# US 2022/0283618 A1 · Power grid lateral trouble ticket cause determination and ticket management

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2022/0283618 A1
- Document ID: US20220283618A1
- Status: Published application
- Kind: A1
- Application number: 17/191,277
- Filed: 2021-03-03
- Published: 2022-09-08
- Earliest claimed: 2021-03-03
- Assignees: Florida Power & Light Company
- Applicants: Florida Power & Light Company
- Inventors: Lucas Bassett-audain; Genese Augustin; Daniel Barbosa; Steven Tolbert
- Web page: https://patentgrep.com/patent/US20220283618A1

## CPC

- G06F 1/28: Supervision thereof, e.g. detecting power-supply failure by out of limits supervision
- H02J 13/12: Monitoring network conditions, e.g. electrical magnitudes or operational status
- G05B 15/02: electric
- G05B 19/4067: Restoring data or position after power failure or other interruption
- H02J 13/333: the equipment forming part of substations
- G06F: ELECTRIC DIGITAL DATA PROCESSING (computer systems based on specific computational models G06N)
- H02J: ELECTRIC POWER NETWORKS; CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- G05B: CONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS (systems for controlling or regulating non-electric variables G05D; systems for regulating electric or magnetic variables G05F; control devices or systems insofar as characterised by mechanical features only G05G)

## Abstract

A power grid monitoring system for determining a cause of a lateral trouble ticket. The power grid monitoring system can determine a cause of a lateral trouble ticket in response to receiving the lateral trouble ticket. The power grid monitoring system associates a set of smart meters with a first, penultimate and last transformer downstream from a given lateral. The power grid monitoring system pings each smart meter in the set of smart meters to indicate a state of the first, penultimate and last transformers of the given lateral. Accordingly, the power monitoring system determines a cause of a lateral trouble ticket associated with the given lateral based on results of the pings to the set of smart meters associated with the first, last and penultimate transformers. The power grid monitoring system can further augment the lateral trouble ticket with information characterizing the cause of the lateral trouble ticket.

## Claims

### Claim 1

A power grid monitoring system operating on a computing platform comprising:
a transformer management engine that:
associates a first smart meter of a set of smart meters with a first transformer downstream from a given lateral, associates a penultimate smart meter of the set of smart meters with a penultimate transformer downstream from the given lateral and associates a last smart meter of the set of smart meters with a last transformer downstream from the given lateral; and
pings each smart meter in the set of smart meters to determine a state of the first transformer, the penultimate transformer and the last transformer of the given lateral;
an event processing engine that determines a cause of a lateral trouble ticket associated with the given lateral based on results of the pings to the set of smart meters associated with the first, last and penultimate transformers, wherein if the results of the pings to the set of selected smart meters indicate that the first transformer is online and that the last and penultimate transformers are offline, the event processing engine determines that the cause of the lateral trouble ticket is a wire down, and if the results of the pings to the set of selected smart meters indicating that the first, last and penultimate transformer are offline, the event processing engine determines that the cause of the lateral trouble ticket is blown fuse; and
a ticket management engine that augments the lateral trouble ticket with information characterizing the cause of the lateral trouble ticket.

### Claim 2 (depends on 1)

The power grid monitoring system of claim 1, wherein if the results of the pings to the set of selected smart meters indicate that the state of penultimate transformer is different than the state of the first and last transformers, the event processing engine determines that the cause of the lateral trouble ticket is a misattributed smart meter.

### Claim 3 (depends on 2)

The power grid monitoring system of claim 2, wherein if the results of the pings to the set of selected smart meters indicate that the state of the penultimate transformer is online and the first and last transformers are offline, the event processing engine determines that the penultimate smart meter is misattributed to the given lateral, such that the state of the penultimate transformer is actually offline and the determined cause of the lateral trouble ticket is a blown fuse.

### Claim 4 (depends on 2)

The power grid monitoring system of claim 2, wherein if the results of the pings to the set of selected smart meters indicate that the state of the penultimate transformer is offline and the first and last transformers are online, the event processing engine determines that the last smart meter is misattributed to the given lateral, such that the state of the last transformer is actually offline and the determined cause of the lateral trouble ticket is a wire down.

### Claim 5 (depends on 2)

The power grid monitoring system of claim 2, wherein if the results of the pings to the set of selected smart meters indicate that the state of the penultimate transformer is offline and the first and last transformers are online, the event processing engine determines that the penultimate smart meter is misattributed to the given lateral, such that the state of the penultimate transformer is actually online and the determined cause of the lateral trouble ticket is an erroneous elevation of a transformer trouble ticket to the lateral trouble ticket.

### Claim 6 (depends on 1)

The power grid monitoring system of claim 1, wherein the power grid monitoring system further comprises a grid topology engine that generates a lateral grid topology of the plurality of transformers downstream from the given lateral using location data provided by a geographic and information system (GIS).

### Claim 7 (depends on 6)

The power grid monitoring system of claim 6, wherein the grid topology engine generates the lateral grid topology in response to the power grid monitoring system receiving a lateral trouble ticket corresponding to the given lateral.

### Claim 8 (depends on 6)

The power grid monitoring system of claim 6, wherein generating the lateral grid topology comprises:
reformatting a parent-child hierarchical relationship between the given lateral and the plurality of transformers downstream from the given lateral to a linear hierarchical relationship between each of the plurality of transformers downstream from the lateral, such that the lateral grid topology arranges the plurality of transformers downstream from the lateral in series; and
employing the location data provided by the GIS to accurately determine the linear hierarchical relationship between each of the plurality of transformers downstream from the lateral.

### Claim 9 (depends on 8)

The power grid monitoring system of claim 8, wherein the transformer management engine associates the set of smart meters with the first, penultimate and last transformer based on the lateral grid topology.

### Claim 10 (depends on 1)

The power grid monitoring system of claim 1, wherein the ticket management engine augments the lateral trouble ticket to indicate a service crew capable of servicing a wire down in response to the event processing engine determining that the cause of the lateral trouble ticket is a wire down.

### Claim 11 (depends on 1)

The power grid monitoring system of claim 1, wherein the ticket management engine augments the lateral trouble ticket to indicate a service crew capable of servicing a blown fuse in response to the event processing engine determining that the cause of the lateral trouble ticket is a blown fuse, wherein the service crew capable of servicing a blown fuse is incapable of servicing a wire down.

### Claim 12 (depends on 5)

The power grid monitoring system of claim 5, wherein the ticket management engine augments the lateral trouble ticket to indicate a service a crew is not required to remedy the lateral trouble ticket.

### Claim 13

A non-transitory computer readable medium, comprising:
a notification engine configured to receive a lateral trouble ticket in response to a ticket management engine elevating a given trouble ticket to the lateral trouble ticket;
a grid topology engine that generates a lateral grid topology of a plurality of transformers downstream from a given lateral associated with the lateral trouble ticket using location data provided by a geographic and information system (GIS);
a transformer management engine that:
associates a first smart meter of a set of smart meters with a first transformer downstream from the given lateral, associates a penultimate smart meter of the set of smart meters with a penultimate transformer downstream from the given lateral and associates a last smart meter of the set of smart meters with a last transformer downstream from the given lateral based on the lateral grid topology; and
pings each smart meter in the set of smart meters to indicate a state of the first transformer, the penultimate transformer and the last transformer of the given lateral;
an event processing engine that determines a cause of the lateral trouble ticket based on results of the pings to the set of smart meters associated with the first, last and penultimate transformers of the lateral grid topology, wherein if the results of the pings to the set of selected smart meters indicate that the first transformer is online and that the last and penultimate transformers are offline, the event processing engine determines that the cause of the lateral trouble ticket is a wire down, and if the results of the pings to the set of selected smart meters indicate that the first, last and penultimate transformer are offline, the event processing engine determines that the cause of the lateral trouble ticket is blown fuse; and
a ticket management engine that augments the lateral trouble ticket with information characterizing the cause of the lateral trouble ticket.

### Claim 14 (depends on 13)

The medium of claim 13, wherein generating the lateral grid topology comprises:
reformatting a parent-child hierarchical relationship between the given lateral and the plurality of transformers downstream from the given lateral into a linear hierarchical relationship between each of the plurality of transformers downstream from the lateral, such that the lateral grid topology arranges the plurality of transformers downstream from the lateral in series; and
employing the location data provided by the GIS to accurately determine the linear hierarchical relationship between each of the plurality of transformers downstream from the lateral.

### Claim 15 (depends on 13)

The medium of claim 13, wherein the ticket management engine augments the lateral trouble ticket to indicate a service crew capable of servicing a wire down in response to the event processing engine determining that the cause of the lateral trouble ticket is a wire down.

### Claim 16 (depends on 13)

The medium of claim 13, wherein the ticket management engine augments the lateral trouble ticket to indicate a service crew capable of servicing a blown fuse in response to the event processing engine determining that the cause of the lateral trouble ticket is a blown fuse, wherein the service crew capable of servicing a blown fuse is incapable of servicing a wire down.

### Claim 17

A method for monitoring a power grid, the method comprising:
receiving, by a notification engine, a lateral trouble ticket in response to a ticket management engine elevating a given trouble ticket to a lateral trouble ticket;
generating, by a grid topology engine, a lateral grid topology using location data provided by a geographic information system (GIS);
associating, by a transformer management engine, a first smart meter of a set of smart meters with a first transformer downstream from a given lateral, associating a penultimate smart meter of the set of smart meters with a penultimate transformer downstream from the given lateral and associating a last smart meter of the set of smart meters with a last transformer downstream from the given lateral based on the lateral grid topology;
pinging, by a smart meter management engine, each smart meter in the set of smart meters to indicate a state of the first transformer, the penultimate transformer and the last transformer of the given lateral;
determining, by an event processing engine, a cause of the lateral trouble ticket based on results of the pings to the set of smart meters associated with the first, last and penultimate transformers of the lateral grid topology, wherein if the results of the pings to the set of selected smart meters indicate that the first transformer is online and that the last and penultimate transformers are offline, the event processing engine determines that cause of the lateral trouble ticket is a wire down, and if the results of the pings to the set of selected smart meters indicate that the first, last and penultimate transformer are offline, the event processing engine determines that cause of the lateral trouble ticket is blown fuse; and
augmenting, by the ticket management engine, the lateral trouble ticket with information characterizing the cause of the lateral trouble ticket.

### Claim 18 (depends on 17)

The method of claim 17, wherein generating the lateral grid topology comprises:
reformatting, by the grid topology engine, a parent-child hierarchical relationship between the given lateral and the plurality of transformers downstream from the given lateral into a linear hierarchical relationship between each of the plurality of transformers downstream from the lateral, such that the lateral grid topology arranges the plurality of transformers downstream from the lateral in series; and
employing, by the grid topology engine, the location data provided by the GIS to accurately determine the linear hierarchical relationship between each of the plurality of transformers downstream from the lateral.

### Claim 19 (depends on 17)

The method of claim 17, further comprising, augmenting, by the ticket management engine, the lateral trouble ticket to indicate a service crew capable of servicing a wire down in response to the event processing engine determining that the cause of the lateral trouble ticket is a wire down.

### Claim 20 (depends on 17)

The method of claim 17, further comprising, augmenting, by the ticket management engine, the lateral trouble ticket to indicate a service crew capable of servicing a blown fuse in response to the event processing engine determining that the cause of the lateral trouble ticket is a blown fuse, wherein the service crew capable of servicing a blown fuse is incapable of servicing a wire down.