# US 2019/0377528 A1 · Print management apparatus, print management system, and non-transitory computer readable medium

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2019/0377528 A1
- Document ID: US20190377528A1
- Status: Published application
- Kind: A1
- Application number: 16/352,848
- Filed: 2019-03-14
- Published: 2019-12-12
- Earliest claimed: 2018-06-12
- Assignees: Fuji Xerox Co., Ltd.
- Applicants: Fuji Xerox Co., Ltd.
- Inventors: Kenichirou HOTOKEISHI
- Web page: https://patentgrep.com/patent/US20190377528A1

## CPC

- G06F 3/1263: {based on job priority, e.g. re-arranging the order of jobs, e.g. the printing sequence}
- G06F 3/1203: {Improving or facilitating administration, e.g. print management}
- G06F 3/1204: {resulting in reduced user or operator actions, e.g. presetting, automatic actions, using hardware token storing data}
- G06F 3/1215: {achieving increased printing speed, i.e. reducing the time between printing start and printing end}
- G06F 3/1259: {Print job monitoring, e.g. job status}
- G06F 3/1282: {High volume printer device}
- G06F 3/1208: {resulting in improved quality of the output result, e.g. print layout, colours, workflows, print preview}
- G06F 3/1229: {Printer resources management or printer maintenance, e.g. device status, power levels}
- G06F 3/1262: {by grouping or ganging jobs}
- G06F 3/1286: {via local network}
- G06F: ELECTRIC DIGITAL DATA PROCESSING (computer systems based on specific computational models G06N)

## Abstract

A print management apparatus includes an allocation unit, a schedule reception unit, and a command reception unit. The allocation unit allocates a schedule item for processing related to generation of a printed material to an operation period of a process for generating the printed material based on print information. The schedule reception unit receives a change of the allocated schedule item from an operator or receives an addition of a schedule item for processing related to the generation of the printed material from the operator. The command reception unit receives a command for prioritizing one of a new schedule item obtained as a result of the change or the addition and an existing schedule item as a command for processing to be performed when the new schedule item partially or entirely overlaps with the existing schedule item.

## Claims

### Claim 1

A print management apparatus comprising:
an allocation unit that allocates a schedule item for processing related to generation of a printed material to an operation period of a process for generating the printed material based on print information;
a schedule reception unit that receives a change of the allocated schedule item from an operator or that receives an addition of a schedule item for processing related to the generation of the printed material from the operator; and
a command reception unit that receives a command for prioritizing one of a new schedule item obtained as a result of the change or the addition and an existing schedule item as a command for processing to be performed when the new schedule item partially or entirely overlaps with the existing schedule item.

### Claim 2 (depends on 1)

The print management apparatus according to claim 1,
wherein the allocation unit allocates another schedule item subsequent to the one of the schedule items to be prioritized based on the command.

### Claim 3 (depends on 2)

The print management apparatus according to claim 2,
wherein, in a case where the command indicates that the existing schedule item is to be prioritized, the allocation unit allocates the new schedule item subsequent to the existing schedule item without shifting the existing schedule item.

### Claim 4 (depends on 2)

The print management apparatus according to claim 2,
wherein, in a case where the command indicates that the new schedule item is to be prioritized, the allocation unit allocates the new schedule item within a period in which the existing schedule item is set and allocates the existing schedule item subsequent to the new schedule item.

### Claim 5 (depends on 2)

The print management apparatus according to claim 2,
wherein another existing schedule item behind the existing schedule item is allocated by the allocation unit such that the another existing schedule item does not overlap with a schedule item allocated in front of the another existing schedule item.

### Claim 6 (depends on 5)

The print management apparatus according to claim 5,
wherein a specific schedule item that is not time-changeable exists as a schedule item outside the operation period, and
wherein the print management apparatus further comprises an output unit that outputs a warning in a case where the schedule item for the processing related to the generation of the printed material overlaps with the specific schedule item due to the allocation performed by the allocation unit.

### Claim 7 (depends on 5)

The print management apparatus according to claim 5, further comprising:
an output unit that acquires a deadline for the processing related to the generation of the printed material and that outputs a warning in a case where a scheduled time point at which the processing ends exceeds the deadline due to the allocation performed by the allocation unit.

### Claim 8 (depends on 5)

The print management apparatus according to claim 5,
wherein the process for generating the printed material includes a plurality of steps that are sequentially executed,
wherein the allocation unit allocates the schedule item for the processing related to the generation of the printed material for each of the plurality of steps with regard to the print information, and
wherein the print management apparatus further comprises an output unit that acquires a deadline for the generation of the printed material based on the print information and that outputs a warning in a case where a scheduled time point at which the processing related to the generation of the printed material ends in a final step of the plurality of steps exceeds the deadline due to the allocation performed by the allocation unit.

### Claim 9 (depends on 1)

The print management apparatus according to claim 1, further comprising:
a display that displays a list of print information to which the schedule item for the processing related to the generation of the printed material based on the print information is not allocated by the allocation unit.

### Claim 10 (depends on 9)

The print management apparatus according to claim 9,
wherein the print information to which the schedule item is not allocated has a scheduled time point at which the processing related to the generation of the printed material ends, the scheduled time point exceeding a preset deadline as a deadline for the processing.

### Claim 11 (depends on 9)

The print management apparatus according to claim 9,
wherein the process for generating the printed material includes a plurality of steps that are sequentially executed,
wherein the allocation unit allocates the schedule item for the processing related to the generation of the printed material for each of the plurality of steps with regard to the print information, and
wherein the print information to which the schedule item is not allocated has a scheduled time point at which the processing related to the generation of the printed material ends in a final step of the plurality of steps, the scheduled time point exceeding a preset deadline as a deadline for the generation of the printed material based on the print information.

### Claim 12 (depends on 11)

The print management apparatus according to claim 11,
wherein the print information includes a plurality of pieces of print information grouped into one, and
wherein the deadline for the generation of the printed material based on the print information including the plurality of pieces of print information grouped into one is an earliest deadline of deadlines for the plurality of pieces of print information.

### Claim 13 (depends on 1)

The print management apparatus according to claim 1,
wherein the command reception unit receives the command for every new schedule item.

### Claim 14

A print management system comprising:
a print management apparatus including
an allocation unit that allocates a schedule item for processing related to generation of a printed material to an operation period of a process for generating the printed material based on print information,
a schedule reception unit that receives a change of the allocated schedule item from an operator or that receives an addition of a schedule item for processing related to the generation of the printed material from the operator, and
a command reception unit that receives a command for prioritizing one of a new schedule item obtained as a result of the change or the addition and an existing schedule item as a command for processing to be performed when the new schedule item partially or entirely overlaps with the existing schedule item; and
a printed-material generating device that performs the processing related to the generation of the printed material in accordance with the schedule item allocated by the allocation unit of the print management apparatus.

### Claim 15 (depends on 14)

The print management system according to claim 14,
wherein the printed-material generating device is a device that performs print processing based on the print information or a device that performs post-processing of the print processing.

### Claim 16

A non-transitory computer readable medium storing a program causing a computer to execute a process, the process comprising:
allocating a schedule item for processing related to generation of a printed material to an operation period of a process for generating the printed material based on print information;
receiving a change of the allocated schedule item from an operator or receiving an addition of a schedule item for processing related to the generation of the printed material from the operator; and
receiving a command for prioritizing one of a new schedule item obtained as a result of the change or the addition and an existing schedule item as a command for processing to be performed when the new schedule item partially or entirely overlaps with the existing schedule item.