# US 2020/0140242 A1 · Ship unloading control system, ship loading control system, and related systems and apparatuses

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2020/0140242 A1
- Document ID: US20200140242A1
- Status: Published application
- Kind: A1
- Application number: 16/677,436
- Filed: 2019-11-07
- Published: 2020-05-07
- Earliest claimed: 2018-11-07
- Assignees: Shanghai Tusen Weilai Artificial Intelligence Technology Co., Ltd.
- Applicants: Shanghai Tusen Weilai Artificial Intelligence Technology Co., Ltd.
- Inventors: Chao Yan
- Web page: https://patentgrep.com/patent/US20200140242A1

## CPC

- B66C 13/48: Automatic control of crane drives for producing a single or repeated working cycle; Program control
- G06Q 10/06314: {Calendaring for a resource}
- B63H 25/02: Initiating means for steering {, for slowing down, otherwise than by use of propulsive elements, or for dynamic anchoring}
- B65G 67/603: {using devices specially adapted for articles}
- G05D 1/0217: {in accordance with energy consumption, time reduction or distance reduction criteria}
- G06Q 10/0631: Resource planning, allocation, distributing or scheduling for enterprises or organisations
- G06Q 10/08: Logistics, e.g. warehousing, loading or distribution; Inventory or stock management
- G06Q 10/083: Shipping
- G06Q 10/0843: {using forecasting or optimisation}
- G06Q 10/087: Inventory or stock management, e.g. order filling, procurement or balancing against orders
- G06Q 10/08744: {by distributed inventory management}
- G06Q 10/109: Time management, e.g. calendars, reminders, meetings or time accounting
- G06Q 10/1097: {using calendar-based scheduling for task assignment}
- B63H 2025/028: {using remote control means, e.g. wireless control; Equipment or accessories therefor}
- B66C: CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES ({specially adapted for lifting invalids A61G7/10;} rope, cable, or chain winding mechanisms, braking or detent devices therefor B66D; specially adapted for nuclear reactors G21)
- G06Q: INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- B63H: MARINE PROPULSION OR STEERING (propulsion of air-cushion vehicles B60V1/14; specially adapted for submarines, other than nuclear propulsion, B63G; specially adapted for torpedoes F42B19/00)
- B65G: TRANSPORT OR STORAGE DEVICES, e.g. CONVEYORS FOR LOADING OR TIPPING, SHOP CONVEYOR SYSTEMS OR PNEUMATIC TUBE CONVEYORS (packaging B65B; handling thin or filamentary materials, e.g. paper sheets or thread, B65H; cranes B66C; portable mobile or lifting or hauling appliances, e.g. hoists, B66D; devices for lifting or lowering goods for loading or unloading purposes, e.g. fork-lift trucks, B66F9/00; emptying bottles, jars, casks, barrels or similar containers, not otherwise provided for, B67C9/00; delivering or transferring liquids B67D; filling or discharging vessels for liquefied, solidified or compressed gases F17C; pipe-line systems for fluids F17D)
- G05D: SYSTEMS FOR CONTROLLING OR REGULATING NON-ELECTRIC VARIABLES

## Abstract

The present disclosure provides a ship unloading control system, a ship loading control system and related systems and apparatuses, capable of achieving fully automated ship loading and unloading. The ship unloading control system includes: a scheduling center system configured to generate a ship unloading plan based on ship information and container information of a target ship and shore crane apparatus information, generate a ship berthing task and a ship unloading task based on the ship unloading plan, and transmit the ship berthing task and the ship unloading task to a ship control system of the target ship and a shore crane control system of a target shore crane apparatus, respectively; the ship control system configured to transmit the ship information and the container information to the scheduling center system, control the target ship to move to an operation area corresponding to the target shore crane apparatus in accordance with the received ship berthing task, and transmit a ship in-position notification message to the shore crane control system of the target shore crane apparatus; and the shore crane control system configured to control, upon receiving the ship in-position notification message from the ship control system, the target shore crane apparatus to load a container on the target ship onto a transportation vehicle in accordance with the ship unloading task.

## Claims

### Claim 1

A ship unloading control system, comprising:
a scheduling center system configured to generate a ship unloading plan based on ship information and container information of a target ship and shore crane apparatus information, generate a ship berthing task and a ship unloading task based on the ship unloading plan, and transmit the ship berthing task and the ship unloading task to a ship control system of the target ship and a shore crane control system of a target shore crane apparatus, respectively;
the ship control system configured to transmit the ship information and the container information to the scheduling center system, control the target ship to move to an operation area corresponding to the target shore crane apparatus in accordance with the received ship berthing task, and transmit a ship in-position notification message to the shore crane control system of the target shore crane apparatus; and
the shore crane control system configured to control, upon receiving the ship in-position notification message from the ship control system, the target shore crane apparatus to load a container on the target ship onto a transportation vehicle in accordance with the ship unloading task.

### Claim 2 (depends on 1)

The ship unloading control system of claim 1, wherein the ship information comprises ship arrival time and ship state information, the shore crane apparatus information comprises operation time information of each shore crane apparatus in a port area, the container information comprises a number of containers and identification information and a type of goods carried by each container, and the scheduling center system being configured to generate the ship unloading plan based on the ship information and container information of the target ship and the shore crane apparatus information comprises the scheduling center system being configured to:
determine the target shore crane apparatus based on the ship arrival time and the operation time information of each shore crane apparatus in the shore crane apparatus information;
estimate ship unloading start time and ship unloading end time based on the ship arrival time, the operation time information of the target shore crane apparatus and the number of containers, and determine a target container area for each container based on the type of goods carried by the container and information on container areas in the port area; and
generate the ship unloading plan containing identification information of the target ship, identification information of the target shore crane apparatus, the ship unloading start time, the ship unloading end time and the identification information and the target container area for each container.

### Claim 3 (depends on 2)

The ship unloading control system of claim 2, wherein the scheduling center system being configured to determine the target shore crane apparatus based on the ship information and the shore crane apparatus information comprises the scheduling center system being configured to:
determine one or more shore crane apparatuses in an idle state at the ship arrival time based on the ship arrival time and the operation time information of each shore crane apparatus; and
select one of the determined one or more shore crane apparatuses as the target shore crane apparatus.

### Claim 4 (depends on 2)

The ship unloading control system of claim 2, wherein the scheduling center system being configured to generate the ship berthing task and the ship unloading task based on the ship unloading plan comprises the scheduling center system being configured to:
generate the ship berthing task containing identification information and an operation area of the target shore crane apparatus, based on the ship unloading plan; and
generate the ship unloading task containing identification information of the target ship, ship unloading start time, ship unloading end time and identification information and a target container area for each container, based on the ship unloading plan.

### Claim 5 (depends on 1)

The ship unloading control system of claim 1, wherein the ship control system being configured to transmit the ship information and the container information to the scheduling center system comprises the ship control system being configured to:
determine a travel time length from a current location of the target ship to a port based on the current location, a location of the port and a travel route;
estimate arrival time at which the target ship arrives at the port based on the travel time length and current time; and
transmit the ship information containing the estimated arrival time and ship state information and the container information to the scheduling center system.

### Claim 6 (depends on 1)

The ship unloading control system of claim 1, wherein the shore crane control system being configured to control the target shore crane apparatus to load the container on the target ship onto the transportation vehicle in accordance with the ship unloading task comprises the shore crane control system being configured to:
confirm an identity of each container on the target ship in a predetermined container unloading order and control the target shore crane apparatus to hoist each container when its identity is confirmed; and
control, upon receiving a vehicle in-position notification message from a vehicle control system of the transportation vehicle, the target shore crane apparatus to load the container onto the transportation vehicle, mark the container in the ship unloading task as in an unloaded state, and transmit a ship unloading completion notification message to the scheduling center system and/or the ship control system of the target ship when determining that all containers in the ship unloading task are in the unloaded state.

### Claim 7 (depends on 6)

The ship unloading control system of claim 6, wherein the predetermined container unloading order is an order in which containers are unloaded by columns, from top to bottom per column, and
the shore crane control system is further configured to, when confirmation of the identity fails, lift and place the container on top of another column of containers whose identities have been confirmed on the target ship.

### Claim 8

A shore crane control system, comprising at least one machine executable instruction, the at least one machine executable instruction comprising a shore crane communication module and a hoisting control module, wherein the at least one machine executable instruction is executed by a processor such that:
the shore crane communication module is configured to transmit and receive information, and
the hoisting control module is configured to receive a ship unloading task from a scheduling center system via the shore crane communication module, and upon receiving a ship in-position notification message from a ship control system via the shore crane communication module, control a target shore crane apparatus to load a container on a target ship onto a transportation vehicle in accordance with the ship unloading task.

### Claim 9 (depends on 8)

The shore crane control system of claim 8, wherein the hoisting control module being configured to control the target shore crane apparatus to load the container on the target ship onto the transportation vehicle in accordance with the ship unloading task comprises the hoisting control module being configured to:
confirm an identity of each container on the target ship in a predetermined container unloading order and control the target shore crane apparatus to hoist each container when its identity is confirmed; control the target shore crane apparatus to load the container onto the transportation vehicle upon receiving a vehicle in-position notification message from a vehicle control system of the transportation vehicle via the shore crane communication module, and mark the container in the ship unloading task as in an unloaded state; and
transmit a ship unloading completion notification message to the scheduling center system and/or the ship control system of the target ship when determining that all containers in the ship unloading task are in the unloaded state.

### Claim 10 (depends on 9)

The shore crane control system of claim 9, wherein the predetermined container unloading order is an order in which containers are unloaded by columns, from top to bottom per column, and
the hoisting control module is further configured to, when confirmation of the identity fails, control the target shore crane apparatus to lift and place the container on top of another column of containers whose identities have been confirmed on the target ship.

### Claim 11

A ship loading control system, comprising:
a scheduling center system configured to determine a ship loading plan based on ship information, container information, and shore crane apparatus information, generate a ship berthing task and a ship loading task based on the ship loading plan, and transmit the ship berthing task and the ship loading task to a ship control system of a target ship and a shore crane control system of a target shore crane apparatus, respectively;
the ship control system configured to control, upon receiving the ship berthing task, the target ship to move to an operation area corresponding to the target shore crane apparatus, and transmit a ship in-position notification message to the shore crane control system of the target shore crane apparatus; and
the shore crane control system configured to control, upon receiving the ship in-position notification message from the ship control system, the target shore crane apparatus to load a container on a transportation vehicle onto the target ship in accordance with the received ship loading task.

### Claim 12 (depends on 11)

The ship loading control system of claim 11, wherein the shore crane control system is further configured to:
confirm, upon receiving a vehicle in-position notification message from a vehicle control system of the transportation vehicle, identification information of the container on the transportation vehicle, control the target shore crane apparatus to load the container on the transportation vehicle onto the target ship when the identification information is confirmed, and mark the container in the ship loading task as in a loaded state; and
transmit a ship loading completion notification message to the scheduling center system and/or the ship control system of the target ship when determining that all containers in the ship loading task have been marked as in the loaded state.