# US 2021/0281215 A1 · Current cyclical testing for pv electrical connections

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2021/0281215 A1
- Document ID: US20210281215A1
- Status: Published application
- Kind: A1
- Application number: 16/807,312
- Filed: 2020-03-03
- Published: 2021-09-09
- Earliest claimed: 2020-03-03
- Assignees: SunPower Corporation
- Applicants: SunPower Corporation
- Inventors: Yafu Lin; Ryan Reagan; Itai Suez; Katherine Han; Hai-Yue Han
- Web page: https://patentgrep.com/patent/US20210281215A1

## CPC

- H02S 50/10: Testing of PV devices, e.g. of PV modules or single PV cells (testing of semiconductor devices during manufacturing {H10P74/00})
- G01R 31/66: Testing of connections, e.g. of plugs or non-disconnectable joints (testing for incorrect line connections G01R31/55)
- H10F 19/908: {for back-contact photovoltaic cells}
- H02S 40/36: characterised by special electrical interconnection means between two or more PV modules, e.g. electrical module-to-module connection
- Y02E 10/50: Photovoltaic [PV] energy
- H02S: GENERATION OF ELECTRIC POWER BY CONVERSION OF INFRARED RADIATION, VISIBLE LIGHT OR ULTRAVIOLET LIGHT, e.g. USING PHOTOVOLTAIC [PV] MODULES (obtaining electrical energy from radioactive sources G21H1/12; light sensitive inorganic semiconductor devices H10F; light sensitive organic semiconductor devices H10K30/00; thermoelectric devices H10N10/00; pyroelectric devices H10N15/00)
- G01R: MEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES (indicating correct tuning of resonant circuits H03J3/12)
- H10F: INORGANIC SEMICONDUCTOR DEVICES SENSITIVE TO INFRARED RADIATION, LIGHT, ELECTROMAGNETIC RADIATION OF SHORTER WAVELENGTH OR CORPUSCULAR RADIATION
- Y02E: REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION

## Abstract

Cyclical testing of electrically conductive bonding (ECB) is provided. Cyclical testing comprises high current flows using multiples of max operating currents and monitoring sensors with periods of no current to accelerate testing of electrical connections employing ECBs.

## Claims

### Claim 1

An electrically conductive bond test management controller comprising:
a processing unit; and
system memory,
wherein the system memory comprises instructions, which when executed, cause the processing unit to perform functions comprising:
determining whether a number of complete test cycles of one or more electrically conductive bond (ECB) of an ECB test piece has been reached or has not been reached, the ECB test piece located in a test chamber;
if a determination is made that the number of complete test cycles has not been reached, performing a no current test on the ECB test piece for a first period of time and performing an imposed current test on the ECB test piece during a second period of time,
during the imposed current test, receiving and analyzing signals from thermal sensors and voltage sensors or current sensors, the thermal sensors and voltage sensors or current sensors sensing temperature, and voltage or current, of one or more ECB connections on the ECB test piece; and
commanding a power supply to provide a high-current to the one or more ECB connections, the high-current exceeding the maximum short-circuit current for at least one ECB connection of the one or more ECB connections.

### Claim 2 (depends on 1)

The controller of claim 1 wherein the system memory further comprises instructions, which when executed, cause the processing unit, during the imposed current test, to compare the received signals to a safety value, and when a received signal exceeds a safety value threshold, to stop commanding the power supply to provide the high-current.

### Claim 3 (depends on 1)

The controller of claim 1 wherein the second time period is longer than the first time period.

### Claim 4 (depends on 1)

The controller of claim 1 wherein the system memory further comprises instructions, which when executed,
cause the processing unit to determine the temperature, during the no current test, and
to maintain active operation of a cooling system in the test chamber,
the cooling system sized to lower the temperature of one or more ECB connections on the ECB test piece.

### Claim 5 (depends on 1)

The controller of claim 1 wherein instructions, which when executed, cause the processing unit to perform functions further comprising: determining the temperature and voltage or current for each ECB connection of the ECB test piece.

### Claim 6 (depends on 1)

The controller of claim 1 wherein the ECB test piece comprises a plurality of photovoltaic cells.

### Claim 7 (depends on 1)

The controller of claim 1 wherein during the imposed current test, the signals from thermal sensors and voltage sensors or current sensors are received via a test chamber interface, the interface comprising a processing unit and electrically coupled to the thermal sensors, and the voltage sensors or the current sensors, of the test chamber.

### Claim 8 (depends on 1)

The controller of claim 1 wherein the high-current exceeds three-times the maximum short-circuit current for at least one ECB connection of the one or more ECB connections.

### Claim 9 (depends on 1)

The controller of claim 1 wherein the high-current exceeds six-times the maximum short-circuit current for at least one ECB connection of the one or more ECB connections.

### Claim 10

An electrically conductive bond test manager system comprising:
a processing unit; and
system memory,
wherein the system memory comprises instructions, which when executed, cause the processing unit to perform functions comprising:
determining whether a number of complete test cycles of electrically conductive bonding (ECB) on an ECB test piece has been reached or has not been reached, the ECB test piece located in a test chamber;
if a determination is made that the number of complete test cycles has not been reached, performing a no current test on the ECB test piece for a first period of time and performing an imposed current test on the ECB test piece during a second period of time,
during the imposed current test, receiving and analyzing signals from thermal sensors and voltage sensors or current sensors, the thermal sensors and voltage sensors or current sensors sensing temperature, and voltage or current, of one or more ECB connections on the ECB test piece; and
commanding a power supply to provide a high-current to the one or more ECB connections, the high-current exceeding the maximum short-circuit current for at least one ECB connection of the one or more ECB connections.

### Claim 11 (depends on 10)

The system of claim 10 wherein the system memory further comprises instructions, which when executed, cause the processing unit, during the imposed current test, to compare the received signals to a safety value, and when a received signal exceeds a safety value threshold, to stop commanding the power supply to provide the high-current.

### Claim 12 (depends on 10)

The system of claim 10 wherein the second time period is longer than the first time period.

### Claim 13 (depends on 10)

The system of claim 10 wherein the system memory further comprises instructions, which when executed,
cause the processing unit to determine the temperature, during the no current test, and
to maintain active operation of a cooling system in the test chamber,
the cooling system sized to lower the temperature of one or more ECB connections on the ECB test piece.

### Claim 14 (depends on 10)

The system of claim 10 wherein instructions, which when executed, cause the processing unit to perform functions further comprising: determining the temperature and voltage or current for each ECB connection of the ECB test piece.

### Claim 15 (depends on 10)

The system of claim 10 wherein the ECB test piece comprises a plurality of photovoltaic (PV) cells.

### Claim 16 (depends on 10)

The system of claim 10 wherein, during the imposed current test, the signals from thermal sensors and voltage sensors or current sensors are received via a test chamber interface, the interface comprising a processing unit and electrically coupled to the thermal sensors, and the voltage sensors or the current sensors, of the test chamber.

### Claim 17 (depends on 10)

The system of claim 10 wherein the high-current exceeds three-times the maximum short-circuit current for at least one ECB connection of the one or more ECB connections.

### Claim 18 (depends on 10)

The system of claim 10 wherein the high-current exceeds six-times the maximum short-circuit current for at least one ECB connection of the one or more ECB connections.

### Claim 19

An electrically conductive bond (ECB) cyclical test process comprising:
determining whether a number of complete test cycles of an ECB photovoltaic (PV) test piece has been reached or has not been reached, the ECB PV test piece located in a test chamber;
if a determination is made that the number of complete test cycles has not been reached, performing a no current test on the ECB PV test piece for a first period of time and performing an imposed current test on the ECB PV test piece during a second period of time,
during the imposed current test, receiving and analyzing signals from thermal sensors and voltage sensors or current sensors, the thermal sensors and voltage sensors or current sensors sensing temperature, and voltage or current, of one or more ECB connections on the ECB PV test piece; and
commanding a power supply to provide a high-current to the one or more ECB connections, the high-current exceeding the maximum short-circuit current for at least one ECB connection of the one or more ECB connections.

### Claim 20 (depends on 19)

The process of claim 19 further comprising during the imposed current test, comparing the received signals to a safety value, and when a received signal exceeds a safety value threshold, to stop commanding the power supply to provide the high-current.