# US 2021/0277751 A1 · Methods and systems for hanging structures in downhole environments

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2021/0277751 A1
- Document ID: US20210277751A1
- Status: Published application
- Kind: A1
- Application number: 16/809,858
- Filed: 2020-03-05
- Published: 2021-09-09
- Earliest claimed: 2020-03-05
- Assignees: Baker Hughes Oilfield Operations LLC
- Inventors: Zhiyue Xu; Guijun Deng; Oleksandr Kuznetsov; Deepak Kumar
- Web page: https://patentgrep.com/patent/US20210277751A1

## CPC

- E21B 23/01: for anchoring the tools or the like (E21B23/02 - E21B23/06 take precedence; anchoring of drives in the borehole E21B4/18)
- E21B 43/106: {Couplings or joints therefor}
- E21B 17/08: Casing joints
- E21B 43/10: Setting of casings, screens, liners {or the like} in wells
- E21B: EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS

## Abstract

Downhole hanger systems and methods for hanging a first structure from a second structure in downhole environments are described. The systems include a first structure and a second structure, with the first structure disposed within the second structure. A composite joint is arranged on an outer surface of the first structure. The composite joint is formed of a material configured to be fused to both the first structure and the second structure and form a hanger joint having a shear strength of at least 2 ksi when the material is fused to the outer surface of the first structure and an inner surface of the second structure.

## Claims

### Claim 1

A downhole hanger system comprising:
a first structure;
a second structure, wherein the first structure is disposed within the second structure; and
a composite joint arranged on an outer surface of the first structure, wherein the composite joint is formed of a material configured to be fused to both the first structure and the second structure and having a shear strength of at least 2 ksi when the material is fused to the outer surface of the first structure and an inner surface of the second structure.

### Claim 2 (depends on 1)

The downhole hanger system of claim 1, wherein the first structure is a liner and the second structure is a casing.

### Claim 3 (depends on 1)

The downhole hanger system of claim 1, wherein the material of the composite joint is a self-energizing material that is configured to be triggered to fuse the first structure to the second structure.

### Claim 4 (depends on 1)

The downhole hanger system of claim 1, further comprising:
a surface-based high energy source;
a high energy delivery device; and
a downhole high energy application head,
wherein the high energy delivery device operably connects the surface-based high energy source to the downhole high energy application head.

### Claim 5 (depends on 4)

The downhole hanger system of claim 4, wherein the surface-based high energy source is one of a millimeter wave (MMW) gyrotron and a kilowatt laser beam source.

### Claim 6 (depends on 4)

The downhole hanger system of claim 4, wherein the high energy delivery device is one of an optical fiber and a wave guide.

### Claim 7 (depends on 4)

The downhole hanger system of claim 4, wherein the downhole high energy application head is configured to be moveable both axially relative to an axis of the first structure and rotationally about said axis.

### Claim 8 (depends on 4)

The downhole hanger system of claim 4, wherein the downhole high energy application head comprises a beam collimate lens and a beam focus lens.

### Claim 9 (depends on 1)

The downhole hanger system of claim 1, wherein the composite joint comprises a plurality of discrete elements distributed equally about the outer surface of the first structure.

### Claim 10 (depends on 1)

The downhole hanger system of claim 1, further comprising a seal arranged on the outer surface of the first structure and at a position closer uphole from the composite joint and configured to form a fluid seal uphole of the fused composite joint.

### Claim 11 (depends on 10)

The downhole hanger system of claim 10, wherein the seal is configured to be fused to the outer surface of the first structure and the inner surface of the second structure by application of high energy.

### Claim 12 (depends on 10)

The downhole hanger system of claim 10, wherein the seal is formed of a material that is a self-energizing material configured to be triggered to fuse the first structure to the second structure and form a fluid seal.

### Claim 13

A method for hanging a first structure from a second structure in a downhole environment, the method comprising:
deploying the first structure within the second structure, wherein the first structure includes a composite joint arranged on an outer surface of the first structure;
activating the composite joint to fuse the outer surface of the first structure to the second structure, wherein the composite joint is formed of a material configured to be fused to both the first structure and the second structure and having a shear strength of at least 2 ksi when the material is fused to the outer surface of the first structure and an inner surface of the second structure.

### Claim 14 (depends on 13)

The method of claim 13, wherein the material of the composite joint is a self-energizing material that is configured to be triggered to fuse the first structure to the second structure, the method further comprising:
performing a triggering operation to activate the composite joint.

### Claim 15 (depends on 13)

The method of claim 13, further comprising:
transmitting high energy from a surface-based high energy source, through a high energy delivery device, to a downhole high energy application head to apply the high energy to the material of the composite joint.

### Claim 16 (depends on 15)

The method of claim 15, wherein the surface-based high energy source is one of a millimeter wave (MMW) gyrotron, a kilowatt laser beam source, and an electric current sent by wireline to an electronic-match.

### Claim 17 (depends on 15)

The method of claim 15, wherein the downhole high energy application head is configured to be moveable both axially relative to an axis of the first structure and rotationally about said axis, the method further comprising:
controlling movement of the downhole high energy application head to apply the high energy to the material of the composite joint.

### Claim 18 (depends on 13)

The method of claim 13, wherein the composite joint comprises a plurality of discrete elements distributed equally about the outer surface of the first structure.

### Claim 19 (depends on 13)

The method of claim 13, further comprising a seal arranged on the outer surface of the first structure and at a position closer to the Earth's surface than the composite joint and configured to form a fluid seal uphole from the fused composite joint.

### Claim 20 (depends on 19)

The method of claim 19, the method further comprising applying high energy to the seal to fuse to the outer surface of the first structure and the inner surface of the second structure.