at least one processor calculate the story point prediction by causing the system to multiply the expected resource capacity by the velocity.

### Claim 20 (depends on 15)

The system of claim 15, wherein the instructions that, when executed by the at least one processor generate and output to the display the visualization of the story point prediction and the future plan data for the future sprints by the team.

### Claim 21 (depends on 15)

The system of claim 15, wherein:
the actual resource capacity and the expected resource capacity is measured in workdays; and