# US 2021/0062677 A1 · A method for starting up a gas turbine engine of a combined cycle power plant

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2021/0062677 A1
- Document ID: US20210062677A1
- Status: Published application
- Kind: A1
- Application number: 16/963,620
- Filed: 2018-02-20
- Published: 2021-03-04
- Earliest claimed: 2018-02-20
- Assignees: Siemens Aktiengesellschaft
- Applicants: Siemens Aktiengesellschaft
- Inventors: Kok-Mun Tham; Christian Keune; Nicolas Benjamin Wappler
- Web page: https://patentgrep.com/patent/US20210062677A1

## CPC

- F01D 19/00: Starting of machines or engines; Regulating, controlling, or safety means in connection therewith (warming-up before starting F01D25/10; turning or inching gear F01D25/34)
- F01K 13/02: Controlling, e.g. stopping or starting
- F02C 9/54: by throttling the working fluid, by adjusting vanes
- F05D 2220/32: in gas turbines
- F05D 2220/72: a steam turbine
- F05D 2260/85: Starting
- Y02E 20/16: Combined cycle power plant [CCPP], or combined cycle gas turbine [CCGT]
- F01D: NON-POSITIVE DISPLACEMENT MACHINES OR ENGINES, e.g. STEAM TURBINES (machines or engines for liquids F03; non-positive displacement pumps F04D)
- F01K: STEAM ENGINE PLANTS; STEAM ACCUMULATORS; ENGINE PLANTS NOT OTHERWISE PROVIDED FOR; ENGINES USING SPECIAL WORKING FLUIDS OR CYCLES (gas-turbine or jet-propulsion plants F02; nuclear power plants, engine arrangements therein G21D)
- F02C: GAS-TURBINE PLANTS; AIR INTAKES FOR JET-PROPULSION PLANTS; CONTROLLING FUEL SUPPLY IN AIR-BREATHING JET-PROPULSION PLANTS (construction of turbines F01D; jet-propulsion plants F02K; construction of compressors or fans F04; generating combustion products of high pressure or high velocity F23R; using gas turbines in compression refrigeration plants F25B11/00)
- F05D: INDEXING SCHEME FOR ASPECTS RELATING TO NON-POSITIVE-DISPLACEMENT MACHINES OR ENGINES, GAS-TURBINES OR JET-PROPULSION PLANTS
- Y02E: REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION

## Abstract

The invention relates to a method for starting up a gas turbine engine of a combined cycle power plant. The method includes applying load to the gas turbine engine and increasing the load until a predetermined combustor firing temperature is reached, while keeping the adjustable inlet guide vanes in a start position adapted to reduce the mass flow of air into the compressor; further increasing the load of the gas turbine engine while opening the adjustable inlet guide vanes and keeping the predetermined combustor firing temperature constant until the inlet guide vanes reach an end position adapted to increase the mass flow of air into the compressor; further increasing the load of the gas turbine engine while keeping the adjustable inlet guide vanes in the end position until a predetermined load of the gas turbine engine is reached.

## Claims

### Claim 1

A method for starting up a gas turbine engine of a combined cycle power plant, the gas turbine engine including a compressor, a combustor and a turbine, the compressor providing compressed air to the combustor for combustion with a fuel to produce a working fluid and the turbine receiving the working fluid to produce power; the compressor comprising adjustable inlet guide vanes, the adjustable inlet guide vanes being adjustable between a fully closed position for minimizing the mass flow of air into the compressor and a fully open position for providing the maximum mass flow of air into the compressor wherein the method comprises the steps of:
step 1: applying load to the gas turbine engine and increasing the load until a predetermined combustor firing temperature is reached, while keeping the adjustable inlet guide vanes in a start position adapted to reduce the mass flow of air into the compressor, whereby the predetermined combustor firing temperature is chosen to be an emission-compliant temperature,
step 2: further increasing the load of the gas turbine engine while opening the adjustable inlet guide vanes and keeping the predetermined combustor firing temperature constant until the inlet guide vanes reach an end position adapted to increase the mass flow of air into the compressor,
step 3: further increasing the load of the gas turbine engine while keeping the adjustable inlet guide vanes in the end position until a predetermined load of the gas turbine engine is reached.

### Claim 2 (depends on 1)

A method according claim 1, wherein the predetermined combustor firing temperature is between 1000° C. and 1850° C.

### Claim 3 (depends on 1)

A method according to claim 1, wherein in step 3 the predetermined load is a base load of the gas turbine engine.

### Claim 4 (depends on 1)

A method according to claim 1, wherein in step 1 the start position of the adjustable inlet guide vanes is the fully closed position.

### Claim 5 (depends on 1)

A method according to claim 1, wherein in step 3 the end position of adjustable inlet guide vanes is the fully open position.

### Claim 6

Gas turbine engine of a combined cycle power plant, comprising:
a compressor, a combustor and a turbine the compressor providing compressed air to the combustor) for combustion with a fuel to produce a working fluid and the turbine receiving the working fluid to produce power;
the compressor comprising adjustable inlet guide vanes, the adjustable inlet guide vanes being adjustable between a fully closed position for minimizing the mass flow of air into the compressor and a fully open position for providing the maximum mass flow of air into the compressor;
a control unit for modulating the adjustable inlet guide vanes between a fully closed position for minimizing the mass flow of air into the compressor and a fully open position for providing the maximum mass flow of air into the compressor, the modulation of the adjustable inlet guide vanes depending on a combustor firing temperature, whereby the predetermined combustor firing temperature is an emission-compliant temperature.

### Claim 7 (depends on 6)

Combined cycle power plant comprising:
a gas turbine engine according to claim 6 producing an exhaust fluid;
a heat recovery steam generator receiving the exhaust fluid and producing steam;
a steam turbine engine receiving the steam of the heat recovery steam generator.