# US 2020/0393746 A1 · Projector

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2020/0393746 A1
- Document ID: US20200393746A1
- Status: Published application
- Kind: A1
- Application number: 16/898,598
- Filed: 2020-06-11
- Published: 2020-12-17
- Earliest claimed: 2019-06-12
- Assignees: Seiko Epson Corporation
- Applicants: Seiko Epson Corporation
- Inventors: Nobuo SUGIYAMA
- Web page: https://patentgrep.com/patent/US20200393746A1

## CPC

- G03B 21/16: Cooling; Preventing overheating
- H04N 9/3144: {Cooling systems (cooling of liquid crystal cells in general G02F1/133382; cooling of projectors not peculiar to the presence of an electronic spatial light modulator G03B21/16)}
- H04N 9/3155: {for controlling the light source (light source control per se H05B35/00 – H05B47/00; control of an illumination source for displays in general G09G3/3406)}
- H04N 9/3194: {including sensor feedback}
- G03B: APPARATUS OR ARRANGEMENTS FOR TAKING PHOTOGRAPHS OR FOR PROJECTING OR VIEWING THEM; APPARATUS OR ARRANGEMENTS EMPLOYING ANALOGOUS TECHNIQUES USING WAVES OTHER THAN OPTICAL WAVES; ACCESSORIES THEREFOR (optical parts of such apparatus G02B; photosensitive materials or processes for photographic purposes G03C; apparatus for processing exposed photographic materials G03D)
- H04N: PICTORIAL COMMUNICATION, e.g. TELEVISION

## Abstract

A projector including cooling target includes a controller and a cooler configured to cool the cooling target based on transformation of a refrigerant into gas. The cooler includes a refrigerant generator and a cooling air blower. The controller is configured to perform a first control and a second control. The controller performs one of the first and second controls based on information on the activation of the projector from the activation of the projector. In the second control, the controller performs at least one of a luminance control and an output control, the luminance control which reduces the luminance of the light outputted from the light source to a value smaller than the luminance of the light in the first control, and the output control which increases the output of the cooling air blower to a value larger than the output of the cooling air blower in the first control.

## Claims

### Claim 1

A projector including a cooling target, the projector comprising:
a light source configured to emit light;
a light modulator configured to modulate the light emitted from the light source in accordance with an image signal;
a projection optical apparatus configured to project the light modulated by the light modulator;
a cooler configured to cool the cooling target based on transformation of a refrigerant into a gas; and
a controller configured to control at least one of the cooler and the light source,
wherein the cooler includes
a refrigerant generator configured to generate the refrigerant,
a refrigerant sender configured to send the generated refrigerant toward the cooling target, and
a cooling air blower configured to deliver air to the cooling target,
the controller is configured to perform a first control and a second control, the first and second controls which control at least one of the cooling air blower and the light source,
the controller performs one of the first control and the second control based on information on activation of the projector from a time of the activation of the projector, and
in the second control, the controller performs at least one of a luminance control and an output control, the luminance control which reduces luminance of the light outputted from the light source in the second control to a value smaller than the luminance of the light outputted from the light source in the first control, and the output control which increases output of the cooling air blower in the second control to a value larger than the output of the cooling air blower in the first control.

### Claim 2 (depends on 1)

The projector according to claim 1,
wherein the controller performs both the luminance control and the output control in the second control.

### Claim 3 (depends on 1)

The projector according to claim 1,
wherein when performing the second control from the time of the activation of the projector, the controller terminates the second control and then performs the first control.

### Claim 4 (depends on 3)

The projector according to claim 3,
wherein when performing the second control from the time of the activation of the projector and a period for which the second control was performed is longer than or equal to a predetermined period, the controller terminates the second control.

### Claim 5 (depends on 3)

The projector according to claim 3,
further comprising a temperature sensor configured to measure a temperature of the cooling target,
wherein when performing the second control from the time of the activation of the projector, the controller terminates the second control based on the temperature of the cooling target provided from the temperature sensor.

### Claim 6 (depends on 5)

The projector according to claim 5,
wherein when performing the second control from the time of the activation of the projector and the temperature of the cooling target provided from the temperature sensor starts lowering at a rate of change greater than or equal to a predetermined value, the controller terminates the second control.

### Claim 7 (depends on 5)

The projector according to claim 5,
wherein during the first control, the controller terminates the first control based on the temperature of the cooling target provided from the temperature sensor and performs the second control.

### Claim 8 (depends on 7)

The projector according to claim 7,
wherein during the first control, the controller terminates the first control when the temperature of the cooling target provided from the temperature sensor is higher than or equal to a predetermined value, and performs the second control.

### Claim 9 (depends on 1)

The projector according to claim 1,
wherein the information on the activation of the projector includes a number of the activation of the projector, and
when the projector is activated for the first time, the controller performs the second control from the time of the activation of the projector.

### Claim 10 (depends on 1)

The projector according to claim 1,
wherein the information on the activation of the projector includes a length of an off period for which the projector was powered off, and
when the length of the off period is longer than or equal to a predetermined length, the controller performs the second control from the time of the activation of the projector.

### Claim 11 (depends on 10)

The projector according to claim 10,
wherein the predetermined length is at least one week.

### Claim 12 (depends on 1)

The projector according to claim 1,
wherein when the second control is performed from the time of the activation of the projector, an execution period of time for which the second control was performed is longer than or equal to a period of a startup time of the projector.

### Claim 13 (depends on 12)

The projector according to claim 12,
wherein when the second control is performed from the time of the activation of the projector, the execution period is longer than or equal to 5 minutes but shorter than or equal to 20 minutes.

### Claim 14 (depends on 1)

The projector according to claim 1,
wherein the cooling target is the light modulator.