# US 2021/0218580 A1 · Method and Control System for Technical Installations with Certificate Management

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2021/0218580 A1
- Document ID: US20210218580A1
- Status: Published application
- Kind: A1
- Application number: 17/146,738
- Filed: 2021-01-12
- Published: 2021-07-15
- Earliest claimed: 2020-01-14
- Assignees: Siemens Aktiengesellschaft
- Applicants: Siemens Aktiengesellschaft
- Inventors: Benjamin LUTZ; Anna PALMIN
- Web page: https://patentgrep.com/patent/US20210218580A1

## CPC

- G05B 19/042: using digital processors (G05B19/05 takes precedence)
- H04L 9/3268: {using certificate validation, registration, distribution or revocation, e.g. certificate revocation list [CRL]}
- G05B 19/4185: {characterised by the network communication}
- H04L 9/3247: {involving digital signatures}
- G05B 2219/24163: Authentication tag in configuration file
- Y02P 90/02: Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
- G05B: CONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS (systems for controlling or regulating non-electric variables G05D; systems for regulating electric or magnetic variables G05F; control devices or systems insofar as characterised by mechanical features only G05G)
- H04L: TRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION (arrangements common to telegraphic and telephonic communication H04M)
- Y02P: CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS

## Abstract

A control system for a technical installation, in particular a manufacturing facility or process plant, includes at least one first operator station server and one second operator station server and is configured to initiate the issuance and revocation of certificates for components of the technical installation as part of certificate management, and is configured to publish revocation of a previously issued certificate within the control system as a certificate revocation list, where the control system is configured to store the certificate revocation list on the first operator station server and/or on the second operator station server, where the control system is configured to synchronize the first operator station server and the second operator station server with one another such that a certificate revocation list with identical content is stored on both operator station servers.

## Claims

### Claim 1

A control system for a technical installation, the control system comprising:
at least one first operator station server; and
a second operator station server;
wherein the control system is configured to initiate issuance and revocation of certificates for components of the technical installation as part of certificate management and configured to publish any revocation of a previously issued certificate within the control system as a certificate revocation list;
wherein the control system is further configured to store the certificate revocation list on at least one of (i) the at least one first operator station server and (ii) the second operator station server; and
wherein the control system is further configured to synchronize the at least one first operator station server and second operator station server with one another such that a certificate revocation list with identical content is stored on the first and second operator station servers.

### Claim 2 (depends on 1)

The control system as claimed in claim 1, wherein the control system further comprises:
a computer-implemented revocation service which initiates the revocation of certificates in an event-controlled and automated manner.

### Claim 3 (depends on 1)

The control system as claimed in claim 1, wherein a change in communication relationships between components of the technical system constitutes an event taken into account for initiating the revocation of certificates.

### Claim 4 (depends on 2)

The control system as claimed in claim 2, wherein a change in communication relationships between components of the technical system constitutes an event taken into account for initiating the revocation of certificates.

### Claim 5 (depends on 2)

The control system as claimed in claim 2, wherein the revocation service is configured to initiate revocation of certificates by said revocation service submitting a revocation request to a certification authority; and
wherein the revocation service is configured to one of (i) monitor processing of the revocation request and (ii) cause processing of the revocation request to be monitored.

### Claim 6 (depends on 1)

The control system as claimed in claim 1, further comprising:
at least one first component connected to at least one of (i) the at least one first operator station server and (ii) the second operator station server; and
at least one second component connected to at least one of (i) the first operator station server and (ii) the second operator station server;
wherein the at least one first component forms part of a first engineering project and the at least one second component forms part of a second engineering project;
wherein the control system is configured to store a first certificate revocation list specific to the first engineering project on at least one of (i) the at least one first operator station server and (ii) the second operator station server, and is configured to store a second certificate revocation list specific to the second engineering project on at least one of (i) the at least one first operator station server and (ii) the second operator station server; and
wherein the at least one first component has access solely to the first certificate revocation list and the at least one second component has access solely to the second certificate revocation list.

### Claim 7 (depends on 1)

The control system as claimed in claim 1, wherein the technical installation comprises one of a manufacturing facility and process plant.

### Claim 8

A method comprising:
a) initiating, by a control system of a technical installation, issuance of a certificate to a component of the technical installation, the control system having at least one first operator station server and a second operator station server;
b) initiating, by a computer-implemented revocation service of the control system of the technical installation, revocation of the certificate;
c) publishing the revocation of a previously issued certificate within the control system as a certificate revocation list which is stored on at least one of (i) the first operator station server and (ii) the second operator station server; and
d) synchronizing the at least one first operator station server and the second operator station server such that a certificate revocation list with identical content is stored on the first and second operator station servers.

### Claim 9 (depends on 8)

The method as claimed in claim 8, wherein a change in communication relationships between components of the technical system constitutes an event which triggers automated initiation of revocation of the certificate.

### Claim 10 (depends on 8)

The method as claimed in claim 8, wherein the revocation service submits a revocation request to a certification authority to initiate the revocation of certificates; and
wherein the revocation service one of (i) monitors the processing of the revocation request and (ii) instigates the monitoring of the revocation request.

### Claim 11 (depends on 9)

The method as claimed in claim 9, wherein the revocation service submits a revocation request to a certification authority to initiate the revocation of certificates; and
wherein the revocation service one of (i) monitors the processing of the revocation request and (ii) instigates the monitoring of the revocation request.