# US 2022/0294219 A1 · Managing queue distribution between critical datacenter and flexible datacenter

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2022/0294219 A1
- Document ID: US20220294219A1
- Status: Published application
- Kind: A1
- Application number: 17/750,883
- Filed: 2022-05-23
- Published: 2022-09-15
- Earliest claimed: 2018-10-30
- Assignees: Lancium LLC
- Applicants: Lancium LLC
- Inventors: Michael T. MCNAMARA; David J. HENSON; Raymond E. CLINE, JR.
- Web page: https://patentgrep.com/patent/US20220294219A1

## CPC

- H02J 3/12: Arrangements for adjusting voltage in AC networks by changing a characteristic of the network load
- G06F 1/3206: Monitoring of events, devices or parameters that trigger a change in power modality
- G06F 1/329: by task scheduling
- G06F 9/4893: {taking into account power or heat criteria (power management in computers in general G06F1/3203; thermal management in computers in general G06F1/206)}
- G06F 9/5027: {the resource being a machine, e.g. CPUs, Servers, Terminals}
- G06F 9/5088: {involving task migration}
- G06F 9/5094: {where the allocation takes into account power or heat criteria (power management in computers in general G06F1/3203; thermal management in computers in general G06F1/206)}
- H02J 1/14: Balancing load and power generation in DC networks
- H02J 3/14: by switching loads on to, or off from, the networks, e.g. progressively balanced loading
- H02J 2101/20: Dispersed power generation using renewable energy sources
- H02J 2105/425: {the loads being an Information and Communication Technology [ICT] facility}
- H02J: ELECTRIC POWER NETWORKS; CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- G06F: ELECTRIC DIGITAL DATA PROCESSING (computer systems based on specific computational models G06N)

## Abstract

Systems include one or more critical datacenter connected to behind-the-meter flexible datacenters. The critical datacenter is powered by grid power and not necessarily collocated with the flexible datacenters, which are powered “behind the meter.” When a computational operation to be performed at the critical datacenter is identified and determined that it can be performed more efficiently or advantageously at a flexible datacenter, the computational operation is instead obtained by the flexible datacenters for performance The critical datacenter and flexible datacenters preferably share a dedicated communication pathway to enable high-bandwidth, low-latency, secure data transmissions. A queue system may be used to organize computational operations waiting for distribution to either the critical datacenter or the flexible datacenter.

## Claims

### Claim 1

A system comprising:
a flexible datacenter comprising:
a behind-the-meter (“BTM”) power input system;
a power distribution system;
a plurality of computing systems powered by the BTM power input system via the power distribution system;
a queue system configured to organize a plurality of computational operations, wherein the queue system comprises multiple queue subsystems, and wherein each queue subsystem organizes a set of computational operations according to rules associated with the queue subsystem; and
a routing control system configured to:
determine, using the queue system, a computational operation to be performed;
determine whether to route the computational operation to the flexible datacenter; and
based on a determination to route the computational operation to the flexible datacenter, assign the computational operation for performance at the flexible datacenter.

### Claim 2 (depends on 1)

The system of claim 1, wherein the routing control system is a remote master control system positioned remotely from the flexible datacenter.

### Claim 3 (depends on 1)

The system of claim 1, wherein the routing control system is a remote master control system positioned at the flexible datacenter.

### Claim 4 (depends on 1)

The system of claim 1, wherein the flexible datacenter further comprises:
a datacenter control system, wherein the datacenter control system is configured to modulate power delivery to the plurality of computing systems based on one or more monitored power system conditions.

### Claim 5 (depends on 4)

The system of claim 4, wherein the one or more monitored power system conditions comprises:
behind-the-meter (“BTM”) power availability at the plurality of computing systems.

### Claim 6 (depends on 4)

The system of claim 4, wherein the one or more monitored power system conditions comprises:
one or more of excess local power generation at a local station level, excess local power generation that a grid cannot receive, local power generation subject to economic curtailment, local power generation subject to reliability curtailment, local power generation subject to power factor correction, low local power generation, start up local power generation situations, transient local power generation situations, or testing local power generation situations where there is an economic advantage to using local behind-the-meter power generation.

### Claim 7 (depends on 1)

The system of claim 1, wherein the flexible datacenter further comprises:
a datacenter control system, wherein the datacenter control system is configured to modulate power delivery to the plurality of computing systems based on an operational directive.

### Claim 8 (depends on 7)

The system of claim 7, wherein the operational directive originates from the routing control system and depends on behind-the-meter (“BTM”) power availability at the plurality of computing systems.

### Claim 9 (depends on 1)

The system of claim 1, wherein the BTM power input system is configured to receive power from a power generation system prior to the power undergoing step-up transformation for transmission to a grid.

### Claim 10 (depends on 1)

The system of claim 1, wherein the routing control system controls distribution of the plurality of computational operations from the queue system.

### Claim 11 (depends on 1)

The system of claim 1, wherein a first queue subsystem of the queue system is located at the flexible datacenter.

### Claim 12 (depends on 11)

The system of claim 11, further comprising:
a second datacenter, wherein a second queue subsystem of the queue system is located at the second datacenter.

### Claim 13 (depends on 12)

The system of claim 12, wherein the second datacenter is a second flexible datacenter.

### Claim 14

A flexible datacenter comprising:
a behind-the-meter (“BTM”) power input system;
a power distribution system;
a datacenter control system;
a plurality of computing systems, wherein the plurality of computing systems are powered by the BTM power input system via the power distribution system; and
a queue subsystem configured to organize a set of computational operations for performance by the plurality of computing systems, wherein the queue subsystem is part of a distributed queue system.

### Claim 15 (depends on 14)

The flexible datacenter of claim 14, wherein the distributed queue system includes at least two queue subsystems having different rules for organizing computational operations.

### Claim 16 (depends on 14)

The flexible datacenter of claim 14, wherein the datacenter control system is configured to modulate power delivery to the plurality of computing systems based on an operational directive received from a remote master control system.

### Claim 17 (depends on 16)

The flexible datacenter of claim 16, wherein the remote master control system is positioned remotely from the flexible datacenter.

### Claim 18 (depends on 14)

The flexible datacenter of claim 14, wherein the BTM power input system is configured to receive power from a power generation system prior to the power undergoing step-up transformation for transmission to a grid.

### Claim 19

A method comprising:
determining, by a routing control system and using a queue system, a computation operation to be performed, wherein the queue system organizes a plurality of computational operations and comprises multiple queue subsystems, wherein each queue subsystem organizes a set of computational operations according to rules associated with the queue subsystem;
determining whether to route the computational operation to a flexible datacenter, wherein the flexible datacenter comprises: (i) a behind-the-meter (“BTM”) power input system, (ii) a power distribution system, and (iii) a plurality of computing systems powered by the BTM power input system via the power distribution system; and
based on a determination to route the computational to the flexible datacenter, assigning the computational operation for performance at the flexible datacenter.

### Claim 20 (depends on 19)

The method of claim 19, wherein determining whether to route the computational operation to the flexible datacenter comprises:
determining to route the computational operation to the flexible datacenter based on BTM power availability at the flexible datacenter.