# US 2022/0291658 A1 · Production line scheduling method, production line system and non-temporary computer readable medium

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2022/0291658 A1
- Document ID: US20220291658A1
- Status: Published application
- Kind: A1
- Application number: 17/372,176
- Filed: 2021-07-09
- Published: 2022-09-15
- Earliest claimed: 2021-03-10
- Assignees: Industrial Technology Research Institute
- Applicants: Industrial Technology Research Institute
- Inventors: Yu-Jung YEH; Tsan-Cheng SU; Chung-Wei LIN
- Web page: https://patentgrep.com/patent/US20220291658A1

## CPC

- G05B 19/4097: characterised by using design data to control NC machines, e.g. CAD/CAM (G05B19/4093 takes precedence)
- G05B 19/41865: {characterised by job scheduling, process planning, material flow}
- G06F 30/20: Design optimisation, verification or simulation (optimisation, verification or simulation of circuit designs G06F30/30)
- G05B 2219/32301: Simulate production, process stages, determine optimum scheduling rules
- G05B 2219/32342: Real time simulation
- G05B: CONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS (systems for controlling or regulating non-electric variables G05D; systems for regulating electric or magnetic variables G05F; control devices or systems insofar as characterised by mechanical features only G05G)
- G06F: ELECTRIC DIGITAL DATA PROCESSING (computer systems based on specific computational models G06N)

## Abstract

A production line scheduling method, adapted to a plurality of jobs passing a bottleneck station having at least one manufacturing machine, the jobs respectively correspond to a plurality of job conditions, and the method comprises: performing a plurality of times of a schedule simulation algorithm on the jobs to sequentially establish a plurality of schedule simulation trees, and obtaining a job schedule and a simulated finishing period of each job based on the schedule simulation trees, wherein each schedule simulation tree comprises at least one scheduling route, and each scheduling route is generated from one schedule simulation algorithm; and calculating a plurality of expected feeding times of each job at a plurality of stations comprising the bottleneck station, wherein the schedule simulation algorithm comprises: performing a node expansion step based on at least one node expansion condition and the job conditions to obtain the scheduling route.

## Claims

### Claim 1

A production line scheduling method, adapted to a plurality of jobs of an order, wherein the jobs pass a bottleneck station having at least one manufacturing machine, and the jobs respectively correspond to a plurality of job conditions, and the production line scheduling method comprising:
performing a plurality of times of a schedule simulation algorithm on the jobs to sequentially establish a plurality of schedule simulation trees, and obtaining a job schedule and a simulated finishing period of each one of the jobs based on the schedule simulation trees, wherein each one of the schedule simulation trees comprises at least one scheduling route, and each scheduling route is generated from one of the times of performing the schedule simulation algorithm; and
calculating a plurality of expected feeding times of each one of the jobs at a plurality of stations comprising the bottleneck station based on the simulated finishing period of each one of the jobs,
wherein the schedule simulation algorithm comprises: performing a node expansion step based on at least one node expansion condition and the job conditions to obtain the scheduling route.

### Claim 2 (depends on 1)

The production line scheduling method according to claim 1, wherein the at least one node expansion condition comprises at least one of a part number condition, a fixture moving condition and a production starting time condition.

### Claim 3 (depends on 1)

The production line scheduling method according to claim 1, wherein the at least one node expansion condition is a plurality of node expansion conditions, the node expansion step of the schedule simulation algorithm is for arranging the jobs into the scheduling route, wherein the node expansion step comprises a plurality of node selection procedures, and each one of the node selection procedures comprises a sub-node selection procedure, wherein the sub-node selection procedure comprises:
determining whether at least one of the job conditions complies with at least one of the node expansion conditions;
when determining at least one of the job conditions complies with at least one of the node expansion conditions, selecting one of the jobs and a corresponding available manufacturing machine with the at least one of the job conditions complying with the at least one of the node expansion conditions, based on a current node, as a pre-selected node following the current node; and
when determining none of the job conditions complies with the node expansion conditions, randomly selecting one of the jobs and a corresponding another available manufacturing machine as the pre-selected node following the current node.

### Claim 4 (depends on 3)

The production line scheduling method according to claim 3, wherein the sub-node selection procedure is a first sub-node selection procedure, each one of the node selection procedures further comprises a second sub-node selection procedure, and the second sub-node selection procedure is performed after the first sub-node selection procedure, wherein the second sub-node selection procedure comprises:
determining whether at least one working period respectively corresponding to the at least one manufacturing machine all complies with a time threshold based on the pre-selected node and at least one current node connecting the pre-selected node, wherein the at least one current node connecting the pre-selected node comprises said current node;
defining the pre-selected node as another current node and performing another one of the node selection procedures based on the another current node when the working period of one of the at least one manufacturing machine does not reach the time threshold; and
stopping the node selection procedures when the at least one working period all complies with the time threshold.

### Claim 5 (depends on 4)

The production line scheduling method according to claim 4, wherein the schedule simulation algorithm further comprises a simulation step performed after stopping the node expansion step, and the simulation step comprises: calculating a simulation score of the scheduling route corresponding to the schedule simulation algorithm.

### Claim 6 (depends on 5)

The production line scheduling method according to claim 5, wherein in a first one of the node selection procedures, the current node is an initial node, the pre-selected node is a first pre-selected node, and the schedule simulation algorithm further comprises a backpropagation step performed after the simulation step, and the backpropagation step comprising:
adding the simulation score to a total score of the first pre-selected node.

### Claim 7 (depends on 6)

The production line scheduling method according to claim 6, wherein performing the plurality of times of the schedule simulation algorithm on the jobs to sequentially establish the plurality of schedule simulation trees comprises:
determining whether one of the schedule simulation trees comprising the initial node complies with an ending condition;
performing another one of the times of the schedule simulation algorithm when the schedule simulation tree is determined as not reaching the ending condition; and
selecting one of a plurality of the first pre-selected nodes connecting the initial node as a selected node corresponding to the schedule simulation tree when the schedule simulation tree complies with the ending condition, wherein a total score of the selected node is higher than other total scores of the plurality of the first pre-selected nodes excluding the selected node.

### Claim 8 (depends on 1)

The production line scheduling method according to claim 1, wherein performing the plurality of times of the schedule simulation algorithm on the jobs to sequentially establish the plurality of schedule simulation trees, and obtaining the job schedule and the simulated finishing period of each one of the jobs based on the schedule simulation trees comprises:
determining whether the jobs are all selected as a plurality of selected nodes respectively corresponding to the schedule simulation trees;
performing another time of the schedule simulation algorithm when at least one of the jobs hasn't been selected as one of the selected nodes; and
obtaining the simulated finishing period of each one of the jobs using the job schedule comprising the selected nodes when the jobs are all selected as the plurality of selected nodes.

### Claim 9 (depends on 2)

The production line scheduling method according to claim 2, wherein the part number condition comprises: a state in which a product part number of the job condition is the same as a current part number of the current node.

### Claim 10 (depends on 9)

The production line scheduling method according to claim 9, wherein the part number condition further comprises: another state in which an expected feeding time of the job condition falls within the time threshold.

### Claim 11 (depends on 2)

The production line scheduling method according to claim 2, wherein the fixture moving condition comprises: a state in which a machine fixture of the job condition is the same as a current machine fixture of the current node.

### Claim 12 (depends on 2)

The production line scheduling method according to claim 2, wherein the production starting time condition comprises: a state in which a machine available time of the job condition is the earliest one among the job conditions.

### Claim 13 (depends on 4)

The production line scheduling method according to claim 4, wherein determining whether at least one of the job conditions complies with at least one of the node expansion conditions comprises:
determining whether at least one of the job conditions complies with a part number condition;
determining whether at least one of the job conditions complies with a fixture moving condition when none of the job conditions complies with the part number condition;
determining whether at least one of the job conditions complies with a production starting time condition when none of the job conditions complies with the fixture moving condition; and
randomly selecting another one of the jobs as the pre-selected node when none of the job conditions complies with the production starting time.

### Claim 14 (depends on 4)

The production line scheduling method according to claim 4, wherein when more than one of the job conditions comply with the node expansion condition, the production line scheduling method further comprises:
using the job corresponding to the job condition with an earliest required feeding time among the job conditions as the pre-selected node.

### Claim 15 (depends on 4)

The production line scheduling method according to claim 4, wherein the node expanding conditions comprise a part number condition, the part number condition comprises: a state in which a sum of a working period of the pre-selected node obtained in the node expansion step and a working period of the at least one current node connected to the pre-selected node is less than a continuous working period, and determining whether at least one of the job conditions complies with at least one of the node expansion conditions comprises:
determining, based on the job conditions, whether the sum of the working period of the pre-selected node obtained in the node expansion step and the working period of the at least one current node connected to the pre-selected node is less than the continuous working period; and
determining whether at least one of the job conditions complies with another one of the job conditions when the sum of the working periods is not less than the continuous working period.

### Claim 16 (depends on 5)

The production line scheduling method according to claim 5, wherein calculating the simulation score of the scheduling route corresponding to the schedule simulation algorithm comprises:
calculating the simulation score based on an allowable times of production line switching, an expected production capacity and an allowable delayed quantity.

### Claim 17 (depends on 16)

The production line scheduling method according to claim 16, wherein calculating the simulation score based on the allowable times of production line switching is: calculating the simulation score based on the time threshold, the allowable times of production line switching within the time threshold and a total times of production line switching within the time threshold.

### Claim 18 (depends on 16)

The production line scheduling method according to claim 16, wherein calculating the simulation score based on the expected production capacity is: calculating the simulation score based on the time threshold, a produced number within the time threshold and the expected production capacity within the time threshold.

### Claim 19 (depends on 16)

The production line scheduling method according to claim 16, wherein calculating the simulation score based on the allowable delayed quantity is: calculating the simulation score based on the time threshold, the allowable delayed quantity within the time threshold and a total delayed number within the time threshold.

### Claim 20 (depends on 16)

The production line scheduling method according to claim 16, wherein calculating the simulation score based on the allowable times of production line switching, the expected production capacity and the allowable delayed quantity is:
calculating reference simulation scores respectively corresponding to the allowable times of production line switching, the expected production capacity and the allowable delayed quantity;
multiplying each of the reference simulation scores of the allowable times of production line switching, the expected production capacity and the allowable delayed quantity with a respective one of a weight; and
using a sum of the reference simulation scores respectively multiplied with the weights as the simulation score.

### Claim 21 (depends on 1)

The production line scheduling method according to claim 1, wherein calculating one of the expected feeding times comprises:
dividing a product delivery time of one of the jobs by an actual processing time to obtain a flow factor; and
subtracting a product of a required processing time and the flow factor from the simulated finishing period of the one of the jobs to obtain the expected feeding time.

### Claim 22 (depends on 1)

A production line system, comprising:
a computing device, configured to perform the production line scheduling method of claim 1 to obtain the job schedule; and
a plurality of available manufacturing machines, communicatively connected to the computing device, with each of the available manufacturing machines obtaining a pending job among the jobs based on the job schedule after finishing a current job, and each of the available manufacturing machines further outputting a processing parameter notification based on a part number of the pending job.

### Claim 23 (depends on 22)

The production line system according to claim 22, wherein
each of the available manufacturing machines outputs the processing parameter notification comprising a parameter switching notification when determining the part number is different from another part number of the current job, and
each of the available manufacturing machines outputs the processing parameter notification comprising a parameter inheriting notification when determining the part number is the same as the another part number of the current job.

### Claim 24 (depends on 1)

A non-temporary computer readable medium, comprising a program, wherein the program is performed by a computing device to perform the production line scheduling method of claim 1.