# US 2023/0069168 A1 · Systems and methods for operating an islanded distribution substation using inverter power generation

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2023/0069168 A1
- Document ID: US20230069168A1
- Status: Published application
- Kind: A1
- Application number: 17/806,318
- Filed: 2022-06-10
- Published: 2023-03-02
- Earliest claimed: 2021-09-01
- Assignees: Schweitzer Engineering Laboratories, Inc.
- Applicants: Schweitzer Engineering Laboratories, Inc.
- Inventors: Scott M. Manson; Jorge Fernando Calero; Angelos Kokkinis
- Web page: https://patentgrep.com/patent/US20230069168A1

## CPC

- H02H 3/006: {Calibration or setting of parameters}
- H02H 7/22: for distribution gear, e.g. bus-bar systems; for switching devices {(detecting mechanical or electrical defects in gas-insulated switchgears H02B13/065)}
- H02H 1/0007: {concerning the detecting means (in general G01R or other subclasses of G01; reed switches H01H71/2445)}
- H02H 7/28: for meshed systems
- H02J 3/28: Arrangements for balancing of the load in networks by storage of energy
- H02J 3/388: Arrangements for the handling of islanding, e.g. for disconnection or for avoiding the disconnection of power
- H02J 11/00: Circuit arrangements for providing service supply to auxiliaries of stations in which electric power is generated, distributed or converted
- H02H: EMERGENCY PROTECTIVE CIRCUIT ARRANGEMENTS (indicating or signalling undesired working conditions G01R, e.g. G01R31/00, G08B; locating faults along lines G01R31/08; emergency protective devices H01H)
- H02J: ELECTRIC POWER NETWORKS; CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY

## Abstract

Systems and methods are described herein to accommodate different settings associated with a converter-based electric power generator and an inverter-based electric power generator for electric power generation within an electric power delivery system. The electric power delivery system may provide electric power generated by a bulk electric system to the loads via distributed substations using a first operating frequency. Moreover, the distributed substations may include inverter-based electric power generators to supply the electric power demand of downstream loads in an islanded configuration. That said, the inverter-based electric power generators may supply the electric power using a second frequency that is higher than the first frequency. Protective systems, positioned downstream from the distributed substations, may use different settings associated with the bulk electric system or the inverter-based electric power generators based on detecting the frequency of the supplied electric power.

## Claims

### Claim 1

A fault current detector configured to:
operate in a first mode when a bulk electric system is providing electric power to a first load of an electrical delivery system using a first operating frequency, wherein the fault current detector is configured to disconnect the first load from the bulk electric system in response to determining that the first operating frequency droops below a first frequency threshold; and
operate in a second mode when an inverter is providing the electric power to the first load using a second operating frequency, wherein the fault current detector is configured to disconnect the first load from the inverter in response to determining that the second operating frequency droops below a second frequency threshold.

### Claim 2 (depends on 1)

The fault current detector of claim 1, wherein the fault current detector is configured to determine whether to operate in the first mode or the second mode based on determining whether the electric power is using the first operating frequency or the second operating frequency.

### Claim 3 (depends on 1)

The fault current detector of claim 1, wherein:
the first operating frequency is equal to or below a high frequency threshold; and
the second operating frequency is above a low frequency threshold.

### Claim 4 (depends on 3)

The fault current detector of claim 3, wherein the high frequency threshold and the low frequency threshold are between the first operating frequency and the second operating frequency.

### Claim 5 (depends on 3)

The fault current detector of claim 3, wherein fault current detector is configured to switch from operating in the first mode to operate in the second mode based on the first operating frequency increasing above the high frequency threshold.

### Claim 6 (depends on 3)

The fault current detector of claim 3, wherein fault current detector is configured to switch from operating in the second mode to operate in the first mode based on the second operating frequency decreasing below the low frequency threshold.

### Claim 7 (depends on 1)

The fault current detector of claim 1, wherein the fault current detector is associated with a first breaker and is configured to open the first breaker to disconnect the first load from the bulk electric system or the inverter.

### Claim 8 (depends on 1)

The fault current detector of claim 1, wherein the second operating frequency associated with the bulk electric system is higher than the first operating frequency.

### Claim 9 (depends on 1)

The fault current detector of claim 1, wherein the second operating frequency is greater than 60 Hertz.

### Claim 10 (depends on 1)

The fault current detector of claim 1, wherein the second operating frequency is greater than 50 Hertz.

### Claim 11

A method, comprising:
providing, via a substation of an electric power delivery system, electric power to one or more loads of the electric power delivery system;
determining, by a fault current detector of the electric power delivery system disposed downstream from the substation, that the electrical power is supplied by:
an inverter when an operating frequency of the electric power is higher than a high operating frequency threshold associated with a bulk electric system; and
the bulk electric system when the operating frequency is lower than a low operating frequency threshold associated with the inverter; and
shedding, by the fault current detector, the one or more loads based on determining:
an operating frequency below or equal to a bulk electric system frequency threshold when the electric power is supplied by the bulk electric system; and
an operating frequency below or equal to an inverter frequency threshold that is different from the bulk electric system frequency threshold when the electric power is supplied by the inverter.

### Claim 12 (depends on 11)

The method of claim 11, comprising switching, by the substation, between the inverter and the bulk electric system for providing the electric power to the one or more loads.

### Claim 13 (depends on 12)

The method of claim 12, wherein the substation is configured to switch to use the inverter for providing the electric power to the one or more loads when a breaker disconnects the bulk electrical system from the substation.

### Claim 14 (depends on 11)

The method of claim 11, comprising monitoring, by the fault current detector, the operating frequency of a distribution line of the electric power delivery system to determine that the electrical power is supplied by the inverter or determine that the electrical power is supplied by the bulk electrical system.

### Claim 15 (depends on 11)

The method of claim 11, wherein the high operating frequency threshold associated with the bulk electric system and the low operating frequency threshold associated with the inverter are between the operating frequency of the inverter and the operating frequency of the bulk electric system.

### Claim 16 (depends on 11)

The method of claim 11, wherein one or more breakers remain closed in response to determining that the operating frequency is above the inverter frequency threshold when the inverter is providing the electric power and is above the bulk electric system frequency threshold when the bulk electric system is providing the electric power.

### Claim 17

A non-transitory computer-readable medium comprising instructions, wherein the instructions, when executed by processing circuitry, are configured to cause the processing circuitry to perform operations comprising:
determining that electrical power to an electrical load is supplied by:
an inverter when an operating frequency of the electric power is higher than a high operating frequency threshold associated with a bulk electric system; and
the bulk electric system when the operating frequency is lower than a low operating frequency threshold associated with the inverter; and
shedding the electrical load based on determining:
an operating frequency of the electrical load is below or equal to a bulk electric system frequency threshold when the electric power is supplied by the bulk electric system; and
an operating frequency of the electrical load is below or equal to an inverter frequency threshold when the electric power is supplied by the inverter.

### Claim 18 (depends on 17)

The non-transitory computer-readable medium of claim 17, wherein shedding the electrical load comprises opening one or more breakers associated with the electrical load.

### Claim 19 (depends on 17)

The non-transitory computer-readable medium of claim 17, wherein the operations comprise monitoring operation frequency of a transmission line of the electric power delivery system to determine the switch to using electrical power provided by the bulk electric system.

### Claim 20 (depends on 17)

The non-transitory computer-readable medium of claim 17, wherein the low operating frequency threshold associated with the bulk electric system and the high operating frequency threshold associated with the inverter are in a range of 60 to 61 Hz.