# US 2023/0146873 A1 · Method for monitoring physical downlink control channel, user terminal and readable storage medium

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2023/0146873 A1
- Document ID: US20230146873A1
- Status: Published application
- Kind: A1
- Application number: 17/914,975
- Filed: 2021-03-24
- Published: 2023-05-11
- Earliest claimed: 2020-03-27
- Assignees: Spreadtrum Communications (Shanghai) Co., Ltd.
- Applicants: Spreadtrum Communications (Shanghai) Co., Ltd.
- Inventors: Sicong ZHAO; Xinghang GAO
- Web page: https://patentgrep.com/patent/US20230146873A1

## CPC

- H04W 52/0216: {using a pre-established activity schedule, e.g. traffic indication frame}
- H04W 72/23: in the downlink direction of a wireless link, i.e. towards a terminal
- H04L 5/0053: {Allocation of signalling, i.e. of overhead other than pilot signals}
- H04L 5/0092: {Indication of how the channel is divided}
- H04L 27/26025: {Numerology, i.e. varying one or more of symbol duration, subcarrier spacing, Fourier transform size, sampling rate or down-clocking (allocating sub-channels of the transmission path H04L5/003)}
- H04W 24/08: Testing, {supervising or monitoring} using real traffic
- H04W 72/12: Wireless traffic scheduling
- H04W 72/20: Control channels or signalling for resource management
- H04L 5/0007: {the frequencies being orthogonal, e.g. OFDM(A) or DMT}
- Y02D 30/70: in wireless communication networks
- H04W: WIRELESS COMMUNICATION NETWORKS (broadcast communication H04H; communication systems using wireless links for non-selective communication, e.g. wireless extensions H04M1/72)
- H04L: TRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION (arrangements common to telegraphic and telephonic communication H04M)
- Y02D: CLIMATE CHANGE MITIGATION TECHNOLOGIES IN INFORMATION AND COMMUNICATION TECHNOLOGIES [ICT], I.E. INFORMATION AND COMMUNICATION TECHNOLOGIES AIMING AT THE REDUCTION OF THEIR OWN ENERGY USE

## Abstract

A physical downlink control channel monitoring method, a user terminal and a readable storage medium. The method comprises: receiving downlink control information in an nth slot; and when the downlink control information comprises switching indication information of a physical downlink control channel monitoring state, starting from an (n+X)th slot, executing a physical downlink control channel monitoring behavior according to a switched physical downlink control channel monitoring state, wherein n and X are both integers and X≥1. By using the solution, the switching of a monitoring behavior of a physical downlink control channel during scheduling of the same bandwidth part can be realized.

## Claims

### Claim 1

A method for monitoring a physical downlink control channel, comprising:
receiving downlink control information in an n-th time slot; and
performing physical downlink control channel monitoring from a (n+X)-th time slot, based on a switched physical downlink control channel monitoring state, in a case that the downlink control information comprises switching indication information on a physical downlink control channel monitoring state; wherein n and X are both integers, and X is greater than or equal to 1.

### Claim 2 (depends on 1)

The method for monitoring the physical downlink control channel according to claim 1, wherein the value of X is determined based on a value of a minimum available scheduling delay activated and applied in a currently active downlink bandwidth part.

### Claim 3 (depends on 2)

The method for monitoring the physical downlink control channel according to claim 2, wherein the value of X is determined based on the value of the minimum available scheduling delay activated in the currently active downlink bandwidth part by:
in a case that the minimum available scheduling delay is greater than 0, the value of X is the minimum available scheduling delay, or a greater of the minimum available scheduling delay and Z, wherein a value of Z corresponds to a subcarrier spacing of the currently active downlink bandwidth part where the downlink control information is located; and
in a case that the minimum available scheduling delay is equal to 0, the value of X is 1 or Z.

### Claim 4 (depends on 3)

The method for monitoring the physical downlink control channel according to claim 3, wherein in a case that the subcarrier spacing of the currently active downlink bandwidth part where the downlink control information is located is 15 Khz or 30 Khz, the value of Z is 1; and in a case that the subcarrier spacing of the currently active downlink bandwidth part where the downlink control information is located is 60 Khz or 120 Khz, the value of Z is 2.

### Claim 5 (depends on 1)

The method for monitoring the physical downlink control channel according to claim 1, wherein the value of X is a fixed value.

### Claim 6 (depends on 5)

The method for monitoring the physical downlink control channel according to claim 5, wherein in a case that X is equal to 1, a skipping duration of the physical downlink control channel monitoring indicated in the downlink control information is greater than a minimum available scheduling delay.

### Claim 7 (depends on 1)

The method for monitoring the physical downlink control channel according to claim 1, wherein the switching indication information on the monitoring state of the physical downlink control channel comprises at least one of:
skipping all or part of the physical downlink control channel monitoring in a time period; and
switching a parameter of a physical downlink control channel search space.

### Claim 8 (depends on 7)

The method for monitoring the physical downlink control channel according to claim 7, wherein the skipping all or part of the physical downlink control channel monitoring in the time period comprises:
during a current discontinuous reception periodicity, not monitoring the physical downlink control channel.

### Claim 9

A user equipment, comprising:
a memory; and
a processor,
wherein the memory stores a computer program executable on the processor, wherein the computer program, when being executed by the processor, causes the processor to:
receive downlink control information in an n-th time slot; and
perform physical downlink control channel monitoring from a (n+X)-th time slot, based on a switched physical downlink control channel monitoring state, in a case that the downlink control information comprises switching indication information on a physical downlink control channel monitoring state; wherein n and X are both integers, and X is greater than or equal to 1.

### Claim 10 (depends on 9)

The user equipment according to claim 9, wherein the value of X is determined based on a value of a minimum available scheduling delay activated and applied in a currently active downlink bandwidth part.

### Claim 11 (depends on 10)

The user equipment according to claim 10, wherein in a case that the minimum available scheduling delay is greater than 0, the value of X is the minimum available scheduling delay, or a greater of the minimum available scheduling delay and Z, wherein a value of Z corresponds to a subcarrier spacing of the currently active downlink bandwidth part where the downlink control information is located, and
in a case that the minimum available scheduling delay is equal to 0, the value of X is 1 or Z.

### Claim 12 (depends on 11)

The user equipment according to claim 11, wherein in a case that the subcarrier spacing of the currently active downlink bandwidth part where the downlink control information is located is 15 Khz or 30 Khz, the value of Z is 1; and in a case that the subcarrier spacing of the currently active downlink bandwidth part where the downlink control information is located is 60 Khz or 120 Khz, the value of Z is 2.

### Claim 13 (depends on 9)

The user equipment according to claim 9, wherein the value of X is a fixed value.

### Claim 14 (depends on 13)

The user equipment according to claim 13, wherein in a case that X is equal to 1, a skipping duration of the physical downlink control channel monitoring indicated in the downlink control information is greater than a minimum available scheduling delay.

### Claim 15

A non-transitory computer readable storage medium having a computer program stored thereon, wherein the computer program, when being executed by a processor, causes the processor to:
receive downlink control information in an n-th time slot; and
perform physical downlink control channel monitoring from a (n+X)-th time slot, based on a switched physical downlink control channel monitoring state, in a case that the downlink control information comprises switching indication information on a physical downlink control channel monitoring state; wherein n and X are both integers, and X is greater than or equal to 1.

### Claim 16

(canceled)

### Claim 17 (depends on 15)

The non-transitory computer readable storage medium according to claim 15, wherein the value of X is determined based on a value of a minimum available scheduling delay activated and applied in a currently active downlink bandwidth part.

### Claim 18 (depends on 17)

The non-transitory computer readable storage medium according to claim 17, wherein in a case that the minimum available scheduling delay is greater than 0, the value of X is the minimum available scheduling delay, or a greater of the minimum available scheduling delay and Z, wherein a value of Z corresponds to a subcarrier spacing of the currently active downlink bandwidth part where the downlink control information is located, and
in a case that the minimum available scheduling delay is equal to 0, the value of X is 1 or Z.

### Claim 19 (depends on 18)

The non-transitory computer readable storage medium according to claim 18, wherein in a case that the subcarrier spacing of the currently active downlink bandwidth part where the downlink control information is located is 15 Khz or 30 Khz, the value of Z is 1; and in a case that the subcarrier spacing of the currently active downlink bandwidth part where the downlink control information is located is 60 Khz or 120 Khz, the value of Z is 2.

### Claim 20 (depends on 15)

The non-transitory computer readable storage medium according to claim 15, wherein the value of X is a fixed value.

### Claim 21 (depends on 20)

The non-transitory computer readable storage medium according to claim 20, wherein in a case that X is equal to 1, a skipping duration of the physical downlink control channel monitoring indicated in the downlink control information is greater than a minimum available scheduling delay.