# US 2021/0083474 A1 · Optimal sparse placement of phasor measurement units and state estimation of key buses in distribution networks

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2021/0083474 A1
- Document ID: US20210083474A1
- Status: Published application
- Kind: A1
- Application number: 17/007,301
- Filed: 2020-08-31
- Published: 2021-03-18
- Earliest claimed: 2019-07-03
- Assignees: Bigwood Technology, Inc.; Tianjin University
- Applicants: Bigwood Technology, Inc.
- Inventors: Hsiao-Dong Chiang; Qiancheng Lv; Xiangyu Kong
- Web page: https://patentgrep.com/patent/US20210083474A1

## CPC

- G01R 19/2513: {Arrangements for monitoring electric power systems, e.g. power lines or loads; Logging}
- H02J 3/003: {Load forecast, e.g. methods or systems for forecasting future load demand}
- H02J 3/004: {Generation forecast, e.g. methods or systems for forecasting future energy generation}
- G06Q 10/04: Forecasting or optimisation specially adapted for administrative or management purposes, e.g. linear programming or "cutting stock problem" (market predictions or forecasting for commercial activities G06Q30/0202)
- H02J 3/00144: {using phasor measuring units [PMU]}
- H02J 13/12: Monitoring network conditions, e.g. electrical magnitudes or operational status
- H02J 2103/30: Simulating, planning, modelling, reliability check or computer assisted design [CAD] of electric power networks
- H02J 2103/35: Grid-level management of power transmission or distribution systems, e.g. load flow analysis or active network management
- Y02E 40/70: Smart grids as climate change mitigation technology in the energy generation sector
- Y02E 60/00: Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation
- Y04S 10/22: Flexible AC transmission systems [FACTS] or power factor or reactive power compensating or correcting units
- Y04S 10/30: State monitoring, e.g. fault, temperature monitoring, insulator monitoring, corona discharge
- Y04S 40/20: Information technology specific aspects, e.g. CAD, simulation, modelling, system security
- G01R: MEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES (indicating correct tuning of resonant circuits H03J3/12)
- H02J: ELECTRIC POWER NETWORKS; CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- G06Q: INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- Y02E: REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y04S: SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS

## Abstract

A method for state estimation of a distribution network comprises: (a) obtaining measurements from phasor measurement units (PMUs) placed at buses in the distribution network; (b) constructing a quotient gradient system (QGS) based on a constraint set H that relates the measurements to state variables of the distribution network; (c) integrating the QGS to reach a steady state; (d) identifying one or more of the state variables whose measurement residuals violate a measurement residual constraint in the constraint set H; (e) integrating a reconstructed QGS, which is reconstructed based on the constraint set H by setting the identified one or more state variables to values of corresponding PMU measurements; (f) iterating steps of (d) and (e) until no measurement residuals violate the measurement residual constraint, to thereby obtain the state estimation; and (g) reporting the state estimation to a control system during real-time monitoring of the distribution network.

## Claims

### Claim 1

A method for state estimation of a distribution network, comprising:
(a) obtaining measurements from a plurality of phasor measurement units (PMUs) placed at a plurality of buses in the distribution network;
(b) constructing a quotient gradient system (QGS) based on a constraint set H that relates the measurements to state variables of the distribution network;
(c) integrating the QGS to reach a steady state;
(d) identifying one or more of the state variables whose measurement residuals violate a measurement residual constraint in the constraint set H;
(e) integrating a reconstructed QGS, which is reconstructed based on the constraint set H by setting the identified one or more state variables to values of corresponding PMU measurements;
(f) iterating steps of (d) and (e) until no measurement residuals violate the measurement residual constraint, to thereby obtain a solution for the state variables as the state estimation; and
(g) reporting the state estimation to a control system during real-time monitoring of the distribution network.

### Claim 2 (depends on 1)

The method of claim 1, wherein the plurality of PMUs include a plurality of micro-PMUs.

### Claim 3 (depends on 1)

The method of claim 1, further comprising:
determining optimal placement of the PMUs at the buses by solving a nonlinear integer programming problem constrained by at least an observability requirement for a subset of the buses.

### Claim 4 (depends on 3)

The method of claim 3, wherein solving the nonlinear integer programming problem further comprises: performing discrete particle swarm optimization, clustering of particles, and local optimization.

### Claim 5 (depends on 3)

The method of claim 3, wherein determining the optimal placement further comprises:
identifying a minimal number and locations of the PMUs to be placed in the distribution network according to a requirement specifying that all predetermined key buses are observable from the measurements.

### Claim 6 (depends on 3)

The method of claim 3, wherein determining the optimal placement further comprises:
identifying locations of a predetermined number of PMUs to be placed in the distribution network according to requirements specifying that all predetermined key buses are observable from the measurements and observable non-key buses are maximized in number.

### Claim 7 (depends on 3)

The method of claim 3, wherein determining the optimal placement further comprises:
identifying locations of a predetermined number of PMUs to be placed in the distribution network according to a requirement specifying that observable key buses are maximized in number.

### Claim 8 (depends on 1)

The method of claim 1, wherein the state estimation includes voltage amplitudes and phase angles at a subset of the buses.

### Claim 9 (depends on 8)

The method of claim 8, wherein the subset of the buses includes key buses predetermined to be observable.

### Claim 10 (depends on 1)

The method of claim 1, further comprising:
determining optimal placement of the PMUs at the buses to satisfy an observability requirement, wherein the observability requirement is formulated with an observability vector that identifies whether each of the buses in the distribution network is to be observable.

### Claim 11 (depends on 1)

The method of claim 1, wherein the constraint set H comprises:
a function vector (HEmicro-PMU(x)) relating the measurements to the state variables, a power-balance function vector (HEzero(x)) representing zero-injection power measurements, and a measurement residual constraint function vector (HImicro-PMU(x)) relating the measurements to the measurement residual constraint.

### Claim 12 (depends on 1)

The method of claim 1, wherein the measurement residual constraints constrain a difference between calculated values of the state variables and corresponding PMU measurements.

### Claim 13

A non-transitory computer-readable storage medium including instructions that, when executed by a computer system, cause the computer system to perform state estimation of a distribution network, the computer system operative to:
(a) obtain measurements from a plurality of phasor measurement units (PMUs) placed at a plurality of buses in the distribution network;
(b) construct a quotient gradient system (QGS) based on a constraint set H that relates the measurements to state variables of the distribution network;
(c) integrate the QGS to reach a steady state;
(d) identify one or more of the state variables whose measurement residuals violate a measurement residual constraint in the constraint set H;
(e) integrate a reconstructed QGS, which is reconstructed based on the constraint set H by setting the identified one or more state variables to values of corresponding PMU measurements;
(f) iterate steps of (d) and (e) until no measurement residuals violate the measurement residual constraint, to thereby obtain a solution for the state variables as the state estimation; and
(g) report the state estimation to a control system during real-time monitoring of the distribution network.

### Claim 14 (depends on 13)

The non-transitory computer-readable storage medium of claim 13, wherein the plurality of PMUs include a plurality of micro-PMUs.

### Claim 15 (depends on 13)

The non-transitory computer-readable storage medium of claim 13, wherein the instructions when executed by the computer system, cause the computer system to:
determine optimal placement of the PMUs at the buses by solving a nonlinear integer programming problem constrained by at least an observability requirement for a subset of the buses.

### Claim 16 (depends on 15)

The non-transitory computer-readable storage medium of claim 15, wherein the computer system in determining the optimal placement is further operative to:
identify a minimal number and locations of the PMUs to be placed in the distribution network according to a requirement specifying that all predetermined key buses are observable from the measurements.

### Claim 17 (depends on 15)

The non-transitory computer-readable storage medium of claim 15, wherein the computer system in determining the optimal placement is further operative to:
identify locations of a predetermined number of PMUs to be placed in the distribution network according to requirements specifying that all predetermined key buses are observable from the measurements and observable non-key buses are maximized in number.

### Claim 18 (depends on 15)

The non-transitory computer-readable storage medium of claim 15, wherein the computer system in determining the optimal placement is further operative to:
identify locations of a predetermined number of PMUs to be placed in the distribution network according to a requirement specifying that observable key buses are maximized in number.

### Claim 19 (depends on 13)

The non-transitory computer-readable storage medium of claim 13, wherein the state estimation includes voltage amplitudes and phase angles at a subset of the buses.

### Claim 20 (depends on 13)

The non-transitory computer-readable storage medium of claim 13, wherein the measurement residual constraints constrain a difference between calculated values of the state variables and corresponding PMU measurements.