# US 2020/0401974 A1 · Work plan management system and component mounting system

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2020/0401974 A1
- Document ID: US20200401974A1
- Status: Published application
- Kind: A1
- Application number: 16/969,179
- Filed: 2018-02-28
- Published: 2020-12-24
- Earliest claimed: 2018-02-28
- Assignees: Yamaha Hatsudoki Kabushiki Kaisha
- Applicants: Yamaha Hatsudoki Kabushiki Kaisha
- Inventors: Yoichi MATSUSHITA; Kotaro SUGIYAMA
- Web page: https://patentgrep.com/patent/US20200401974A1

## CPC

- G06Q 10/06316: {Sequencing of tasks or work}
- H05K 13/085: {Production planning, e.g. of allocation of products to machines, of mounting sequences at machine or facility level}
- G05B 19/4155: characterised by program execution, i.e. part program or machine function execution, e.g. selection of a program
- G06Q 10/06312: {Adjustment or analysis of established resource schedule, e.g. resource or task levelling, or dynamic rescheduling}
- G06Q 10/0875: Itemisation or classification of parts, supplies or services, e.g. bill of materials
- G06Q 50/04: Manufacturing
- H05K 13/02: Feeding of components
- H05K 13/086: {Supply management, e.g. supply of components or of substrates}
- G05B 2219/36195: Assembly, mount of electronic parts onto board
- G06Q: INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- H05K: PRINTED CIRCUITS; CASINGS OR CONSTRUCTIONAL DETAILS OF ELECTRIC APPARATUS; MANUFACTURE OF ASSEMBLAGES OF ELECTRICAL COMPONENTS
- G05B: CONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS (systems for controlling or regulating non-electric variables G05D; systems for regulating electric or magnetic variables G05F; control devices or systems insofar as characterised by mechanical features only G05G)

## Abstract

This work plan management system is provided with a component replenishment management unit for managing a plan for component replenishment work to be performed on component supply devices; and an ancillary work management unit for managing a plan for ancillary work. The component replenishment management unit includes a component supply monitoring unit and a replenishment target specifying unit. The component supply monitoring unit specifies, for each of the component supply devices, replenishment possibility time windows during which component replenishment work is possible. The replenishment target specifying unit recognizes overlapping replenishment time windows in which the individual replenishment possibility time windows overlap, and specifies component supply devices on which it is possible to perform component replenishment work during the overlapping replenishment time windows. The ancillary work management unit specifies ancillary work that is to be started during the overlapping replenishment time windows.

## Claims

### Claim 1

A work plan management system that manages a plan for setup work for producing a component mounted substrate with respect to a mounter that produces the component mounted substrate by mounting, onto a substrate, components supplied from a plurality of attached component supply devices into which a plurality of component storage members are loadable, the work plan management system comprising:
a component replenishment management unit configured to manage a plan for component replenishment work, the component replenishment work being setup work that replenishes each of the plurality of component supply devices with a new component storage member; and
an ancillary work management unit configured to manage a plan for a plurality of ancillary work performed during the production of the component mounted substrate, the ancillary work being setup work other than the component replenishment work, wherein
the component replenishment management unit includes
a component supply monitoring unit configured to monitor a supply status of the components in each of the plurality of component supply devices, and specifies, for each of the plurality of component supply devices, a replenishment possibility time window expressing a time window during which the component replenishment work is possible, and
a replenishment target specifying unit configured to recognize an overlapping replenishment time window in which the replenishment possibility time windows overlap each other, and specify a component supply device for which the component replenishment work is possible within the overlapping replenishment time window as a component replenishment target device treated as a target of the component replenishment work, and
the ancillary work management unit includes
a work duration specifying unit configured to specify, for each of the plurality of ancillary work, a recommended work start time window expressing a time window in which the start of work is recommended, based on a work duration from a start until an end of each of the plurality of ancillary work, and
a work start target specifying unit configured to specify, from among the plurality of ancillary work, ancillary work for which an earliest time of the overlapping replenishment time window is included in the recommended work start time window as start target work to be started within the overlapping replenishment time window.

### Claim 2 (depends on 1)

The work plan management system according to claim 1, wherein
in a case where a plurality of overlapping replenishment time windows exist, the replenishment target specifying unit is configured to specify the component replenishment target device for each of the overlapping replenishment time windows, and
the work start target specifying unit is configured to specify the start target work in association with one of the plurality of overlapping replenishment time windows.

### Claim 3 (depends on 1)

The work plan management system according to claim 1, wherein
the component replenishment management unit additionally includes a replenishment timing specifying unit configured to specify a same replenishment work timing of the component replenishment work with respect to the component replenishment target device in the overlapping replenishment time window, and
the ancillary work management unit additionally includes an ancillary work timing specifying unit configured to specify the replenishment work timing as work start timing of the start target work.

### Claim 4 (depends on 3)

The work plan management system according to claim 3, wherein in a case where the overlapping replenishment time window is a first overlapping time window of interest containing a latest time of the recommended work start time window, the replenishment timing specifying unit is configured to specify a predetermined time earlier than the latest time within the first overlapping time window of interest as the replenishment work timing.

### Claim 5 (depends on 3)

The work plan management system according to claim 3, wherein
the work duration specifying unit is configured to specify, for each of the plurality of ancillary work, a work end time in a case where the ancillary work is started at the work start timing, and
in a case where the overlapping replenishment time window is a second overlapping time window of interest that is later than a latest time of the recommended work start time window of each of the plurality of ancillary work and also contains the work end time, the replenishment timing specifying unit is configured to specify the work end time within the second overlapping time window of interest as the replenishment work timing.

### Claim 6 (depends on 3)

The work plan management system according to claim 3, wherein
the work duration specifying unit is configured to specify, for each of the plurality of ancillary work, an estimated work end time at which the ancillary work is estimated to end in a case where the ancillary work is started at the latest time of the recommended work start time window, and
in a case where the overlapping replenishment time window is a third overlapping time window of interest that is later than a latest time of the recommended work start time window of each of the plurality of ancillary work and also contains the estimated work end time, the replenishment timing specifying unit is configured to specify the estimated work end time within the third overlapping time window of interest as the replenishment work timing.

### Claim 7 (depends on 6)

The work plan management system according to claim 6, wherein the latest time of the recommended work start time window is set such that the estimated work end time matches a substrate type switch timing in the production of the component mounted substrate.

### Claim 8 (depends on 1)

A component mounting system comprising:
a mounter that produces a component mounted substrate by mounting, onto a substrate, components supplied from a plurality of attached component supply devices into which a plurality of component storage members are loadable; and
the work plan management system according to claim 1 that manages a plan for setup work for producing the component mounted substrate with respect to the mounter.

### Claim 9 (depends on 2)

The work plan management system according to claim 2, wherein
the component replenishment management unit additionally includes a replenishment timing specifying unit configured to specify a same replenishment work timing of the component replenishment work with respect to the component replenishment target device in the overlapping replenishment time window, and
the ancillary work management unit additionally includes an ancillary work timing specifying unit configured to specify the replenishment work timing as work start timing of the start target work.

### Claim 10 (depends on 9)

The work plan management system according to claim 9, wherein in a case where the overlapping replenishment time window is a first overlapping time window of interest containing a latest time of the recommended work start time window, the replenishment timing specifying unit is configured to specify a predetermined time earlier than the latest time within the first overlapping time window of interest as the replenishment work timing.

### Claim 11 (depends on 9)

The work plan management system according to claim 9, wherein
the work duration specifying unit is configured to specify, for each of the plurality of ancillary work, a work end time in a case where the ancillary work is started at the work start timing, and
in a case where the overlapping replenishment time window is a second overlapping time window of interest that is later than a latest time of the recommended work start time window of each of the plurality of ancillary work and also contains the work end time, the replenishment timing specifying unit is configured to specify the work end time within the second overlapping time window of interest as the replenishment work timing.

### Claim 12 (depends on 9)

The work plan management system according to claim 9, wherein
the work duration specifying unit is configured to specify, for each of the plurality of ancillary work, an estimated work end time at which the ancillary work is estimated to end in a case where the ancillary work is started at the latest time of the recommended work start time window, and
in a case where the overlapping replenishment time window is a third overlapping time window of interest that is later than a latest time of the recommended work start time window of each of the plurality of ancillary work and also contains the estimated work end time, the replenishment timing specifying unit is configured to specify the estimated work end time within the third overlapping time window of interest as the replenishment work timing.

### Claim 13 (depends on 12)

The work plan management system according to claim 12 wherein the latest time of the recommended work start time window is set such that the estimated work end time matches a substrate type switch timing in the production of the component mounted substrate.