# US 2021/0268690 A1 · Method for Casting a Construction Element

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2021/0268690 A1
- Document ID: US20210268690A1
- Status: Published application
- Kind: A1
- Application number: 17/320,341
- Filed: 2021-05-14
- Published: 2021-09-02
- Earliest claimed: 2013-02-21
- Assignees: Laing O'Rourke Australia Pty Limited
- Applicants: Laing O'Rourke Australia Pty Limited
- Inventors: James Bruce Gardiner; Steven Robert Janssen
- Web page: https://patentgrep.com/patent/US20210268690A1

## CPC

- B28B 7/346: {Manufacture of moulds}
- B25J 11/00: Manipulators not otherwise provided for
- B28B 1/14: by simple casting, the material being neither forcibly fed nor positively compacted (for molten material B28B1/54)
- B28B 7/342: {which are at least partially destroyed, e.g. broken, molten, before demoulding; Moulding surfaces or spaces shaped by, or in, the ground, or sand or soil, whether bound or not; Cores consisting at least mainly of sand or soil, whether bound or not}
- B28B 7/362: {specially for making moulded articles from concrete with exposed aggregate}
- B28B 23/022: {Means for inserting reinforcing members into the mould or for supporting them in the mould (inserting during extrusion B28B3/2645)}
- B29C 64/106: using only liquids or viscous materials, e.g. depositing a continuous bead of viscous material
- B29C 64/118: using filamentary material being melted, e.g. fused deposition modelling [FDM]
- B29C 64/188: involving additional operations performed on the added layers, e.g. smoothing, grinding or thickness control (surface shaping B29C59/00; after-treatment of articles without altering their shape B29C71/00)
- E04G 11/00: Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs {(for prefabrication of concrete elements in a plant B28B7/00)}
- E04G 21/0463: {with boom control mechanisms, e.g. to automate concrete distribution}
- B33Y 10/00: Processes of additive manufacturing
- B33Y 80/00: Products made by additive manufacturing
- E04B 1/3505: {characterised by the in situ moulding of large parts of a structure (E04B1/3511, E04B1/3516, E04B1/3522, E04B1/3533, E04B1/3544, E04B1/355 take precedence)}
- F24D 3/14: incorporated in a ceiling, wall or floor
- Y02B 30/00: Energy efficient heating, ventilation or air conditioning [HVAC]
- Y02P 10/25: Process efficiency
- B28B: SHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER (foundry moulding B22C; working stone or stone-like material B28D; shaping of substances in a plastic state, in general B29C; making layered products not composed wholly of these substances B32B)
- B25J: MANIPULATORS; CHAMBERS PROVIDED WITH MANIPULATION DEVICES ({manipulators specially adapted for use in surgery A61B34/70; manipulators used in cleaning hollow articles B08B9/04}; manipulators associated with rolling mills B21B39/20; manipulators associated with forging machines B21J13/10; {manipulators associated with picking-up and placing mechanisms B23P19/007}; means for holding wheels or parts thereof B60B30/00; {vehicles with ground-engaging propulsion means, e.g. walking members B62D57/02, B62D57/032; devices for picking-up and depositing articles or materials between conveyors B65G47/90, B65G47/91; manipulators with gripping or holding means for transferring packages B65H67/065}; cranes B66C; {manipulators used in the protection or supervision of pipe-line installations F17D5/00; walking equipment adapted for nuclear steam-generators F22B37/006}; manipulators specially adapted for, or associated with, nuclear reactors G21C; {apparatus used for handling wafers during manufacture or treatment of semiconductor H10P72/50})
- B29C: SHAPING OR JOINING OF PLASTICS; SHAPING OF MATERIAL IN A PLASTIC STATE, NOT OTHERWISE PROVIDED FOR; AFTER-TREATMENT OF THE SHAPED PRODUCTS, e.g. REPAIRING (making preforms B29B11/00; making laminated products by combining previously unconnected layers which become one product whose layers will remain together B32B37/00 - B32B41/00)
- E04G: SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- B33Y: ADDITIVE MANUFACTURING, i.e. MANUFACTURING OF THREE-DIMENSIONAL [3D] OBJECTS BY ADDITIVE DEPOSITION, ADDITIVE AGGLOMERATION OR ADDITIVE LAYERING, e.g. BY 3D PRINTING, STEREOLITHOGRAPHY OR SELECTIVE LASER SINTERING
- E04B: GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS (border constructions of opening in walls, floors or ceilings E06B1/00; {electromagnetic shielding H05K9/0001})
- F24D: DOMESTIC- OR SPACE-HEATING SYSTEMS, e.g. CENTRAL HEATING SYSTEMS; DOMESTIC HOT-WATER SUPPLY SYSTEMS; ELEMENTS OR COMPONENTS THEREFOR (using steam or condensate extracted or exhausted from steam engine plants for heating purposes F01K17/02)
- Y02B: CLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
- Y02P: CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS

## Abstract

The present invention relates to a method for casting building material to form a construction element using a computer-controlled apparatus. The method comprises the steps of: moving the material deposition head and selectively depositing material, to fabricate a formwork; pouring building material in contact with at least a portion of the formwork; at least partially curing the building material, thereby forming the construction element; and removing at least a portion of the formwork from the construction element.

## Claims

### Claim 1

A method for casting building material to form a construction element using a computer-controlled apparatus, the apparatus having a material deposition head in communication with a reservoir of formwork material and being movable within a build volume responsive to computer instructions, the method comprising the steps of:
receiving, by the apparatus, computer instructions relating to a formwork geometry;
moving the material deposition head within the build volume and selectively depositing formwork material in specific locations to fabricate a formwork corresponding with the formwork geometry;
pouring building material in contact with at least a portion of the formwork;
at least partially curing the building material in contact with the formwork to form the construction element; and
removing at least a portion of the formwork from the construction element.

### Claim 2 (depends on 1)

The method for casting building material to form a construction element according to claim 1, wherein the step of removing the formwork comprises heating the construction element and the formwork to a temperature above the melting point of the to melt the at least a portion of the formwork.

### Claim 3 (depends on 2)

The method for casting building material to form a construction element according to claim 2, comprising the further step of collecting and recirculating the melted formwork material to the reservoir.

### Claim 4 (depends on 2)

The method for casting building material to form a construction element according to claim 2, wherein the temperature is less than 70° C.

### Claim 5 (depends on 2)

The method for casting building material to form a construction element according to claim 2, wherein the formwork material is a wax compound.

### Claim 6 (depends on 1)

The method for casting building material to form a construction element according to claim 1, wherein the step of removing the formwork comprises spraying the formwork with a liquid to dissolve the at least a portion of the formwork.

### Claim 7 (depends on 1)

The method for casting building material to form a construction element according to claim 1, wherein the step of removing the formwork comprises at least partially submerging the construction element and the at least a portion of the formwork in a liquid to dissolve the at least a portion of the formwork.

### Claim 8 (depends on 1)

The method for casting building material to form a construction element according to claim 1, further comprising the step of selectively applying one or more materials in specific locations to affect a surface finish of the construction element to the formwork.

### Claim 9 (depends on 0)

The method for casting building material to form a construction element according to claim 0, wherein the one or more material include at least one of an acid, a pigment, paint, or masking.

### Claim 10 (depends on 1)

The method for casting building material to form a construction element according to claim 1, further comprising the steps of:
before pouring the building material, selectively applying a retarder to the formwork in specific locations; and
after the at least a portion of the formwork is removed from the construction element, removing uncured building material from the construction element by mechanical means.

### Claim 11 (depends on 0)

The method for casting building material to form a construction element according to claim 0, wherein the apparatus further has a milling head movable within the build volume responsive to computer instructions, and the method further comprises the step of, before pouring the building material, selectively milling, by the apparatus, the formwork in specific locations.

### Claim 12 (depends on 1)

The method for casting building material to form a construction element according to claim 1, wherein the step of moving the material deposition head to fabricate the formwork comprises the further sub-step of moving the material deposition head to fabricate a scaffold structure at least partially enclosed by a shell, the scaffold structure and shell thereby forming the formwork.

### Claim 13 (depends on 12)

The method for casting building material to form a construction element according to claim 12, wherein the scaffold structure comprises a network of interconnected braces.

### Claim 14 (depends on 12)

The method for casting building material to form a construction element according to claim 12, wherein the scaffold structure defines at least one conduit arranged to allow a fluid to pass through the formwork.

### Claim 15 (depends on 0)

The method for casting building material to form a construction element according to claim 0, wherein the step of moving the material deposition head to fabricate the formwork comprises the further sub-step of selectively heating or cooling at least a portion of the build volume.

### Claim 16 (depends on 1)

The method for casting building material to form a construction element according to claim 1, further comprising the step of:
before pouring the building material, selectively applying one or more portions of composite material to the formwork in specific locations;
such that after the at least a portion of the formwork is removed from the construction element, the one or more portions of composite material are secured to the construction element.

### Claim 17 (depends on 16)

The method for casting building material to form a construction element according to claim 16, further comprising the step of:
after selectively applying one or more portions of composite material selectively to the formwork, at least partially curing the one or more portions of composite material.

### Claim 18

A method for casting building material to form a construction element using a computer-controlled apparatus, the apparatus having a material deposition head in communication with a reservoir of formwork material and being movable within a build volume responsive to computer instructions, the method comprising the steps of:
receiving, by the apparatus, computer instructions relating to a first formwork geometry;
moving the material deposition head within the build volume and selectively depositing formwork material in specific locations to fabricate a first formwork corresponding with the formwork geometry;
selectively applying one or more portions of composite material to the first formwork in specific locations to form a homogenous layer of composite material;
curing the layer of composite material to form a composite element;
removing the first formwork from the composite element;
pouring a first building material in contact with at least a portion of the composite element; and
curing the first building material in contact with the composite element, thereby forming a first construction element.

### Claim 19 (depends on 18)

The method for casting building material to form a construction element according to claim 18 comprising the further steps of:
arranging a second formwork proximally to the first construction element;
pouring a second building material in contact with at least a portion of the first construction element and the second formwork;
curing the second building material in contact with the first construction element and the second formwork, thereby forming a second construction element joined to the first construction element; and
removing the second formwork from both construction elements.

### Claim 20 (depends on 19)

The method for casting building material to form a construction element according to claim 19, wherein the first and second building materials have a substantially identical composition.

### Claim 21 (depends on 16)

The method for casting building material to form a construction element according to claim 16 wherein the one or more portions of composite material are selectively applied to the formwork by a computer-controlled composite lay-up head movable responsive to computer instructions.

### Claim 22 (depends on 16)

The method for casting building material to form a construction element according to claim 16 wherein the composite material is a preimpregnated tape.

### Claim 23

A method for casting building material to form a construction element using a computer-controlled apparatus, the apparatus having a material deposition head in communication with a reservoir of formwork material and being movable within a build volume responsive to computer instructions, the method comprising the steps of:
receiving, by the apparatus, computer instructions relating to a first formwork geometry;
moving the material deposition head within the build volume and selectively depositing formwork material in specific locations to fabricate a first formwork corresponding with the first formwork geometry;
selectively applying one or more portions of composite material to the first formwork in specific locations;
curing the one or more portions of composite material to form one or more first composite elements;
receiving, by the apparatus, computer instructions relating to a second formwork geometry;
moving the material deposition head within the build volume and selectively depositing formwork material in specific locations to fabricate a second formwork corresponding with the second formwork geometry, the second formwork at least partially in contact with the first formwork or the one or more first composite elements;
selectively applying one or more portions of composite material to the second formwork in specific locations;
curing the one or more portions of composite material to form one or more second composite elements;
pouring building material in contact with at least a portion of the first and second formworks;
curing the building material in contact with the first and second formworks, thereby forming a construction element; and
removing the first and second formworks from the construction element.