# US 2022/0397036 A1 · Method and Apparatus for Controlling Stratum Deformation in Shield Construction Process, and Non-volatile Storage Medium

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2022/0397036 A1
- Document ID: US20220397036A1
- Status: Published application
- Kind: A1
- Application number: 17/431,725
- Filed: 2020-05-07
- Published: 2022-12-15
- Earliest claimed: 2019-03-20
- Assignees: China Railway 14th Bureau Group Corporation Limited; China Railway Siyuan Survey and Design Group Co., Ltd.
- Applicants: China Railway 14Th Bureau Group Co., Ltd.; China Railway Siyuan Survey and Design Group Co., Ltd.
- Inventors: Jian CHEN; Mingqing XIAO; Chengzhen WANG; Xiuting SU; Shuchen LI; Feng XUE; Xiudong LI; Yankun WU; Wenhao SUN
- Web page: https://patentgrep.com/patent/US20220397036A1

## CPC

- E21D 9/06: Making by using a driving shield {, i.e. advanced by pushing means bearing against the already placed lining (pushing prefabricated elements through the ground from an access pit E21D9/005)}
- E21D 9/0607: {the shield being provided with devices for lining the tunnel, e.g. shuttering (E21D9/0873, E21D9/0879 take precedence; tail sealing means used as end shuttering E21D9/0635)}
- E21D 9/093: Control of the driving shield {, e.g. of the hydraulic advancing cylinders (arrangement of measuring or indicating devices for use during driving of tunnels E21D9/003)}
- E21D 11/10: with concrete cast in situ; Shuttering {also lost shutterings, e.g. made of blocks, of metal plates} or other equipment adapted therefor
- E21D: SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS (soil-conditioning or soil-stabilising materials C09K17/00; drilling or cutting machines for mining or quarrying E21C; safety devices, transport, rescue, ventilation or drainage E21F)

## Abstract

A method and apparatus for controlling stratum deformation in a shield construction process, a non-volatile storage medium, and a processor are disclosed. The method includes: monitoring settlement characteristic parameters in a shield construction process; predicting a settlement proportion according to the settlement characteristic parameters, the settlement proportion being a ratio between a predicted settlement value and a corresponding settlement threshold; and determining construction parameters in the shield construction process according to the settlement proportion. In the method, a settlement proportion is predicted through settlement characteristic parameters monitored in a shield construction process, and then appropriate construction parameters are determined according to the settlement proportion, so that the construction parameters in the shield construction process can be corrected in real time, and the safety and scientificity of stratum deformation control in shield construction can be ensured.

## Claims

### Claim 1

A method for controlling stratum deformation in a shield construction process, comprising:
monitoring settlement characteristic parameters in a shield construction process;
predicting a settlement proportion according to the settlement characteristic parameters, the settlement proportion being a ratio between a predicted settlement value and a corresponding settlement threshold; and
determining construction parameters in the shield construction process according to the settlement proportion.

### Claim 2 (depends on 1)

The method according to claim 1, wherein the stratum deformation process in the shield construction process is divided into five settlement stages, namely a pre-deformation stage, an excavation face deformation stage, a deformation stage in passing process in passing process, a shield tail rear deformation stage, and a post-deformation stage; and
determining construction parameters in the shield construction process according to the settlement proportion comprises: determining the construction parameters corresponding to the settlement stages according to a settlement proportion of each settlement stage.

### Claim 3 (depends on 2)

The method according to claim 2, wherein predicting a settlement proportion according to the settlement characteristic parameters comprises:
performing machine training by using a plurality of training data sets to obtain a settlement prediction model, each training data set comprising: training settlement characteristic parameters and a training settlement proportion corresponding to each training settlement stage; and
analyzing the settlement characteristic parameters corresponding to each settlement stage by adopting the settlement prediction model, and predicting the settlement proportion corresponding to each settlement stage.

### Claim 4 (depends on 2)

The method according to claim 2, wherein the settlement characteristic parameters corresponding to the pre-deformation stage comprise a tunnel burial depth, a section size, an underground pore water pressure, and a supporting force, the settlement characteristic parameters corresponding to the excavation face deformation stage comprise a tunnel burial depth, a section size, an underground water pressure, and a supporting force, the settlement characteristic parameters corresponding to the deformation stage in passing process in passing process comprise a tunnel burial depth, a section size, an underground pore water pressure, and a filling amount of inert filling materials, the settlement characteristic parameters corresponding to the shield tail rear deformation stage comprise a tunnel burial depth, a section size, an underground water pressure, a elastic modulus of elastic modulus of synchronous post-grouting slurry, and a grouting pressure, and the settlement characteristic parameters corresponding to the post-deformation stage comprise a tunnel burial depth, a section size, an underground water pressure, and mechanical parameters of stratum.

### Claim 5 (depends on 2)

The method according to claim 2, wherein determining the construction parameters corresponding to the settlement stages according to a settlement proportion of each settlement stage comprises:
determining whether the settlement proportion of each settlement stage is within a corresponding predetermined range; and
adjusting the construction parameters corresponding to target settlement stage when the settlement proportion of the target settlement stage is not within the corresponding predetermined range.

### Claim 6 (depends on 5)

The method according to claim 5, wherein the construction parameters corresponding to the pre-deformation stage and the excavation face deformation stage comprise a slurry pressure, the settlement proportion corresponding to the pre-deformation stage is a first settlement proportion, the settlement proportion corresponding to the excavation face deformation stage is a second settlement proportion, the predetermined ranges corresponding to the pre-deformation stage and the excavation face deformation stage are a first predetermined range, a minimum value of the first predetermined range is a first threshold, and a maximum value of the first predetermined range is a second threshold; and
adjusting the construction parameters corresponding to target settlement stage when the settlement proportion of the target settlement stage is not within the corresponding predetermined range comprises:
reducing the slurry pressure when the first settlement proportion and/or the second settlement proportion are smaller than the first threshold; and
increasing the slurry pressure when the first settlement proportion and/or the second settlement proportion are greater than the second threshold.

### Claim 7 (depends on 6)

The method according to claim 6, wherein the slurry pressure ranges from Pw to Pw+20 kpa, where Pw is a hydrostatic pressure at the location of the pre-deformation stage or the excavation face deformation stage.

### Claim 8 (depends on 5)

The method according to claim 5, wherein the construction parameters corresponding to the deformation stage in passing process in passing process comprise at least one of a fluctuation value of a incision water pressure, a tunneling speed, a cutter head torque, a cutter head rotating speed, and a filling material injection rate, the settlement proportion corresponding to the deformation stage in passing process in passing process is a third settlement proportion, the predetermined range corresponding to the deformation stage in passing process in passing process is a second predetermined range, a minimum value of the second predetermined range is a third threshold, and a maximum value of the second predetermined range is a fourth threshold; and
adjusting the construction parameters corresponding to target settlement stage when the settlement proportion of the target settlement stage is not within the corresponding predetermined range comprises:
increasing at least one of the fluctuation value of the incision water pressure, the tunneling speed, the cutter head torque, and the cutter head rotating speed, and/or reducing the filling material injection rate when the third settlement proportion is smaller than the third threshold; and
reducing at least one of the fluctuation value of the incision water pressure, the tunneling speed, the cutter head torque, and the cutter head rotating speed, and/or increasing the filling material injection rate when the third settlement proportion is greater than the fourth threshold.

### Claim 9 (depends on 8)

The method according to claim 8, wherein the fluctuation value of the incision water pressure ranges from 0 to 10 kpa, the tunneling speed ranges from 15 to 30 mm/min, the cutter head torque ranges from 6 to 9 MNm, the cutter head rotating speed ranges from 0.8 to 1.2 rpm, and the filling material injection rate ranges from 120% to 130%.

### Claim 10 (depends on 5)

The method according to claim 5, wherein the construction parameters corresponding to the shield tail rear deformation stage comprise a grouting pressure and/or a grouting amount, the settlement proportion corresponding to the shield tail rear deformation stage is a fourth settlement proportion, the predetermined range corresponding to the shield tail rear deformation stage is a third predetermined range, a minimum value of the third predetermined range is a fifth threshold, and a maximum value of the third predetermined range is a sixth threshold; and
adjusting the construction parameters corresponding to target settlement stage when the settlement proportion of the target settlement stage is not within the corresponding predetermined range comprises:
reducing the grouting pressure and/or the grouting amount when the fourth settlement proportion is smaller than the fifth threshold; and
increasing the grouting pressure and/or the grouting amount when the fourth settlement proportion is greater than the sixth threshold.

### Claim 11 (depends on 10)

The method according to claim 10, wherein the grouting pressure ranges from Ps+0.85 Ff to Ps+1.25 Ff, and the grouting amount is greater than or equal to 1.3 Vs, where Ps is a predetermined grouting pressure, Ff is a pipeline friction force, and Vs is a predetermined grouting amount.

### Claim 12 (depends on 5)

The method according to claim 5, wherein the construction parameters corresponding to the post-deformation stage comprise a secondary grouting pressure, the settlement proportion corresponding to the post-deformation stage is a fifth settlement proportion, the predetermined range corresponding to the post-deformation stage is a fourth predetermined range, a minimum value of the fourth predetermined range is a seventh threshold, and a maximum value of the predetermined range is an eighth threshold; and
adjusting the construction parameters corresponding to target settlement stage when the settlement proportion of the target settlement stage is not within the corresponding predetermined range comprises:
reducing the secondary grouting pressure when the fifth settlement proportion is smaller than the seventh threshold; and
increasing the secondary grouting pressure when the fifth settlement proportion is greater than the eighth threshold.

### Claim 13 (depends on 12)

The method according to claim 12, wherein the secondary grouting pressure ranges from 400 to 600 kpa.

### Claim 14

An apparatus for controlling stratum deformation in a shield construction process, comprising:
a monitoring unit, configured to monitor settlement characteristic parameters of stratum deformation in a shield construction process;
a prediction unit, configured to predict a settlement proportion according to the settlement characteristic parameters, the settlement proportion being a ratio between a predicted settlement value and a corresponding settlement threshold; and
a determination unit, configured to determine construction parameters in the shield construction process according to the settlement proportion.

### Claim 15 (depends on 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13)

A non-volatile storage medium, comprising a stored program, wherein when the program is run, a device where the non-volatile storage medium is located is controlled to perform the control method according to any one of claims 1 to 13.

### Claim 16 (depends on 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13)

A processor, configured to run a program, wherein the program, when run, performs the control method according to any one of claims 1 to 13.