# US 2022/0294229 A1 · Method and stabilization controller for operating a stand-alone grid

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2022/0294229 A1
- Document ID: US20220294229A1
- Status: Published application
- Kind: A1
- Application number: 17/829,474
- Filed: 2022-06-01
- Published: 2022-09-15
- Earliest claimed: 2019-12-09
- Assignees: RWE Renewables GmbH
- Inventors: Jörn Runge; Christian Feltes
- Web page: https://patentgrep.com/patent/US20220294229A1

## CPC

- H02J 3/381: {Dispersed generators}
- F03D 7/0284: {in relation to the state of the electric grid}
- F03D 7/048: {controlling wind farms}
- H02J 3/00142: {Oscillations concerning frequency}
- H02J 3/32: using batteries or super capacitors with converting means
- H02J 3/388: Arrangements for the handling of islanding, e.g. for disconnection or for avoiding the disconnection of power
- H02J 7/34: Parallel operation in networks using both storage and other DC sources, e.g. providing buffering (H02J7/14 takes precedence)
- H02J 13/13: characterised by the transmission of data to equipment in the power network
- H02J 2101/28: Wind energy
- H02J 2103/35: Grid-level management of power transmission or distribution systems, e.g. load flow analysis or active network management
- H02J 2105/10: Local stationary networks having a local or delimited stationary reach
- Y02E 10/72: Wind turbines with rotation axis in wind direction
- Y02E 10/76: Power conversion electric or electronic aspects
- Y02E 40/70: Smart grids as climate change mitigation technology in the energy generation sector
- Y02E 70/30: Systems combining energy storage with energy generation of non-fossil origin
- Y04S 10/123: the energy generation units being or involving renewable energy sources
- H02J: ELECTRIC POWER NETWORKS; CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- F03D: WIND MOTORS
- Y02E: REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y04S: SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS

## Abstract

Disclosed is a method for operating a stand-alone grid, in which at least one participant of the stand-alone grid is coupled to a stabilization controller and an impedance between an output of the stabilization controller and a grid node of the stand-alone grid is determined. Further, a nominal voltage at the grid node is regulated by means of the stabilization controller depending on the determined impedance.

## Claims

### Claim 1

A method for starting up a stand-alone grid with at least two participants comprising:
coupling an electrical feeder, in particular an electrical storage device and/or a generator, with the stand-alone grid via a stabilization controller, wherein the stabilization controller has an ohmic load; and
coupling at least one of the participants with the stabilization controller,
wherein a nominal frequency setpoint for the stabilization controller and/or a nominal phase setpoint for the stabilization controller is controlled in a phase-locked loop at least depending on a measured grid frequency of the stand-alone grid and/or a state of charge and/or an active power of the feeder,
wherein the stabilization controller is operated as a load and absorbs active power when the active power of a participant exceeds the load in the stand-alone grid and
wherein first, a first participant is started-up and is synchronized with a grid frequency and injects active power into the stand-alone grid and after the first participant is started-up, additional loads and participants are connected to the stand-alone grid as loads.

### Claim 2 (depends on 1)

The method of claim 1,
wherein active component and/or reactive component, in particular d and q components of a nominal voltage at an output of the stabilization controller is controlled in a voltage control loop depending on a state of charge of the feeder and/or a measured grid voltage at the stabilization controller.

### Claim 3 (depends on 1)

The method of claim 1,
wherein an impedance between an output of the stabilization controller and a grid node of the stand-alone grid is determined,
the active and/or reactive components, in particular d and q components of the nominal voltage for the stabilizing controller are controlled in the voltage control loop depending on the determined impedance.

### Claim 4 (depends on 3)

The method of claim 3,
wherein a forward connection in the voltage control loop is dependent on the determined impedance.

### Claim 5 (depends on 1)

The method of claim 1,
wherein a nominal active current setpoint, in particular d component of a nominal current from the voltage control loop is coupled into the phase-locked loop.

### Claim 6 (depends on 1)

The method of claim 1,
wherein a nominal power setpoint for the participant is output from the phase-locked loop via a communication link, or wherein a nominal power setpoint for the participant is output from the phase-locked loop via the nominal frequency setpoint for the stabilization controller.

### Claim 7 (depends on 1)

The method of claim 1,
wherein in the phase-locked loop, the nominal frequency setpoint for the stabilization controller is fed back and/or wherein in the phase-locked loop, the nominal phase setpoint for the stabilization controller is fed back.

### Claim 8 (depends on 1)

The method of claim 1,
wherein a first nominal frequency setpoint is determined in the phase-locked loop from the difference between an actual power value at the feeder and a nominal power setpoint at the feeder, and wherein a difference between the first nominal frequency setpoint and the fed-back frequency setpoint is determined for the stabilization controller.

### Claim 9 (depends on 3)

The method of claim 3,
wherein the impedance is measured for a fundamental frequency.

### Claim 10 (depends on 1)

The method of claim 1,
wherein a bandwidth of a frequency response of the stabilization controller is larger than a bandwidth of a frequency response of an inverter of the participant.

### Claim 11 (depends on 1)

The method of claim 1,
wherein the stabilizing controller comprises at least one attenuator, and that the attenuator is dependent on the impedance and/or a natural frequency of the stand-alone grid and/or a transfer function of an inverter of the participant, wherein the attenuator stabilizes the stabilizing controller.

### Claim 12 (depends on 11)

The method of claim 11,
wherein the stabilizing controller injects active or reactive power depending on the attenuator.

### Claim 13 (depends on 1)

The method of claim 1,
wherein a power balance of the stabilizing controller and the participant is controlled by power measurement at the participant and communication between the participant and the stabilizing controller.

### Claim 14 (depends on 1)

The method of claim 1,
wherein the stabilizing controller is frequency-controlled, wherein the stabilizing controller has a lead-lag compensator.

### Claim 15 (depends on 14)

The method of claim 14,
wherein the lead-lag compensator modifies an active power output at the stabilizing controller in such a way that it counteracts the frequency change.

### Claim 16 (depends on 1)

The method of claim 1,
wherein an output power of the participant is lower than a maximum power of the stabilizing controller.

### Claim 17 (depends on 1)

The method of claim 1,
wherein the stabilization controller is operated as a slack bus.

### Claim 18 (depends on 1)

The method of claim 1,
wherein a reactive power of the participant is set depending on an active power of the participant and/or an active power of the stabilization controller, in particular wherein a dependency between active and reactive power is stored in a look-up table.

### Claim 19 (depends on 1)

A stabilizing controller for carrying out the method of claim 1,
wherein the stabilization controller is installed at least in parts together with a medium-voltage transformer and an electrical energy storage device in a standard container and has the ohmic load.