# US 2020/0403444 A1 · Power interchange apparatus, computer readable storage medium and power interchange method

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2020/0403444 A1
- Document ID: US20200403444A1
- Status: Published application
- Kind: A1
- Application number: 17/013,882
- Filed: 2020-09-08
- Published: 2020-12-24
- Earliest claimed: 2018-03-19
- Assignees: Honda Motor Co., Ltd.
- Applicants: Honda Motor Co.,Ltd.
- Inventors: Takayuki YAMADA; Koichiro TAKEMASA; Kazuyoshi MIYAJIMA; Keiichi TAKIKAWA; Yuiko KOGA
- Web page: https://patentgrep.com/patent/US20200403444A1

## CPC

- H02J 13/12: Monitoring network conditions, e.g. electrical magnitudes or operational status
- G06Q 10/02: Reservations, e.g. for tickets, services or events
- G06Q 50/06: Energy or water supply
- H02J 3/0075: {for providing alternative feeding paths between load and source according to economic or energy efficiency considerations, e.g. economic dispatch}
- H02J 3/008: Circuit arrangements for power supply or distribution technologies responsive to energy trading
- H02J 13/00: Circuit arrangements for providing remote monitoring or remote control of equipment in a power distribution network
- H02J 13/10: characterised by displaying of information or by user interaction, e.g. supervisory control and data acquisition [SCADA] systems
- H02J 13/333: the equipment forming part of substations
- H02J 13/34: the equipment being switches, relays or circuit breakers
- H02J 2105/00: Networks for supplying or distributing electric power characterised by their spatial reach or by the load
- H02J 2105/10: Local stationary networks having a local or delimited stationary reach
- Y02E 60/00: Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation
- Y04S 10/18: using switches, relays or circuit breakers, e.g. intelligent electronic devices [IED]
- Y04S 50/10: Energy trading, including energy flowing from end-user application to grid
- H02J: ELECTRIC POWER NETWORKS; CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- G06Q: INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- Y02E: REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y04S: SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS

## Abstract

Included are: a performance information obtaining unit that obtains, for each of a plurality of first power customers that configure a first community, information about a power interchange performance between the first power customer and the first community; a contribution degree determination unit that determines a contribution degree of at least one of the plurality of first power customers to a surplus power amount of the first community in a certain time period, based on information about the performance obtained by the performance information obtaining unit.

## Claims

### Claim 1

A power interchange apparatus comprising:
a performance information obtaining unit that obtains, for each of a plurality of first power customers that configure a first community, information about a power interchange performance between the first power customer and the first community;
a contribution degree determination unit that determines a contribution degree of at least one of the plurality of first power customers to a surplus power amount of the first community in a certain time period, based on information about the performance obtained by the performance information obtaining unit;
a request obtaining unit that obtains an interchange request from at least one of the plurality of first power customers, to request for interchanging at least a part of surplus power of the first community in a future time period to a second community that is different from the first community;
an expectation information obtaining unit that obtains information indicating an expected value of the surplus power amount of the first community in the future time period; and
an interchange amount determination unit that determines a power amount to be interchanged from the first community to the second community in the future time period, based on: (i) the expected value of the surplus power amount indicated by the information obtained by the expectation information obtaining unit; and (ii) the contribution degree in the future time period determined by the contribution degree determination unit.

### Claim 2 (depends on 1)

The power interchange apparatus according to claim 1, wherein
the interchange request includes information indicating a target value of a power amount interchanged from the first community to the second community, and wherein
the power interchange apparatus further comprising:
a procurement judgement unit that judges, if the power amount determined by the interchange amount determination unit is smaller than the target value indicated by the interchange request, whether a first power customer that outputs the interchange request can procure power from one or a plurality of first power customers different from the first power customer in the future time period.

### Claim 3 (depends on 2)

The power interchange apparatus according to claim 2, further comprising a condition determination unit that determines a power interchange condition between: (i) a first user that requires for power interchange in a first time period prior to a second time period under a condition that it provides power in the second time period; and (ii) a second user that can provide power to the first user in the first time period, wherein
the first user is a first power customer that outputs the interchange request,
the second user is the one or plurality of first power customers different from the first power customer that outputs the interchange request, and
the first time period is the future time period.

### Claim 4 (depends on 3)

The power interchange apparatus according to claim 3, wherein
the condition determination unit comprises:
a supply-side condition obtaining unit that obtains information indicating a condition for providing power by the second user in the first time period; and
a return condition determination unit that determines at least one of: (i) a second target value related to a power amount provided to the second user from the first user in the second time period, and (ii) a parameter that indicates a relationship between the target value and the second target value, based on the first time period, the target value indicated by the interchange request, and the condition for providing power by the second user in the first time period.

### Claim 5 (depends on 1)

The power interchange apparatus according to claim 1, further comprising a supply/demand information obtaining unit that obtains information about power supply/demand of each of the plurality of first power customers, wherein
the expectation information obtaining unit expects a surplus power amount of the first community in the future time period, based on the information about the power supply/demand obtained by the supply/demand information obtaining unit.

### Claim 6 (depends on 1)

The power interchange apparatus according to claim 1, wherein
the contribution degree determination unit determines the contribution degree of at least one of the plurality of first power customers, based on at least one of:
(i) a power amount interchanged from each first power customer to the first community, between a reference clock time and either one of a beginning or an end of the certain time period;
(ii) a ratio of a power amount interchanged from each first power customer to the first community to a power amount interchanged from all of the plurality of first power customers to the first community, between the reference clock time and either one of a beginning or an end of the certain time period;
(iii) the number of times each first power customer interchanges power to the first community, between the reference clock time and either one of a beginning or an end of the certain time period; and
(iv) the number of times each first power customer accepts demand response from the first community, between the reference clock time and either one of a beginning or an end of the certain time period.

### Claim 7 (depends on 1)

The power interchange apparatus according to claim 1, wherein
the information about a power interchange performance includes information in which identification information of a power transmission side, identification information of a power receiving side, information indicating a time period in which is power is interchanged, and information indicating an interchanged power amount, which are associated with one another.

### Claim 8 (depends on 1)

The power interchange apparatus according to claim 1, further comprising: a switching unit that switches electrical connections between a power network of a commercial utility grid and a power transmission/distribution network of the first community.

### Claim 9

A non-transitory computer readable storage medium that stores a program, wherein the program makes a computer perform a power interchange method,
the power interchange method comprising:
obtaining performance information being, for each of a plurality of first power customers that configure a first community, information about a power interchange performance between the first power customer and the first community;
determining a contribution degree of at least one of the plurality of first power customers to a surplus power amount of the first community in a certain time period, based on information about the performance obtained in the obtaining of the performance information;
obtaining an interchange request from at least one of the plurality of first power customers, to request for interchanging at least a part of surplus power of the first community in a future time period to a second community that is different from the first community;
obtaining expectation information being information indicating an expected value of the surplus power amount of the first community in the future time period; and
determining a power amount to be interchanged from the first community to the second community in the future time period, based on: (i) the expected value of the surplus power amount indicated by the information obtained in the obtaining of the expectation information; and (ii) the contribution degree in the future time period determined in the obtaining of the contribution degree.

### Claim 10

A power interchange method comprising:
obtaining performance information being, for each of a plurality of first power customers that configure a first community, information about a power interchange performance between the first power customer and the first community;
determining a contribution degree of at least one of the plurality of first power customers to a surplus power amount of the first community in a certain time period, based on information about the performance obtained in the obtaining of the performance information;
obtaining an interchange request from at least one of the plurality of first power customers, to request for interchanging at least a part of surplus power of the first community in a future time period to a second community that is different from the first community;
obtaining expectation information being information indicating an expected value of the surplus power amount of the first community in the future time period; and
determining a power amount to be interchanged from the first community to the second community in the future time period, based on: (i) the expected value of the surplus power amount indicated by the information obtained in the obtaining of the expectation information; and (ii) the contribution degree in the future time period determined in the obtaining of the contribution degree.