# US 2021/0334428 A1 · Method for prediction of dynamic rescheduling with digital twin workshop for circuit breaker and system using the same

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2021/0334428 A1
- Document ID: US20210334428A1
- Status: Published application
- Kind: A1
- Application number: 17/015,032
- Filed: 2020-09-08
- Published: 2021-10-28
- Earliest claimed: 2020-04-24
- Assignees: Technology Institute of Wenzhou University, Yueqing
- Applicants: Technology Institute of Wenzhou University, Yueqing
- Inventors: Liang Shu; Yanfang Yang; Miao Yang; Dingfang Chen; Shasha Li; Zhenquan Lin; Guichu Wu; Xiangou Zhu
- Web page: https://patentgrep.com/patent/US20210334428A1

## CPC

- G06F 30/18: Network design, e.g. design based on topological or interconnect aspects of utility systems, piping, heating ventilation air conditioning [HVAC] or cabling (circuit design at the physical level G06F30/39; network planning tools for wireless communication networks H04W16/18)
- G06F 30/367: Design verification, e.g. using simulation, simulation program with integrated circuit emphasis [SPICE], direct methods or relaxation methods
- G06F 2111/10: Numerical modelling
- G06F 2113/04: Power grid distribution networks
- G06F 2119/06: Power analysis or power optimisation
- G06F 2119/18: Manufacturability analysis or optimisation for manufacturability
- Y02P 90/02: Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
- G06F: ELECTRIC DIGITAL DATA PROCESSING (computer systems based on specific computational models G06N)
- Y02P: CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS

## Abstract

A method for prediction of dynamic rescheduling with a digital twin workshop for circuit breakers includes: building a circuit breaker digital manufacturing twin workshop system; determining a circuit breaker circuit breaker workshop dynamic rescheduling mathematical model that is based on rush order events, and performing prediction of information related to the rush order events on twin data of the circuit breaker digital manufacturing twin workshop system based on a prediction mechanism that relies on time window setting and order inquiry, and further updating the circuit breaker workshop dynamic rescheduling mathematical model with the predicted information related to the rush order events; and based on the updated circuit breaker workshop dynamic rescheduling mathematical model, developing a workshop dynamic rescheduling prediction model for multi-objective optimization focused on production efficiency and equipment energy consumption, and further finding an optimal solution to the workshop dynamic rescheduling prediction model using a multi-objective backtracking optimization algorithm, thereby obtaining a final dynamic rescheduling prediction scheme.

## Claims

### Claim 1

A method for prediction of dynamic rescheduling with a digital twin workshop for circuit breakers, the method comprising steps of:
Step S1: performing multi-granularity mapping, movement control and scene optimization on a circuit breaker workshop, and building a circuit breaker digital manufacturing twin workshop system;
Step S2: determining a circuit breaker workshop dynamic rescheduling mathematical model that is based on rush order events, predicting times and contents of the rush order events according to real-time twin data provided by the circuit breaker digital manufacturing twin workshop system based on a prediction mechanism that relies on time window setting and order inquiry, and further updating the circuit breaker workshop dynamic rescheduling mathematical model with the predicted times and content of the rush order events; and
Step S3: based on the updated circuit breaker circuit breaker workshop dynamic rescheduling mathematical model, using a multi-objective backtracking optimization algorithm, together with a random key encoding and plug-in decoding method, efficiently finding a solution to the circuit breaker circuit breaker workshop dynamic rescheduling mathematical model in a distributed computing platform, thereby obtaining an optimal dynamic rescheduling prediction scheme.

### Claim 2 (depends on 1)

The method of claim 1, wherein the step of performing multi-granularity mapping, movement control and scene optimization on a circuit breaker workshop is achieved by:
performing workshop geometric texture modeling, workshop hierarchy modeling, workshop equipment action modeling, workshop semantic modeling, workshop movement control and workshop scene optimization for the circuit breaker workshop.

### Claim 3 (depends on 1)

The method of claim 1, wherein the circuit breaker workshop dynamic rescheduling mathematical model based on the rush order events is generated through automatic update based on a predefined circuit breaker workshop production dynamic scheduling rule, in which
the circuit breaker workshop production dynamic scheduling rule includes: generating and executing an initial scheduling scheme first, if one said rush order event arrives or a future more optimal scheduling scheme is found, decoding and executing a corresponding rescheduling scheme, and further re-performing rescheduling prediction; and if no said rush order events arrive or no future more optimal scheduling schemes are found, performing corresponding rescheduling prediction based on variation of prediction time sections in a time window, until production operation in the workshop stops.

### Claim 4 (depends on 1)

The method of claim 1, wherein the times of the rush order events are predicted based on the time window setting, and the contents of the rush order events are predicted based on the order inquiry.

### Claim 5 (depends on 4)

The method of claim 4, wherein the time window setting is achieved by:
dividing operation time of the circuit breaker workshop into plural prediction time sections, and acquiring all the prediction time sections in a given future time period during real-time operation for production of the circuit breakers as times at which dynamic rush order events happen.

### Claim 6 (depends on 4)

The method of claim 4, wherein the order inquiry is achieved by:
checking all normal order events that are likely to cut in in the future, generating n+1 states including a “no new order cut in” state and “new order cut in” states for new orders J1˜Jn, in which the no new order cut in state is for real-time optimization of subsequent production operation in the workshop when there is an absence of said rush orders, and the new order cut in state is for optimization prediction of the rescheduling scheme after each said order event cuts in.

### Claim 7

A system for prediction of dynamic rescheduling with a digital twin workshop for circuit breakers, the system comprising a workshop system building unit, a mathematical model developing and updating unit, and a dynamic rescheduling scheme solution-finding unit,
the workshop system building unit, serving to perform multi-granularity mapping, movement control and scene optimization on a circuit breaker workshop, and building a circuit breaker digital manufacturing twin workshop system;
the mathematical model developing and updating unit, serving to determine a circuit breaker workshop dynamic rescheduling mathematical model based on rush order events, to predict times and contents of the rush order events according to real-time twin data provided by the circuit breaker digital manufacturing twin workshop system based on a prediction mechanism that relies on time window setting and order inquiry, and to further update the circuit breaker workshop dynamic rescheduling mathematical model according to the predicted times and contents of the rush order events; and
the dynamic rescheduling scheme solution-finding unit, serving to efficiently find a solution to the circuit breaker workshop dynamic rescheduling mathematical model in a distributed computing platform based on the updated circuit breaker workshop dynamic rescheduling mathematical model, using a multi-objective backtracking optimization algorithm, together with a random key encoding and plug-in decoding method, thereby obtaining an optimal dynamic rescheduling prediction scheme.

### Claim 8 (depends on 7)

The system of claim 7, wherein the circuit breaker workshop dynamic rescheduling mathematical model based on the rush order events is generated through automatic update based on a predefined circuit breaker workshop production dynamic scheduling rule.

### Claim 9 (depends on 8)

The system of claim 8, wherein the times of the rush order events are predicted based on the time window setting, and the contents of the rush order events are predicted based on the order inquiry.