# US 2022/0277255 A1 · Work reliever mediation system and farm machine sharer mediation system

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2022/0277255 A1
- Document ID: US20220277255A1
- Status: Published application
- Kind: A1
- Application number: 17/631,686
- Filed: 2020-08-06
- Published: 2022-09-01
- Earliest claimed: 2019-08-19
- Assignees: Yanmar Power Technology Co., Ltd.
- Applicants: Yanmar Power Technology Co.,Ltd.
- Inventors: Yusuke NISHIDA; Keiji NAKAMURA
- Web page: https://patentgrep.com/patent/US20220277255A1

## CPC

- G06Q 10/06311: {Scheduling, planning or task assignment for a person or group}
- G06Q 10/063116: {Schedule adjustment for a person or group}
- G06Q 10/063112: {Skill-based matching of a person or a group to a task}
- G06Q 10/06313: {Resource planning in a project environment}
- G06Q 50/02: Agriculture; Fishing; Forestry; Mining
- G06Q: INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR

## Abstract

A server configured to, upon receiving from a user terminal a work relief request demand with respect to a predetermined work plan, select from among work reliever candidates a work reliever candidate who possesses a farm machine required for carrying out the predetermined work plan, and to notify the selected work reliever candidate that the relief request has been made. A work reliever candidate terminal configured to, upon being notified by the server that the relief request has been made, display the predetermined work plan and be able to provide the server with the intention of the work reliever candidate using the work reliever candidate terminal.

## Claims

### Claim 1

A work reliever mediation system comprising:
a server including:
a first storage unit configured to store work plan information including a scheduled work date, a work target field, and a work name for each user and for each work scheduled by the user;
a second storage unit configured to store work plan information including a scheduled work date, a work target field, and a work name for each work reliever candidate and for each work scheduled by the work reliever candidate; and
a third storage unit configured to store farm machine information that indicates a farm machine possessed by the work reliever candidate for each work reliever candidate;
a user terminal configured to transmit a relief request demand including a predetermined work plan to the server in a case where the user requests relief with respect to the predetermined work plan; and
a reliever candidate terminal configured to enable the work reliever candidate to communicate with the server, wherein
the server is configured to, based on receipt of the relief request demand from the user terminal:
select, from among the work reliever candidates, a work reliever candidate who possesses a farm machine configured to carry out the predetermined work plan, and
notify the selected work reliever candidate that a request for relief is made, and
in a case where the server notifies the reliever candidate terminal that the relief is requested, the reliever candidate terminal is configured to display the predetermined work plan and provide the server with an indication of intention of the work reliever candidate who uses the reliever candidate terminal.

### Claim 2 (depends on 1)

The work reliever mediation system according to claim 1, wherein the user terminal and the reliever candidate terminal are configured to negotiate work relief through the server after the server notifies the reliever candidate terminal that the request is made.

### Claim 3 (depends on 1)

The work reliever mediation system according to claim 1, wherein, when a final work reliever candidate who performs work relief with respect to the relief request demand is determined, the server adds the predetermined work plan to a work plan of the final work reliever candidate.

### Claim 4

A farm machine sharer mediation system comprising:
a server including:
a first storage unit configured to store work plan information including a scheduled work date, a work target field, and a work name for each user and for each work scheduled by the user; and
a second storage unit configured to store, for each farm machine sharer candidate, a farm machine possessed by the farm machine sharer candidate;
a user terminal configured to transmit a share request demand including a predetermined work plan to the server in a case where the user requests farm machine share with respect to the predetermined work plan; and
a sharer candidate terminal configured to enable the farm machine sharer candidate to communicate with the server, wherein
the server is configured to:
select, as a sharer candidate and based on receipt of the share request demand from the user terminal, the farm machine sharer candidate who possesses a farm machine configured to carry out the predetermined work plan, and
notify the selected farm machine sharer candidate that a share request is made, and
in a case where the server notifies the sharer candidate terminal that the share request is made, the sharer candidate terminal is configured to display the predetermined work plan and provide the server with an indication of intention of the farm machine sharer candidate who uses the sharer candidate terminal.

### Claim 5 (depends on 4)