# US 2021/0222495 A1 · Method and apparatus for the bottom-up construction of vertical risers from underground passes through the soil, using a pipe jacking equipment

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2021/0222495 A1
- Document ID: US20210222495A1
- Status: Published application
- Kind: A1
- Application number: 17/055,927
- Filed: 2018-05-16
- Published: 2021-07-22
- Earliest claimed: 2018-05-16
- Assignees: Salini Impregilo S.P.A.
- Applicants: Salini Impregilo S.P.A.
- Inventors: Nicola VALIANTE; Alberto BUFFA
- Web page: https://patentgrep.com/patent/US20210222495A1

## CPC

- E21D 9/1066: {with fluid jets (projecting hot gases E21D9/1073; drilling by liquid or gas jets E21B7/18; slitting by liquid jets E21C25/60)}
- E21B 7/18: Drilling by liquid or gas jets, with or without entrained pellets (E21B7/14 takes precedence)
- E21D 9/10: Making by using boring or cutting machines (E21D9/08 takes precedence; mining picks E21C35/18)
- E21D 3/00: Raising shafts, i.e. working upwards from the bottom
- E21D: SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS (soil-conditioning or soil-stabilising materials C09K17/00; drilling or cutting machines for mining or quarrying E21C; safety devices, transport, rescue, ventilation or drainage E21F)
- E21B: EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS

## Abstract

A “Riser Concept” Method and Apparatus includes the bottom-up construction of vertical risers from underground passes through the soil, using a pipe jacking equipment. The pipe jacking equipment vertically push the riser pipe from underground pass upwards through soil formations to waterbody, air intake, terrain surface or like. The method and mechanism can be applied either in traditionally bored tunnel or in tunnel bored by tunnel boring machine.

## Claims

### Claim 1

System for the bottom-up construction of vertical riser pipes from underground tunnels, passes or the like to an upper waterbody through the soil, wherein it comprises: one or more vertical risers pipes comprising at least three riser pipe segments; a pipe jacking equipment which is configured to install said one or more vertical riser pipes by pushing said at least three riser pipe segments into soil formations in the upward direction, from an underground pass/tunnel to an upper level, a load distribution system, configured to transfer thrust force to a tunnel structure during installation of said one ore more vertical riser pipes, and a displacement head configured to perform excavation and removal of soil, wherein said displacement head is equipped with a hydro-demolition system and a soil discharge line; wherein said displacement head is fastened, by means of removable connection elements, to a keystone launching segment equipped with a sealing system configured to connect, with a watertight connection each riser and the tunnel to allow underwater applications, and wherein said sealing system comprises lip gaskets and additional emergency seals, and is configured to ensure the water tightness between each of the vertical riser pipes or the displacement head, and the keystone launching segment.

### Claim 2 (depends on 1)

System according to claim 1, wherein it further comprises two special segment rings: a positioning segmental ring and a launching segmental ring, which are configured so that, considering the direction of the tunnel advance, the first ring is the positioning segmental ring, and the second ring is the launching segmental ring comprising said keystone launching segment.

### Claim 3 (depends on 2)

System according to claim 2, wherein the correct position of said keystone launching segment is adjustable by regulating the position of said segmental ring through slotted holes for longitudinally connecting said two special segment rings to each other, the provision of said slotted holes, enabling an on-site rotational adjustability of the position of the keystone launching segment.

### Claim 4 (depends on 1)

System according to claim 1, wherein said displacement head is initially fastened to said keystone launching segment, previously placed in a desired position for the installation of the vertical riser pipe.

### Claim 5

(canceled)

### Claim 6 (depends on 1)

Method for the bottom-up construction of vertical risers from underground tunnels, passes or the like, to an upper waterbody, air intake, terrain surface or the like through the soil by means of the system according to claim 1, wherein it comprises the following steps:
a) positioning of the special segmental rings, including said keystone launching segment, said displacement head and said sealing system;
b) positioning said pipe jacking equipment underneath said keystone launching segment;
c) placing the initial riser pipe segment onto a thrust platform;
d) connecting said initial riser pipe segment to the displacement head and holding said initial riser pipe segment in a desired position by means of a pipe clamp, and then disconnecting said displacement head from said keystone launching segment, by removing said removable connection elements;
e) hooking up of a high-pressure water system and a discharge line system to said displacement head passing through initial riser pipe segment;
f) starting operation of the pipe jacking equipment to drive/push said initial riser pipe segment through the soil, by means of said trust platform and of the hydro-demolition system of said displacement head provided with nozzles configured to spray pressurized water to weaken the soil structure in the penetration area of said displacement head;
g) removal of the high pressure water system and the discharge line system which have to be passed through each riser pipe segment and reconnected to said displacement head, before activating the pipe jacking equipment;
h) uniformly transferring the thrust force to the tunnel structure by said load distribution system.
i) placing a spacer under the initial riser pipe segment to drive the initial riser pipe segment trough the soil up to the required elevation;
j) blocking, in this position, said initial riser pipe segment by said pipe clamp;
k) removing the spacer and placing an intermediate riser pipe segment on the trust platform, and connecting said riser pipe segment to the preceding riser pipe segment; and
l) repeating the steps from e) to k) up to reach the desired elevation when the ending riser pipe segment has to be installed.

### Claim 7 (depends on 6)

Method according to claim 6, wherein before removing displacement head from the top of the initial riser pipe segment, a temporary bulkhead is installed at the bottom of the ending riser pipe segment to prevent water from entering in the tunnel.

### Claim 8 (depends on 7)

Method according to claim 7, wherein the final step comprises the removal of said displacement head, the installation of a diffuser at the top of the initial riser pipe segment, and the removal of the temporary bulkhead.

### Claim 9 (depends on 1)

System according to claim 1, wherein said at least three pipe riser segments include:
an initial riser pipe segment,
at least one intermediate riser pipe segment, and
an ending riser pipe segment,
wherein said initial riser pipe segment is configured to be connected to the displacement head before starting a jacking process;
wherein said ending rise pipe segment is configured to be connected to the tunnel structure at the completion of the jacking process, and to allow installation of a temporary bulkhead to prevent water from entering into the tunnel structure; and
wherein said at least three riser pipe segments are configured to sustain thrust forces and allow fast joint connection and water tightness of joints and smooth interface with the sealing system.