# US 2020/0272118 A1 · Method of controlling a microgrid, power management system, and energy management system

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2020/0272118 A1
- Document ID: US20200272118A1
- Status: Published application
- Kind: A1
- Application number: 16/797,412
- Filed: 2020-02-21
- Published: 2020-08-27
- Earliest claimed: 2019-02-22
- Assignees: Hitachi Energy Switzerland AG
- Applicants: ABB Power Grids Switzerland AG
- Inventors: Andrew Tuckey; Francesco Baccino
- Web page: https://patentgrep.com/patent/US20200272118A1

## CPC

- G05B 19/042: using digital processors (G05B19/05 takes precedence)
- H02J 3/003: {Load forecast, e.g. methods or systems for forecasting future load demand}
- H02J 3/381: {Dispersed generators}
- H02J 13/13: characterised by the transmission of data to equipment in the power network
- G05B 2219/2639: Energy management, use maximum of cheap power, keep peak load low
- H02J 3/12: Arrangements for adjusting voltage in AC networks by changing a characteristic of the network load
- H02J 3/46: Controlling the sharing of generated power between the generators, sources or networks
- H02J 2105/10: Local stationary networks having a local or delimited stationary reach
- Y02B 70/3225: Demand response systems, e.g. load shedding, peak shaving
- Y02E 60/00: Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation
- Y02P 80/14: District level solutions, i.e. local energy networks
- Y04S 20/222: Demand response systems, e.g. load shedding, peak shaving
- Y04S 40/12: characterised by data transport means between the monitoring, controlling or managing units and monitored, controlled or operated electrical equipment
- G05B: CONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS (systems for controlling or regulating non-electric variables G05D; systems for regulating electric or magnetic variables G05F; control devices or systems insofar as characterised by mechanical features only G05G)
- H02J: ELECTRIC POWER NETWORKS; CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- Y02B: CLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
- Y02E: REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02P: CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y04S: SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS

## Abstract

A method of controlling a microgrid includes receiving, by a power management system, PMS, of the microgrid, operating point values for a plurality of controllable assets. The method includes determining, by the PMS, an asset headroom. The method includes determining, by the PMS, a modified operating point value that is dependent on the received operating point value of the controllable asset, the determined asset headroom of the controllable asset, and a total power offset of the microgrid. The method includes controlling, by the PMS, the controllable assets for which the modified operating point values have been determined in accordance with the modified operating point values.

## Claims

### Claim 1

A method of controlling a microgrid, the method comprising:
receiving, by a power management system, PMS, of the microgrid, operating point values for a plurality of controllable assets of the microgrid;
determining, by the PMS, an asset headroom that is dependent on a difference between an asset-specific fixed parameter value for the controllable asset and the received operating point value for the controllable asset;
determining, by the PMS, a modified operating point value for each controllable asset of at least a sub-set of the plurality of controllable assets, the modified operating point value for a controllable asset being dependent on the received operating point value of the controllable asset, the determined asset headroom of the controllable asset, and a total power offset of the microgrid; and
controlling, by the PMS, the controllable assets for which the modified operating point values have been determined in accordance with the modified operating point values.

### Claim 2 (depends on 1)

The method of claim 1, wherein determining the modified operating point value comprises incrementing or decrementing the received operating point value by an amount that is proportional to the total power offset of the microgrid, the total power offset being a difference between a target power generation of controllable assets of the microgrid and an actual power generation of the controllable assets of the microgrid.

### Claim 3 (depends on 1)

The method of claim 1, wherein determining the modified operating point value comprises determining a product of the total power offset of the microgrid and an asset-specific scaling factor, the asset-specific scaling factor being dependent on the asset headroom.

### Claim 4 (depends on 3)

The method of claim 3, wherein the asset-specific scaling factor is a monotonous function of the asset headroom in particular a linear function of the asset headroom.

### Claim 5 (depends on 3)

The method of claim 3, wherein the asset-specific scaling factor is dependent on the asset headroom of all controllable assets for which the modified operating point values are determined.

### Claim 6 (depends on 3)

The method of claim 3, wherein a sum of the asset-specific scaling factors is equal to 1.

### Claim 7 (depends on 1)

The method of claim 1, wherein
the received operating point values are power setpoints or power limits, and
the asset-specific fixed parameter value is selected from a group consisting of: a nominal maximum power rating, a nominal minimum power rating, an overload power rating, a zero power rating.

### Claim 8 (depends on 1)

The method of claim 1, wherein the modified operating point values are continually determined.

### Claim 9

A power management system, PMS, for a microgrid, comprising:
an interface operative to receive operating point values for a plurality of controllable assets of the microgrid; and
at least one integrated semiconductor circuit operative to
determine an asset headroom that is dependent on a difference between an asset-specific fixed parameter value for the controllable asset and the received operating point value for the controllable asset;
determine a modified operating point value for each controllable asset of at least a sub-set of the plurality of controllable assets, the modified operating point value for a controllable asset being dependent on the received operating point value of the controllable asset, the asset headroom of the controllable asset, and a total power offset of the microgrid; and
control the controllable assets for which the modified operating point values have been determined in accordance with the modified operating point values.

### Claim 10

A method of controlling a microgrid including a plurality of controllable assets, the method comprising:
retrieving, by an energy management system, EMS, a forecast variable value for at least one forecast variable;
executing, by the EMS, an optimization routine to determine an operating point vector for the plurality of controllable assets that is optimal for the retrieved forecast variable value, the operating point vector including an operating point value for each of the plurality of controllable assets;
executing, by the EMS, the optimization routine to determine several additional operating point vectors for the plurality of controllable assets, the additional operating point vectors being determined to be optimal for modified forecast variable values that deviate from the retrieved forecast variable value; and
providing both the operating point vector and the several additional operating point vectors to a power management system, PMS, of the microgrid.

### Claim 11 (depends on 10)

The method of claim 10, wherein the several additional operating point vectors are determined for the modified forecast variable values that
deviate from the retrieved forecast variable value by pre-defined percentages or by pre-defined absolute differences; and/or
are distributed linearly or non-linearly.

### Claim 12 (depends on 10)

The method of claim 10, wherein the operating point vector and the several additional operating point vectors are calculated concurrently using parallel processing.

### Claim 13 (depends on 1, 10)

The method of claim 10, further comprising:
in response to detecting, by the PMS, that an actual value of the forecast variable is not equal to the retrieved forecast variable value and the modified forecast variable values,
performing an interpolation between operating point vectors;
performing an extrapolation using at least one of the operating point vectors; or
performing the method according to claim 1.

### Claim 14

An energy management system, EMS, for a microgrid including a plurality of controllable assets, the EMS comprising:
an interface operative to retrieve a forecast variable value for at least one forecast variable; and
at least one integrated semiconductor circuit operative to
execute an optimization routine to determine an operating point vector for the plurality of controllable assets that is optimal for the retrieved forecast variable value, the operating point vector including an operating point value for each of the plurality of controllable assets;
execute the optimization routine to determine several additional operating point vectors for the plurality of controllable assets, the additional operating point vectors being determined to be optimal for modified forecast variable values that deviate from the retrieved forecast variable value; and
provide the operating point vector and the several additional operating point vectors to a power management system, PMS, of the microgrid.

### Claim 15 (depends on 9, 14)

A microgrid, comprising:
a plurality of controllable assets, and
at least one of the power management system of claim 9 and the energy management system of claim 14.

### Claim 16 (depends on 10)

The method of claim 10, further comprising determining, by the EMS, the modified forecast variable values.

### Claim 17 (depends on 16)

The method of claim 16, wherein one or several of the modified forecast variable values are determined by the EMS as a function of a retrieved forecast variable value and/or wherein one or several of the modified forecast variable values are determined by the EMS independently of any retrieved forecast variable value.

### Claim 18 (depends on 10)

The method of claim 10, wherein one or several of the modified forecast variable values are determined by the EMS based on a statistical distribution.

### Claim 19 (depends on 10)

The method of claim 10, wherein a number of the several additional operating point vectors that is determined is adjusted dynamically in a time-varying manner.

### Claim 20 (depends on 19)

The method of claim 19, wherein the number of the additional operating point vectors is adjusted in dependence on a computational load of the EMS and/or an available communication bandwidth between the EMS and the PMS.