# US 2020/0006946 A1 · Random variable generation for stochastic economic optimization of electrical systems, and related systems, apparatuses, and methods

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2020/0006946 A1
- Document ID: US20200006946A1
- Status: Published application
- Kind: A1
- Application number: 16/235,868
- Filed: 2018-12-28
- Published: 2020-01-02
- Earliest claimed: 2018-07-02
- Assignees: Demand Energy Networks, Inc.
- Applicants: Demand Energy Networks, Inc.
- Inventors: John Michael Fife; Rebecca G. Wolkoff; Cesar A. Silva-Monroy
- Web page: https://patentgrep.com/patent/US20200006946A1

## CPC

- G06Q 10/04: Forecasting or optimisation specially adapted for administrative or management purposes, e.g. linear programming or "cutting stock problem" (market predictions or forecasting for commercial activities G06Q30/0202)
- G05B 13/042: {in which a parameter or coefficient is automatically adjusted to optimise the performance}
- G05B 13/048: {using a predictor}
- G06Q 10/06315: {Needs-based resource requirements planning or analysis}
- G06Q 10/0639: Performance analysis of employees; Performance analysis of enterprise or organisation operations
- H02J 3/003: {Load forecast, e.g. methods or systems for forecasting future load demand}
- H02J 3/008: Circuit arrangements for power supply or distribution technologies responsive to energy trading
- H02J 3/17: Demand-responsive operation of AC power transmission or distribution networks
- H02J 3/322: {the battery being on-board an electric or hybrid vehicle, e.g. vehicle to grid arrangements [V2G], power aggregation, use of the battery for network load balancing, coordinated or cooperative battery charging}
- H02J 3/381: {Dispersed generators}
- G06F 17/11: for solving equations {, e.g. nonlinear equations, general mathematical optimization problems (optimization specially adapted for a specific administrative, business or logistic context G06Q10/04)}
- H02J 3/004: {Generation forecast, e.g. methods or systems for forecasting future energy generation}
- H02J 2101/10: Dispersed power generation using fossil fuels, e.g. diesel generators
- H02J 2101/22: Solar energy
- H02J 2101/40: Hybrid power plants, i.e. a plurality of different generation technologies being operated at one power plant
- Y02B 10/10: Photovoltaic [PV]
- Y02B 70/3225: Demand response systems, e.g. load shedding, peak shaving
- Y04S 20/222: Demand response systems, e.g. load shedding, peak shaving
- Y04S 50/10: Energy trading, including energy flowing from end-user application to grid
- G06Q: INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G05B: CONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS (systems for controlling or regulating non-electric variables G05D; systems for regulating electric or magnetic variables G05F; control devices or systems insofar as characterised by mechanical features only G05G)
- H02J: ELECTRIC POWER NETWORKS; CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- G06F: ELECTRIC DIGITAL DATA PROCESSING (computer systems based on specific computational models G06N)
- Y02B: CLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
- Y04S: SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS

## Abstract

Electrical system controllers, computer-readable storage media, and related methods for generating random variables for stochastic control of electrical systems. An electrical power system controller includes a processor. The processor is configured to generate an uncertainty metric based on observed input data, the uncertainty metric configured to indicate an uncertainty of an input variable. The processor is configured to generate a random variable based on the uncertainty metric to forecast the input data during a future period of time. The processor is also configured to generate a cost function corresponding to a cost of operating the electrical power system during the future period of time. The cost function is a function of the one or more random variables. The processor is further configured to control operation of the electrical power system during the future period of time based on an optimization of the cost function.

## Claims

### Claim 1

An electrical power system controller, comprising:
one or more data storage devices;
one or more observed input data interfaces configured to receive observed input data, the observed input data corresponding to observed values of one or more input variables during one or more previous periods of time; and
one or more processors configured to:
store the observed input data on the one or more data storage devices;
generate one or more uncertainty metrics based on the observed input data, the one or more uncertainty metrics configured to indicate an uncertainty of the one or more input variables;
generate one or more random variables based on the one or more uncertainty metrics to forecast input data during a future period of time;
generate a cost function corresponding to a cost of operating the electrical power system during the future period of time, wherein the cost function is a function of the one or more random variables; and
control operation of the electrical power system during the future period of time based on an optimization of the cost function.

### Claim 2 (depends on 1)

The electrical power system controller of claim 1, wherein the observed input data comprises observed electrical load data of one or more loads of the electrical power system.

### Claim 3 (depends on 1)

The electrical power system controller of claim 1, wherein the observed input data comprises observed electrical power generation data of one or more electrical power generators of the electrical power system.

### Claim 4 (depends on 1)

The electrical power system controller of claim 1, wherein the observed input data comprises observed market data.

### Claim 5 (depends on 1)

The electrical power system controller of claim 1, wherein the one or more uncertainty metrics comprise functions of sample variances of the observed values as functions of time of day.

### Claim 6 (depends on 1)

The electrical power system controller of claim 1, wherein one or more uncertainty metrics comprise functions of error between the observed values and forecasted values.

### Claim 7 (depends on 1)

The electrical power system controller of claim 1, wherein:
the one or more data storage devices are configured to store historic forecasted input data, the historic forecasted input data including one or more previously forecasted values of the one or more input variables as previously forecasted for the one or more previous periods of time; and
the one or more uncertainty metrics are generated based on a comparison between the observed input data and the historic forecasted input data.

### Claim 8 (depends on 7)

The electrical power system controller of claim 7, wherein the one or more uncertainty metrics are based on an error between the observed input data and the historic forecasted input data.

### Claim 9 (depends on 8)

The electrical power system controller of claim 8, wherein the one or more uncertainty metrics comprise a mean square of the error between the observed input data and the historic forecasted input data.

### Claim 10 (depends on 8)

The electrical power system controller of claim 8, wherein the one or more uncertainty metrics comprise a variance or standard deviation of the error between the observed input data and the historic forecasted input data.

### Claim 11 (depends on 1)

The electrical power system controller of claim 1, wherein the one or more uncertainty metrics comprise a sample variance or sample standard deviation of the observed input data.

### Claim 12 (depends on 1)

The electrical power system controller of claim 1, wherein the one or more uncertainty metrics comprise an uncertainty metric profile including varying values of an uncertainty metric at different points of time during a period of time, the period of time correlated to the future period of time and the one or more previous periods of time.

### Claim 13 (depends on 12)

The electrical power system controller of claim 12, wherein the uncertainty metric profile comprises an uncertainty of a forecasted load profile, the forecasted load profile corresponding to a forecasted load of the electrical power system at the different points of time during the future period of time.

### Claim 14 (depends on 12)

The electrical power system controller of claim 12, wherein the uncertainty metric profile comprises a predicted electrical power generation profile, the predicted electrical power generation profile corresponding to a predicted electrical power generation of one or more electrical power generators of the electrical power system at the different points of time during the future period of time.

### Claim 15 (depends on 1)

The electrical power system controller of claim 1, wherein the observed input data includes external input data, process variable data including measurements fed back from an electrical power system, or a combination of the external input data and the process variable data.

### Claim 16

A method of controlling an electrical power system, the method comprising:
receiving observed input data comprising external input data, the observed input data corresponding to observed values of one or more input variables during one or more previous periods of time;
storing the observed input data on one or more data storage devices;
generating one or more uncertainty metrics based on the observed input data, the one or more uncertainty metrics configured to indicate an uncertainty of the one or more input variables;
generating one or more random variables based on the one or more uncertainty metrics to forecast the input data during a future period of time;
generating a cost function corresponding to a cost of operating the electrical power system during the future period of time, wherein the cost function is a function of the one or more random variables; and
controlling operation of the electrical power system during the future period of time based on an optimization of the cost function.

### Claim 17 (depends on 16)

The method of claim 16, wherein generating one or more random variables comprises generating a random variable corresponding to an uncertainty of one or more system constraints.

### Claim 18 (depends on 16)

The method of claim 16, wherein generating one or more random variables comprises generating a random variable corresponding to an uncertainty of one or more cost elements.

### Claim 19 (depends on 18)

The method of claim 18, wherein the one or more cost elements comprise a net electrical cost of electrical power from an electrical grid and a net equipment operation cost of operating equipment of the electrical system.

### Claim 20 (depends on 19)

The method of claim 19, wherein the net equipment operation cost of operating the equipment of the electrical system comprises an equipment degradation cost of one or more energy storage systems, one or more electrical power generators, or combinations thereof.

### Claim 21 (depends on 18)

The method of claim 18, wherein the one or more cost elements comprise a net electrical cost of electrical power from an electrical grid, the net electrical cost of electrical power from the electrical grid including two or more of a time-of-use (ToU) supply charge, a demand charge, or a local contracted maneuver or incentive maneuver.

### Claim 22 (depends on 18)

The method of claim 18, wherein the one or more cost elements comprise a net electrical cost of electrical power from an electrical grid, the net electrical cost of electrical power from the electrical grid including a time-of-use (ToU) supply charge and a demand charge.

### Claim 23 (depends on 16)

The method of claim 16, wherein generating one or more random variables comprises generating a random variable corresponding to an uncertainty of a cost of operating a battery.

### Claim 24 (depends on 16)

The method of claim 16, wherein generating one or more random variables comprises generating a random variable corresponding to an uncertainty of fluctuations in one or more external inputs.

### Claim 25 (depends on 24)

The method of claim 24, wherein the one or more external inputs comprise one or more of predicted weather data, predicted building occupation, predicted demand rates for energy supplied by an electrical grid, predicted time of use (ToU) supply charges, predicted local contracted or incentive maneuvers, or combinations thereof.

### Claim 26 (depends on 16)

The method of claim 16, wherein generating one or more random variables comprises generating a random variable corresponding to an uncertainty of fluctuations in one or more process variables at the different points of time during the future period of time.

### Claim 27 (depends on 26)

The method of claim 26, wherein the one or more process variables comprise one or more of an unadjusted net power, an unadjusted demand, an adjusted net power, a demand, a load, a generation, an energy storage system (ESS) charge, a generation rate for an ESS, an energy storage system (ESS) state of charge (SoC), an ESS temperature, or an electrical meter output.

### Claim 28 (depends on 16)

The method of claim 16, wherein the optimization of the cost function comprises minimization of an expected value of an economic cost of operating the electrical power system during the future time period.