# US 2020/0395865 A1 · Device for connecting a sub-network to an alternating voltage network and method for controlling an electrical power

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2020/0395865 A1
- Document ID: US20200395865A1
- Status: Published application
- Kind: A1
- Application number: 17/005,783
- Filed: 2020-08-28
- Published: 2020-12-17
- Earliest claimed: 2018-02-28
- Assignees: SMA Solar Technology AG
- Applicants: SMA Solar Technology AG
- Inventors: Claus Allert; Mathias Buenemann; Matthias Groene; Alexander Unru
- Web page: https://patentgrep.com/patent/US20200395865A1

## CPC

- H02J 3/26: Arrangements for eliminating or reducing asymmetry in polyphase networks
- H02J 3/06: Controlling the transfer of power between connected networks; Controlling load sharing between connected networks
- H02J 3/14: by switching loads on to, or off from, the networks, e.g. progressively balanced loading
- H02J 3/28: Arrangements for balancing of the load in networks by storage of energy
- H02J 3/36: Arrangements for transfer of electric power between AC networks via high-voltage DC [HVDC] links; Arrangements for transfer of electric power between generators and networks via HVDC links
- H02M 5/14: for conversion between circuits of different phase number
- H02J 3/388: Arrangements for the handling of islanding, e.g. for disconnection or for avoiding the disconnection of power
- H02J 2105/12: supplying households or buildings
- Y02B 70/3225: Demand response systems, e.g. load shedding, peak shaving
- Y02E 40/50: Arrangements for eliminating or reducing asymmetry in polyphase networks
- Y02E 60/60: Arrangements for transfer of electric power between AC networks or generators via a high voltage DC link [HVCD]
- Y02T 10/70: Energy storage systems for electromobility, e.g. batteries
- Y02T 10/7072: Electromobility specific charging systems or methods for batteries, ultracapacitors, supercapacitors or double-layer capacitors
- Y04S 20/222: Demand response systems, e.g. load shedding, peak shaving
- H02J: ELECTRIC POWER NETWORKS; CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02M: APPARATUS FOR CONVERSION BETWEEN AC AND AC, BETWEEN AC AND DC, OR BETWEEN DC AND DC, AND FOR USE WITH MAINS OR SIMILAR POWER SUPPLY SYSTEMS; CONVERSION OF DC OR AC INPUT POWER INTO SURGE OUTPUT POWER; CONTROL OR REGULATION THEREOF (transformers H01F; dynamo-electric converters H02K47/00; controlling transformers, reactors or choke coils, control or regulation of electric motors, generators or dynamo-electric converters H02P)
- Y02B: CLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
- Y02E: REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02T: CLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO TRANSPORTATION
- Y04S: SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS

## Abstract

A method for controlling an electrical power which flows into or out of an electrical subnetwork via a connection point is disclosed. The subnetwork has at least one electrical load, and the electrical load is connected to a control device via a communication connection, the electrical power flowing via the connection point is measured and a maximum power consumption of the electrical load is set by means of the control device on the basis of the electrical power flowing via the connection point. A device for connecting a multiphase subnetwork, which has an energy production installation and an energy store, to a superordinate multiphase alternating voltage network is configured to transmit electrical power between the alternating voltage network and the subnetwork and comprises an AC/AC converter having a network connection, two inverter bridge circuits with an interposed intermediate circuit and a subnetwork connection. The device also comprises a control device which is configured to set the electrical powers flowing via the individual phases of the subnetwork connection on the basis of power values of the energy production installation and/or of the energy store by suitably controlling the inverter bridge circuits of the AC/AC converter.

## Claims

### Claim 1

A method for controlling an electrical power which flows into or out of an electrical subnetwork via a connection point, wherein the subnetwork has at least one electrical load, and the electrical load is connected to a control device via a communication connection, comprising:
measuring the electrical power flowing via the connection point, and
setting a maximum power consumption of the electrical load by means of the control device on the basis of the electrical power flowing via the connection point.

### Claim 2 (depends on 1)

The method as claimed in claim 1, further comprising:
setting a power output of an energy store arranged in the subnetwork and/or of an energy production unit arranged in the subnetwork by means of the control device on the basis of the electrical power flowing via the connection point.

### Claim 3 (depends on 1)

The method as claimed in claim 1, further comprising:
reducing the maximum power consumption if the electrical power flowing into the subnetwork via the connection point exceeds a predefined limit value.

### Claim 4 (depends on 3)

The method as claimed in claim 3, wherein the maximum power consumption is set to zero if the electrical power flowing into the subnetwork via the connection point exceeds the predefined limit value.

### Claim 5 (depends on 4)

The method as claimed in claim 4, wherein an increase in the maximum power consumption by a fraction of the predefined limit value is performed and the following further acts are repeatedly carried out:
comparison of the electrical power flowing into the subnetwork via the connection point with the predefined limit value, and
further increasing the predefined maximum power consumption when the electrical power flowing into the subnetwork via the connection point falls below the predefined limit value.

### Claim 6 (depends on 1)

The method as claimed in claim 1, wherein the measurement of the electrical power flowing via the connection point comprises measuring currents flowing via individual phases of the connection point.

### Claim 7 (depends on 6)

The method as claimed in claim 6, wherein a reduction in the maximum power consumption is performed when at least one of the currents flowing via the individual phases of the connection point exceeds a predefined limit value.

### Claim 8 (depends on 6)

The method as claimed in claim 6, wherein the maximum power consumption is set in such a manner that individual maximum values for a current consumption from a respective phase are set for individual phases of the subnetwork from which the electrical load consumes electrical power.

### Claim 9 (depends on 8)

The method as claimed in claim 8, wherein a reduction in a maximum value for a current consumption from a phase is performed when the current flowing via this phase or the difference between this current and a current flowing via another phase at the connection point exceeds a predefined limit value, wherein an absolute value of the reduction is, in particular, proportional to an absolute value of the exceedance.

### Claim 10 (depends on 9)

The method as claimed in claim 9, wherein the maximum values for the current consumption for all phases of the subnetwork from which the electrical load consumes electrical power are set to zero if a maximum power consumption which is below a predefined minimum value for the power consumption of the electrical load results from reducing maximum values for the current consumption.

### Claim 11 (depends on 9)

The method as claimed in claim 9, wherein the maximum value for the current consumption from a first phase is increased if the maximum value for the current consumption from a second phase is reduced and the maximum value for the current consumption from the first phase is below the predefined limit value.

### Claim 12

A device for connecting a multiphase subnetwork to a superordinate multiphase alternating voltage network, wherein the subnetwork has an energy production installation and an energy store, wherein the device is configured to transmit electrical power between the alternating voltage network and the subnetwork and comprises an AC/AC converter having a network connection, two inverter bridge circuits with an interposed intermediate circuit and a subnetwork connection, and a control device which is configured to set the electrical powers flowing via the individual phases of the subnetwork connection of the energy production installation and/or on the basis of power values of the energy store by controlling the inverter bridge circuits of the AC/AC converter.

### Claim 13 (depends on 12)

The device as claimed in claim 12, wherein the control device is communicatively connected to the energy production installation and/or the energy store and is configured to communicatively receive the power values of the energy production installation and/or of the energy store, respectively.

### Claim 14 (depends on 12)

The device as claimed in claim 12, wherein the control device is communicatively connected to a network control center and is configured to set the electrical powers flowing via the individual phases of the network connection of the AC/AC converter on the basis of communicatively transmitted preset values from the network control center by controlling the inverter bridge circuits of the AC/AC converter.

### Claim 15 (depends on 12)

The device as claimed in claim 12, wherein the AC/AC converter comprises the energy store in a structural unit, wherein the AC/AC converter is configured to feed electrical power into the energy store or to drain electrical power from the energy store by means of at least one of the inverter bridge circuits of the AC/AC converter.

### Claim 16 (depends on 14)

The device as claimed in claim 14, wherein the AC/AC converter is configured to provide an alternating voltage having a predefined frequency and amplitude and a corresponding alternating current within the subnetwork to operate loads arranged in the subnetwork.

### Claim 17

A method for operating a multiphase subnetwork which comprises an energy production installation and an energy store and is connected to a superordinate multiphase alternating voltage network via an AC/AC converter, wherein the AC/AC converter is configured to transmit electrical power between the alternating voltage network and the subnetwork and has a network connection, two inverter bridge circuits with an interposed intermediate circuit and a subnetwork connection, wherein the inverter bridge circuits of the AC/AC converter are controlled such that the electrical powers flowing via the individual phases of the subnetwork connection of the AC/AC converter are set on the basis of power values of the energy production installation and/or of the energy store.

### Claim 18 (depends on 17)

The method as claimed in claim 17, wherein the inverter bridge circuits of the AC/AC converter are controlled such that the electrical powers flowing via the individual phases of the network connection of the AC/AC converter are set such that a maximum difference between the electrical powers flowing via the individual phases of the network connection of the AC/AC converter is minimized, in particular such that said maximum difference is below a predefined unbalanced load limit value and less than a maximum difference between electrical powers flowing via the individual phases of the subnetwork connection of the AC/AC converter.

### Claim 19 (depends on 17)

The method as claimed in claim 17, wherein the energy store is connected to the subnetwork via a bidirectional inverter and provides an alternating voltage having a predefined frequency and amplitude for the purpose of operating loads arranged in the subnetwork, wherein the electrical power flowing via the subnetwork connection of the AC/AC converter is set on the basis of a deviation of the frequency in the subnetwork from a predefined reference frequency.

### Claim 20 (depends on 17)

The method as claimed in claim 17, wherein the AC/AC converter comprises the energy store in a structural unit, and electrical power is fed into the energy store or is drained from the energy store by means of at least one of the inverter bridge circuits of the AC/AC converter.

### Claim 21 (depends on 20)

The method as claimed in claim 20, wherein the AC/AC converter provides an alternating voltage having a predefined frequency and amplitude and a corresponding alternating current at its subnetwork connection to operate loads arranged in the subnetwork.