# US 2021/0081905 A1 · System and method of scheduling work within a workflow with defined process goals

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2021/0081905 A1
- Document ID: US20210081905A1
- Status: Published application
- Kind: A1
- Application number: 17/012,728
- Filed: 2020-09-04
- Published: 2021-03-18
- Earliest claimed: 2012-07-30
- Assignees: Verint Americas Inc.
- Applicants: Verint Americas Inc.
- Inventors: Edward Hamilton; Kaushik Deka
- Web page: https://patentgrep.com/patent/US20210081905A1

## CPC

- G06Q 10/1097: {using calendar-based scheduling for task assignment}
- G06Q 10/04: Forecasting or optimisation specially adapted for administrative or management purposes, e.g. linear programming or "cutting stock problem" (market predictions or forecasting for commercial activities G06Q30/0202)
- G06Q 10/06311: {Scheduling, planning or task assignment for a person or group}
- G06Q 10/063114: {Status monitoring or status determination for a person or group}
- G06Q 10/0633: Workflow analysis
- G06Q 10/06334: {using forecasting or predicting}
- G06Q: INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR

## Abstract

A system and method schedule work within a workflow with defined process goals. A plurality of work queues are defined that comprise work items. The plurality of work queues are associated with one or more links between a parent work queue and at least one child work queue to form at least one work process. At least one work process goal is defined for each work process. A work schedule to achieve the work process goals is generated.

## Claims

### Claim at position 1

-20. (canceled)

### Claim 21

A method of optimizing a workflow for scheduling work assignments, the method comprising:
defining a plurality of work queues, each work queue representative of a task to be completed;
displaying the plurality of defined work queues in a graphical user interface;
receiving, through the graphical user interface, a selection of at least two work queues of the plurality of defined work queues;
presenting a graphical indication of each of the selected work queues on the graphical user interface;
creating, in the graphical user interface, at least one directional graphical link between two of the at least two selected work queues, binding two of the at least two selected work queues;
creating at least one work process in the workflow by receiving, in the graphical user interface, a selection of at least two of the selected work queues;
graphically depicting each of the work processes with a unique color;
defining at least one work process goal for the at least one work process;
generating, using a processor adapted to optimize a work schedule, a workflow for scheduling tasks associated with the graphically depicted work queues, the generated schedule defined by the at least one work process goal;
unbinding a plurality of work queues for a predetermined number of work processes; and
randomly selecting an unbound work queue and iteratively binding another unbound work queue to the selected unbound work queue and simulate the performance of the workflow to optimize the workflow schedule until all unbound work queues are rebound and the workflow schedule is optimized such that all work process goals are met.

### Claim 22 (depends on 21)

The method of claim 21, the method further comprising defining, with the graphical user interface, at least one constraint associated with at least one of the selected work queues.

### Claim 23 (depends on 22)

The method of claim 22, wherein the generated schedule is defined by the at least one constraint and the at least one work process goal.

### Claim 24 (depends on 21)

The method of claim 21, the method further comprising graphically depicting each work queue and each graphical line that are not part of one of the work processes as a single unique color.

### Claim 25

A system for optimizing a workflow for scheduling work assignments, comprising:
a processor;
a graphical user interface; and
a non-transitory computer readable medium programmed with computer readable code that upon execution by the processor causes the processor to:
define a plurality of work queues, each work queue representative of a task to be completed;
display the plurality of defined work queues in the graphical user interface;
receive, from the graphical user interface, a selection of at least two work queues of the plurality of defined work queues;
present a graphical indication of each of the selected work queues on the graphical user interface;
create, in the graphical user interface, at least one directional graphical link between two of the at least two selected work queues, binding two of the at least two selected work queues;
create at least one work process in the workflow by receiving, in the graphical user interface, a selection of at least two of the selected work queues;
graphically depict each of the work processes with a unique color;
define at least one work process goal for the at least one work process;
generate, using a processor adapted to optimize a work schedule, a workflow for scheduling tasks associated with the graphically depicted work queues, the generated schedule defined by the at least one work process goal;
unbind a plurality of work queues for a predetermined number of work processes; and
randomly select an unbound work queue and iteratively binding another unbound work queue to the selected unbound work queue and simulate the performance of the workflow to optimize the workflow schedule until all unbound work queues are rebound and the workflow schedule is optimized such that all work process goals are met.

### Claim 26 (depends on 25)

The system of claim 25, wherein the processor is further instructed to define, in the graphical user interface, at least one constraint associated with at least one of the created graphical directional links.

### Claim 27 (depends on 26)

The system of claim 26, wherein the generated schedule is defined by the at least one constraint and the at least one work process goal.

### Claim 28 (depends on 25)

The system of claim 25, wherein the processor is further instructed to graphically depict each work queue that is part of at least one of the work processes with the unique color assigned to each work process to which the work queue is assigned.

### Claim 29

A method of optimizing a workflow for scheduling work assignments, the method comprising:
providing a workforce management system, the workforce management system including a graphical user interface and a processor, wherein the graphical user interface is used to create workflows, further wherein the processor receives created workflows and optimizes the created workflows;
defining a plurality of work queues, each work queue representative of a task to be completed;
displaying the plurality of defined work queues in the graphical user interface;
receiving, through the graphical user interface, a selection of at least two work queues of the plurality of defined work queues;
presenting a graphical indication of each of the selected work queues on the graphical user interface;
creating, in the graphical user interface, at least one directional graphical link between two of the at least two selected work queues, binding two of the at least two selected work queues;
creating at least one work process in the workflow by receiving, in the graphical user interface, a selection of at least two of the selected work queues;
graphically depicting each of the work processes with a unique color;
defining at least one work process goal for the at least one work process;
generating, using the processor adapted to optimize a work schedule, a workflow for scheduling tasks associated with the graphically depicted work queues, the generated schedule defined by the at least one work process goal;
unbinding a plurality of work queues for a predetermined number of work processes; and
randomly selecting an unbound work queue and iteratively binding another unbound work queue to the selected unbound work queue and simulate the performance of the workflow to optimize the workflow schedule until all unbound work queues are rebound and the workflow schedule is optimized such that all work process goals are met.

### Claim 30 (depends on 29)

The method of claim 29, the method further comprising defining, with the graphical user interface, at least one constraint associated with at least one of the selected work queues or at least one of the created graphical directional links.

### Claim 31 (depends on 30)

The method of claim 30, wherein the generated schedule is defined by the at least one constraint and the at least one work process goal.

### Claim 32

A system of optimizing a workflow for scheduling work assignments, comprising:
a workforce management system, wherein the workforce management system includes:
a graphical user interface used to create workflows;
a processor that receives workflows from the graphical user interface and optimizes the created workflows; and
a non-transitory computer readable medium programmed with computer readable code that upon execution by the processor causes the processor to:
define a plurality of work queues, each work queue representative of a task to be completed;
display the plurality of defined work queues in the graphical user interface;
receive, through the graphical user interface, a selection of at least two work queues of the plurality of defined work queues;
present a graphical indication of each of the selected work queues on the graphical user interface;
create, in the graphical user interface, at least one directional graphical link between two of the at least two selected work queues, binding two of the at least two selected work queues;
create at least one work process in the workflow by receiving, in the graphical user interface, a selection of at least two of the selected work queues;
graphically depict each of the work processes with a unique color;
define at least one work process goal for the at least one work process;
generate, using the processor adapted to optimize a work schedule, a workflow for scheduling tasks associated with the graphically depicted work queues, the generated schedule defined by the at least one work process goal;
unbind a plurality of work queues for a predetermined number of work processes; and
randomly select an unbound work queue and iteratively binding another unbound work queue to the selected unbound work queue and simulate the performance of the workflow to optimize the workflow schedule until all unbound work queues are rebound and the workflow schedule is optimized such that all work process goals are met.

### Claim 33 (depends on 32)

The system of claim 32, wherein the processor is further instructed to define, with the graphical user interface, at least one constraint associated with at least one of the selected work queues or at least one of the created graphical directional links.

### Claim 34 (depends on 33)

The system of claim 33, wherein the generated schedule is defined by the at least one constraint and the at least one work process goal.

### Claim 35

A method of optimizing a workflow for scheduling work assignments, the method comprising:
defining a plurality of work queues, each work queue representative of a task to be completed;
displaying the plurality of defined work queues in a graphical user interface;
receiving, through the graphical user interface, a selection of at least two work queues of the plurality of defined work queues;
presenting a graphical indication of each of the selected work queues on the graphical user interface;
creating, in the graphical user interface, at least one directional graphical link between two of the at least two selected work queues, binding two of the at least two selected work queues;
defining, with the graphical user interface, at least one constraint associated with at least one of the selected work queues or at least one of the created graphical directional links;
creating at least one work process in the workflow by receiving, in the graphical user interface, a selection of at least two of the selected work queues, wherein the two work queues of the at least two selected work queues are connected by the at least one directional graphical link;
graphically depicting each of the work processes with a unique color;
defining at least one work process goal for the at least one work process;
generating, using a processor adapted to optimize a work schedule, a workflow for scheduling tasks associated with the graphically depicted work queues, the generated schedule defined by the at least one constraint and the at least one work process goal; and
simulating, with the processor, the performance of the generated workflow and optimizing the workflow until the simulation determines the workflow is optimized such that all constraints and work process goals are met by the optimized workflow.

### Claim 36 (depends on 35)

The method of claim 35, wherein the simulation includes unbinding a plurality of work queues for a predetermined number of work processes.

### Claim 37 (depends on 36)

The method of claim 36, wherein the simulation includes randomly selecting an unbound work queue and iteratively binding another unbound work queue to the selected unbound work queue and simulate the performance of the workflow to optimize the workflow schedule until all unbound work queues are rebound.

### Claim 38

A system for optimizing a workflow for scheduling work assignments, comprising:
a processor;
a graphical user interface; and
a non-transitory computer readable medium programmed with computer readable code that upon execution by the processor causes the processor to:
define a plurality of work queues, each work queue representative of a task to be completed;
display the plurality of defined work queues in a graphical user interface;
receive, through the graphical user interface, a selection of at least two work queues of the plurality of defined work queues;
present a graphical indication of each of the selected work queues on the graphical user interface;
create, in the graphical user interface, at least one directional graphical link between two of the at least two selected work queues, binding two of the at least two selected work queues;
define, with the graphical user interface, at least one constraint associated with at least one of the selected work queues or at least one of the created graphical directional links;
create at least one work process in the workflow by receiving, in the graphical user interface, a selection of at least two of the selected work queues, wherein the two work queues of the at least two selected work queues are connected by the at least one directional graphical link;
graphically depict each of the work processes with a unique color;
define at least one work process goal for the at least one work process;
generate, using a processor adapted to optimize a work schedule, a workflow for scheduling tasks associated with the graphically depicted work queues, the generated schedule defined by the at least one constraint and the at least one work process goal;
simulate, with the processor, the performance of the generated workflow and optimizing the workflow until the simulation determines the workflow is optimized such that all constraints and work process goals are met by the optimized workflow.

### Claim 39 (depends on 38)

The system of claim 38, wherein the simulation includes unbinding a plurality of work queues for a predetermined number of work processes.

### Claim 40 (depends on 39)

The system of claim 39, wherein the simulation includes randomly selecting an unbound work queue and iteratively binding another unbound work queue to the selected unbound work queue and simulate the performance of the workflow to optimize the workflow schedule until all unbound work queues are rebound.