# US 2020/0004280 A1 · Electric power system control with planning of energy demand and energy efficiency using ami-based data analysis

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2020/0004280 A1
- Document ID: US20200004280A1
- Status: Published application
- Kind: A1
- Application number: 16/502,738
- Filed: 2019-07-03
- Published: 2020-01-02
- Earliest claimed: 2013-03-15
- Assignees: Dominion Energy, Inc.
- Applicants: Dominion Energy, Inc.
- Inventors: Melissa A. Peskin; Phillip W. Powell
- Web page: https://patentgrep.com/patent/US20200004280A1

## CPC

- G05F 1/10: Regulating voltage or current (G05F1/02 takes precedence)
- G05B 13/04: involving the use of models or simulators
- G05B 15/02: electric
- G06Q 10/06: Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q 50/06: Energy or water supply
- H02J 3/00: Circuit arrangements for AC mains or AC distribution networks
- H02J 3/12: Arrangements for adjusting voltage in AC networks by changing a characteristic of the network load
- H02J 13/1323: {using optical fibres}
- H02J 13/16: the power network being controlled at grid-level, e.g. using aggregators
- H02J 13/333: the equipment forming part of substations
- H02J 2103/30: Simulating, planning, modelling, reliability check or computer assisted design [CAD] of electric power networks
- Y02B 90/20: Smart grids as enabling technology in buildings sector (smart grids supporting the management or operation of end-user stationary applications in general, or like technologies with no associated climate change mitigation effect Y04S20/00)
- Y02E 40/70: Smart grids as climate change mitigation technology in the energy generation sector
- Y02E 60/00: Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation
- Y04S 10/50: Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications
- Y04S 20/00: Management or operation of end-user stationary applications or the last stages of power distribution; Controlling, monitoring or operating thereof
- Y04S 40/124: using wired telecommunication networks or data transmission busses
- Y04S 40/20: Information technology specific aspects, e.g. CAD, simulation, modelling, system security
- G05F: SYSTEMS FOR REGULATING ELECTRIC OR MAGNETIC VARIABLES
- G05B: CONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS (systems for controlling or regulating non-electric variables G05D; systems for regulating electric or magnetic variables G05F; control devices or systems insofar as characterised by mechanical features only G05G)
- G06Q: INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- H02J: ELECTRIC POWER NETWORKS; CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- Y02B: CLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
- Y02E: REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y04S: SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS

## Abstract

A method, apparatus, system and computer program is provided for controlling an electric power system, including implementation of an energy planning process (EPP) system which can be used to plan a voltage control and conservation (VCC) system applied to an electrical distribution connection system (EEDCS). The EPP system plans modifications to the EEDCS as a result of operating the VCC system in the “ON” state, in order to maximize the level of energy conservation achieved by the VCC system control of the EEDCS. The EPP system may also identify potential problems in the EEDCS for correction.

## Claims

### Claim 1

A control system for an electric power grid configured to supply electric power from a supply point to a plurality of consumption locations, the system comprising:
a plurality of sensors, wherein each sensor is located at a respective one of a plurality of distribution locations on the electric power grid at or between the supply point and at least one of the plurality consumption locations, and wherein each sensor is configured to sense at least one component of a supplied electric power received at the respective consumption location and at least one of the plurality of sensors is configured to generate measurement data based on the sensed component of the power; and,
a controller configured to receive the measurement data from the sensors and to communicate with at least one component adjusting device to adjust a component of the electric power grid based on a control point, wherein the controller is configured to determine an energy savings for at least one modification to the electric power grid,
wherein the at least one component adjusting device is configured to adjust a component of the electric power grid based on the at least one control point.

### Claim 2 (depends on 1)

The system of claim 1, wherein the at least one modification is a proposed modification.

### Claim 3 (depends on 1)

The system of claim 1, wherein the at least one modification is a variation of load.

### Claim 4 (depends on 1)

The system of claim 1, wherein the at least one modification is at least one of adding or removing a capacitor bank, adding or removing a regulator, adding or reducing impedance, and/or adding or removing distributed generation.

### Claim 5 (depends on 1)

The system of claim 1, wherein the energy savings is determined based on a change in available voltage and a conservation voltage reduction (CVR) factor.

### Claim 6 (depends on 5)

The system of claim 5, wherein the change in available voltage is associated with a proposed modification to the electric power grid.

### Claim 7 (depends on 6)

The system of claim 6, wherein the proposed modification is represented by changing at least one variable associated with the proposed modification in a linear model.

### Claim 8 (depends on 7)

The system of claim 7, the controller is configured to determine a plurality of energy savings respectively associated with a plurality of proposed modifications to the electric power grid.

### Claim 9 (depends on 5)

The system of claim 5, wherein the energy savings is determined based on a forecasted load over at least one interval.

### Claim 10 (depends on 9)

The system of claim 9, wherein the at least one interval is between, and including, at least one 24 hour interval of one hour intervals and yearly intervals of 8760 hour intervals.

### Claim 11 (depends on 5)

The system of claim 5, wherein the controller is further configured to generate a CVR factor based on a change in energy usage between a voltage conservation-voltage-reduction-on state and a conservation-voltage-reduction-off state.

### Claim 12 (depends on 5)

The system of claim 5, wherein the CVR factor is predetermined.

### Claim 13 (depends on 5)

The system of claim 5, further comprising a plurality of proposed modifications and the controller is further configured to optimize the plurality of proposed modifications based on energy savings.

### Claim 14 (depends on 1)

The system of claim 1, wherein the controller is further configured to derive a linear model for at least one power loss from an upstream location to a downstream location.

### Claim 15 (depends on 14)

The system of claim 14, wherein the controller is adapted to compare measurement data received from the sensors to the linear model and to previously fingerprinted deviations to determine an abnormal voltage operation indication for alarming and control.

### Claim 16 (depends on 14)

The system of claim 14 where the controller is further configured to compare the measurement data to the linear model to correlate a sensor to a phase location and circuit location.

### Claim 17 (depends on 11)

The system of claim 11, wherein the measurement data from a voltage conservation-voltage-reduction-on stare and a conservation-voltage-reduction-off state is paired together in a pairing process, the pairing process using blocks of hours where consistent toads exist and paired t comparisons can be calculated within predetermined limits.

### Claim 18

A non-transitory computer readable media having instructions for a control system for an electric power grid configured to supply electric power from a supply point to a plurality of consumption locations, the instructions comprising:
a sensor receiving instruction configured to receive measurement data from at least one of a plurality of sensors, wherein each sensor is located at a respective one of a plurality of distribution locations on the electric power grid at or between the supply point and at least one of the plurality of consumption locations, and wherein each sensor is configured to sense at least one component of a supplied electric power received at the respective distribution location;
a controller instruction configured to determine an energy savings for at least one modification to the electric power grid and to determine a control point; and
a component adjusting instruction configured to communicate with at least one component adjusting device and to cause the at least one component adjusting device to adjust a component of the electric power grid based on the at least one control point.

### Claim 19 (depends on 18)

The computer readable media of claim 18, wherein the at least one modification is a proposed modification.

### Claim 20 (depends on 18)

The computer readable media of claim 18, wherein the at least one modification is a variation of load.

### Claim 21 (depends on 18)

The computer readable media of claim 18, therein the at least one modification is at least one of adding/removing a capacitor bank, adding removing a regulator, adding/reducing impedance, and/or adding removing distributed generation.

### Claim 22 (depends on 18)

The computer readable media of claim 18 wherein the controller instruction is further configured to determine the energy savings based on a change in available voltage and a conservation voltage reduction (CVR) factor.

### Claim 23 (depends on 22)

The computer readable media of claim 22, wherein the change in available voltage is associated with a proposed modification to the electric power grid.

### Claim 24 (depends on 23)

The computer readable media of claim 23, wherein the proposed modification is represented by changing at least one variable associated with the proposed modification in a linear model.

### Claim 25 (depends on 24)

The computer readable media of claim 24, wherein to determine an energy savings for at least one modification to the electric power grid comprises to determine a plurality of energy savings respectively associated with a plurality of proposed modifications to the electric power grid.

### Claim 26 (depends on 22)

The computer readable media of claim 22, wherein the energy savings is determined based on a forecasted load over at least one interval.

### Claim 27 (depends on 26)

The computer readable media of claim 26, wherein the at least one interval is between, and including, at least one 24 hour interval of one hour intervals and yearly intervals of 8760 hour intervals.

### Claim 28 (depends on 22)

The computer readable media of claim 22, wherein the controller instruction is further configured to generate a CVR factor based on a change in energy usage between a voltage conservation-voltage-reduction-on state and a conservation-voltage-reduction-off state.

### Claim 29 (depends on 22)

The computer readable media of claim 22, wherein the CVR factor is predetermined.

### Claim 30 (depends on 22)

The computer readable media of claim 22, wherein the controller instruction is further configured to optimize a plurality of proposed modifications based on energy savings.

### Claim 31 (depends on 18)

The computer readable media of claim 18, wherein the controller instruction is further configured to derive a linear model for at least one power loss from an upstream location to a downstream location.

### Claim 32 (depends on 31)

The computer readable media of claim 31, wherein the controller instruction is adapted to compare measurement data received from the sensors to the linear model and to previously fingerprinted deviations to determine an abnormal voltage operation indication for alarming and control.

### Claim 33 (depends on 31)

The computer readable media of claim 31 where the controller instruction is further configured to compare the measurement data to the linear model to correlate a sensor to a phase location and circuit location.

### Claim 34 (depends on 28)

The computer readable media of claim 28, wherein the controller instruction is further configured to pair together, in a pairing process, measurement data from a voltage conservation-voltage-reduction-on state and a conservation-voltage-reduction-off state, the pairing process using blocks of hours where consistent loads exist and paired t comparisons can be calculated within predetermined limits.