# US 2022/0034058 A1 · Multiple friction joint pile system

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2022/0034058 A1
- Document ID: US20220034058A1
- Status: Published application
- Kind: A1
- Application number: 17/275,469
- Filed: 2019-09-04
- Published: 2022-02-03
- Earliest claimed: 2018-09-12
- Inventors: Ibrahim Gokhan BAYKAL
- Web page: https://patentgrep.com/patent/US20220034058A1

## CPC

- E02D 5/526: {Connection means between pile segments}
- E02D 17/20: Securing of slopes or inclines {(by soil E02D3/12; protection against snowslides or avalanches E01F7/04, E01F15/00; securing banks or like surfaces facing on bodies of water E02B3/12)}
- E02D 5/22: Piles (sheet piles, {i.e. elements shaped to mutually lock or mate} E02D5/02; {pile shoes E02D5/72; foundations on piles E02D27/12, E02D27/20})
- E02D 5/24: Prefabricated piles
- E02D 5/52: Piles composed of separable parts, e.g. telescopic tubes {; Piles composed of segments}
- E02D 17/207: {with means incorporating sheet piles or piles}
- E02D 31/02: against ground humidity or ground water {(E02D31/06 takes precedence; arrangements other than according to E02D31/04; against hydraulic pressure of groundwater E02D31/10)}
- E02D 2300/0034: in wire form
- E02D 2600/20: comprising details of connection between elements
- E02D: FOUNDATIONS; EXCAVATIONS; EMBANKMENTS (specially adapted for hydraulic engineering E02B); UNDERGROUND OR UNDERWATER STRUCTURES {(tunnels, tunnelling, mining E21)}

## Abstract

Disclosed is a multiple friction joint pile connection construction system to construct: shallow and deep foundations for structures, tie beam construction between footings, passive piles to prevent slope failures beam on elastic foundation, pile cap and tie beam in the construction of pile groups, load transfer platforms isolated (not connected) from the upper structure, retaining structure when constructed with vertical and horizontal orientation, vertical and horizontal drain when perforated blocks are used, landing pier, quay wall and platform construction for coastal and harbor structures, by anchoring to the upper section of the existing bored piles, by anchoring to the upper sections of the columns of the upper structure, in railroad tie manufacture, in transportation structures and in all kinds of similar geotechnical applications.

## Claims

### Claim 1

Multiple friction joint pile system, comprising at least two carrier elements, at least one twisted wire duct, a flexible plate, twisted wire of desired thickness in the amount of the rope ducts, a twisted wire tightening-loosening apparatus and a twisted wire fastening apparatus in the amount of the twisted wires.

### Claim 2 (depends on 1)

The system of claim 1, wherein the bearing element is made of wood, steel, composite, stone-filled cage, concrete and/or reinforced concrete.

### Claim 3 (depends on 1)

The system of claim 1, wherein safety rope, steel rope, thick rope, or thick steel wire is used for the twisted wire.

### Claim 4 (depends on 1)

Multiple friction joint pile system of claim 1, wherein it can also be used without a flexible plate.

### Claim 5 (depends on 1)

The system of claim 1, wherein a material that allows stretching such as rubber, cut waste car tire, geofoam, plastic, membrane (geomembrane) can be used.

### Claim 6 (depends on 1)

The system of claim 1, wherein the flexible can be placed as a plate between the bearing elements of the structure or it can be completely and/or partially coated (or fixed) to the bearing element.

### Claim 7 (depends on 1)

The system of claim 1, wherein the bearing element comprises at least one twisted wire duct positioned at any point on the concrete block and it is composed of at least two pieces comprising of a twisted wire long enough to connect the bearing elements passing through the twisted wire duct in the amount to meet the need.

### Claim 8 (depends on 1)

The system of claim 1, wherein the rope is monolithic and/or two pieces (or more) structure.

### Claim 9 (depends on 1)

The multiple friction joint pile system of claim 1, wherein the diameter of the rope duct is bigger than the diameter of the rope to allow lateral displacement.

### Claim 10 (depends on 1)

The system of claim 1, wherein the at least one flexible plate is placed between two bearing elements and used to minimize the vibration of the bearing elements.

### Claim 11 (depends on 1)

The system of claim 1, wherein the twisted wire with sufficient amount of bearing elements, used to hold the system together by passing it through the twisted wire duct located on the bearing elements and the flexible plates placed between it.

### Claim 12 (depends on 1)

The friction joint pile system of claim 1, wherein the twisted wire contains a rope tightening and loosening apparatus which can be adjusted by loosening and tightening from the upper part (or lower part).

### Claim 13 (depends on 1)

The friction joint pile system of claim 1, wherein the twisted wire contains a fastening system ensuring the fastening of the rope, located on the lower part (or upper part).

### Claim 14 (depends on 1)

The friction joint pile system of claim 1, wherein the system is connected together with the bearing element and the flexible plates positioned between said bearing element and the twisted wire used to keep the system together by passing through the bearing elements and the flexible plates and twisted wire tightening and loosening apparatus, which is connected to said twisted wire on the upper section, and the twisted wire fastening apparatus, which is connected from the bottom.

### Claim 15 (depends on 1)

The friction joint pile system of claim 1, wherein its operation in the event of axial shift is shown, wherein only the element under the effect of the force among the bearing elements, where the bearing elements are exposed to lateral force F in any direction moves.

### Claim 16 (depends on 1)

The friction joint pile system of claim 1, wherein when the twisted wire is overloaded inside the multiple friction joint pile system, it can be loosened with the help of the twisted wire tightening and loosening apparatus located on the upper part to reduce the load on the twisted wire and similarly, when the twisted wire is to be tightened, twisted wire tightening and loosening apparatus can be tightened to the desired tension.

### Claim 17 (depends on 1)

The friction joint pile system of claim 1, wherein the segmental structure of the system eliminates the breaking and/or cracking possibility of the pile placed under the structure.

### Claim 18 (depends on 1)

The friction joint pile system of claim 1, wherein it withstands the torsional forces with the frictional force in the joint planes, and exceeding this strength does not cause the pile to twist, but only the bearing element affected by the torsional moment will only rotate.

### Claim 19 (depends on 1)

The friction joint pile system of claim 1, wherein drainage ducts (holes) are formed in the horizontal and vertical directions of the bearing elements allowing the use of the column for drainage in the horizontal and vertical directions.

### Claim 20 (depends on 1)

The friction joint pile system of claim 1, wherein piles are created by using one or more geogrids instead of geomembranes between the bearing elements (100) and the geogrids can be connected to each other from the upper region and/or the lower region of the jointed column (or any desired level).