# US 2019/0316369 A1 · Brick/block laying machine incorporated in a vehicle

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2019/0316369 A1
- Document ID: US20190316369A1
- Status: Published application
- Kind: A1
- Application number: 16/317,792
- Filed: 2017-07-14
- Published: 2019-10-17
- Earliest claimed: 2016-07-15
- Assignees: Fastbrick IP Pty Ltd
- Applicants: Fastbrick IP Pty Ltd
- Inventors: Mark PIVAC
- Web page: https://patentgrep.com/patent/US20190316369A1

## CPC

- G06F 30/13: Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
- B25J 5/00: Manipulators mounted on wheels or on carriages (B25J1/00 takes precedence; program-controlled manipulators B25J9/00)
- B25J 9/023: {Cartesian coordinate type}
- B25J 9/161: {Hardware, e.g. neural networks, fuzzy logic, interfaces, processor}
- B25J 9/1612: {characterised by the hand, wrist, grip control}
- B25J 9/162: {Mobile manipulator, movable base with manipulator arm mounted on it}
- B25J 9/1633: {compliant, force, torque control, e.g. combined with position control}
- B25J 9/1635: {flexible-arm control}
- B25J 9/1638: {compensation for arm bending/inertia, pay load weight/inertia}
- B25J 9/1651: {acceleration, rate control}
- B25J 9/1664: {characterised by motion, path, trajectory planning}
- B25J 9/1674: {characterised by safety, monitoring, diagnostic}
- B25J 9/1679: {characterised by the tasks executed}
- B25J 9/1684: {Tracking a line or surface by means of sensors}
- B25J 9/1694: {characterised by use of sensors other than normal servo-feedback from position, speed or acceleration sensors, perception control, multi-sensor controlled systems, sensor fusion}
- B25J 13/089: {Determining the position of the robot with reference to its environment}
- B25J 19/021: {Optical sensing devices}
- B25J 19/022: {using lasers}
- B28D 1/003: {Multipurpose machines; Equipment therefor}
- B28D 1/10: with provision for measuring
- B28D 1/186: {Tools therefor, e.g. having exchangeable cutter bits (B28D1/181 takes precedence; bits for picks or pick-holders for mining or quarrying E21C35/18)}
- B28D 7/005: {Devices for the automatic drive or the program control of the machines}
- B28D 7/04: for supporting or holding work {or conveying or discharging work (B28D1/047, B28D5/0041, B28D5/0052 take precedence)}
- B60P 1/48: using pivoted arms raisable above load-transporting element ({for refuse collecting vehicles B65F3/041}; load engaging elements B66C1/00 - B66C3/00)
- E04B 1/02: Structures consisting primarily of load-supporting, block-shaped, or slab-shaped elements (E04B1/32 - E04B1/36 take precedence)
- E04G 21/22: for setting building elements with mortar, e.g. bricklaying machines
- G05B 19/4097: characterised by using design data to control NC machines, e.g. CAD/CAM (G05B19/4093 takes precedence)
- G05B 19/416: characterised by control of velocity, acceleration or deceleration (G05B19/19 takes precedence)
- G05B 19/41815: {characterised by the cooperation between machine tools, manipulators and conveyor or other workpiece supply system, workcell}
- G05B 19/4182: {manipulators and conveyor only}
- G06F 16/00: Information retrieval; Database structures therefor; File system structures therefor
- G06F 16/1734: {Details of monitoring file system events, e.g. by the use of hooks, filter drivers, logs}
- H04W 4/70: Services for machine-to-machine communication [M2M] or machine type communication [MTC]
- B25J 9/1697: {Vision controlled systems}
- B60P 3/28: for transporting cranes (vehicles using cranes for self-loading or self-unloading B60P1/54; mobile or travelling cranes B66C)
- B66C 13/22: for electric drives (transmitting control pulses B66C13/40; systems or devices of general application H02P)
- E04B 2/04: Walls having neither cavities between, nor in, the solid elements
- E04F 21/023: {for applying adhesive, e.g. glue or mortar, on the covering elements, in particular tiles}
- G01C 15/002: {Active optical surveying means (optical plumbing G01C15/105)}
- G01S 17/66: Tracking systems using electromagnetic waves other than radio waves
- G05B 2219/35207: Design agent selects planning agent, which selects fabrication agent
- G05B 2219/39001: Robot, manipulator control
- G05B 2219/39172: Vehicle, coordination between manipulator arm and its moving vehicle
- G05B 2219/40257: Flexible macro manipulator with rigid attached micromanipulator
- G05B 2219/40298: Manipulator on vehicle, wheels, mobile
- G05B 2219/40513: Planning of vehicle and of its manipulator arm
- G05B 2219/45086: Brick laying, masonry robot
- G06F 2111/20: Configuration CAD, e.g. designing by assembling or positioning modules selected from libraries of predesigned modules
- Y02B 10/30: Wind power
- Y02P 90/02: Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
- G06F: ELECTRIC DIGITAL DATA PROCESSING (computer systems based on specific computational models G06N)
- B25J: MANIPULATORS; CHAMBERS PROVIDED WITH MANIPULATION DEVICES ({manipulators specially adapted for use in surgery A61B34/70; manipulators used in cleaning hollow articles B08B9/04}; manipulators associated with rolling mills B21B39/20; manipulators associated with forging machines B21J13/10; {manipulators associated with picking-up and placing mechanisms B23P19/007}; means for holding wheels or parts thereof B60B30/00; {vehicles with ground-engaging propulsion means, e.g. walking members B62D57/02, B62D57/032; devices for picking-up and depositing articles or materials between conveyors B65G47/90, B65G47/91; manipulators with gripping or holding means for transferring packages B65H67/065}; cranes B66C; {manipulators used in the protection or supervision of pipe-line installations F17D5/00; walking equipment adapted for nuclear steam-generators F22B37/006}; manipulators specially adapted for, or associated with, nuclear reactors G21C; {apparatus used for handling wafers during manufacture or treatment of semiconductor H10P72/50})
- B28D: WORKING STONE OR STONE-LIKE MATERIALS
- B60P: VEHICLES ADAPTED FOR LOAD TRANSPORTATION OR TO TRANSPORT, TO CARRY, OR TO COMPRISE SPECIAL LOADS OR OBJECTS (vehicles with special provisions for transporting patients or disabled persons, or their personal conveyances A61G3/00)
- E04B: GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS (border constructions of opening in walls, floors or ceilings E06B1/00; {electromagnetic shielding H05K9/0001})
- E04G: SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- G05B: CONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS (systems for controlling or regulating non-electric variables G05D; systems for regulating electric or magnetic variables G05F; control devices or systems insofar as characterised by mechanical features only G05G)
- H04W: WIRELESS COMMUNICATION NETWORKS (broadcast communication H04H; communication systems using wireless links for non-selective communication, e.g. wireless extensions H04M1/72)
- B66C: CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES ({specially adapted for lifting invalids A61G7/10;} rope, cable, or chain winding mechanisms, braking or detent devices therefor B66D; specially adapted for nuclear reactors G21)
- E04F: FINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS (windows, doors E06B)
- G01C: MEASURING DISTANCES, LEVELS OR BEARINGS; SURVEYING; NAVIGATION; GYROSCOPIC INSTRUMENTS; PHOTOGRAMMETRY OR VIDEOGRAMMETRY (measuring liquid level G01F; radio navigation, determining distance or velocity by use of propagation effects, e.g. Doppler effects, propagation time, of radio waves, analogous arrangements using other waves G01S)
- G01S: RADIO DIRECTION-FINDING; RADIO NAVIGATION; DETERMINING DISTANCE OR VELOCITY BY USE OF RADIO WAVES; LOCATING OR PRESENCE-DETECTING BY USE OF THE REFLECTION OR RERADIATION OF RADIO WAVES; ANALOGOUS ARRANGEMENTS USING OTHER WAVES
- Y02B: CLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
- Y02P: CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS

## Abstract

A self-contained truck-mounted brick laying machine (2) is described. A truck (1) supports the brick laying machine (2) which is mounted on a frame (3) on the truck chassis. The frame (3) supports packs or pallets of bricks (52, 53) placed on a platform (51). A transfer robot can then pick up an individual brick and move it to, or between either a saw (46) or a router (47) or a carousel (48). The carousel is located coaxially with a tower (10), at the base of the tower (10). The carousel (48) transfers the brick via the tower (10) to an articulated (folding about horizontal axis (16)) telescoping boom comprising first boom element in the form of telescopic boom (12, 14) and second boom element in the form of telescopic stick (15, 17, 18, 19, 20). The bricks are moved along the folding telescoping boom by linearly moving shuttles, to reach a brick laying and adhesive applying head (32). The brick laying and adhesive applying head (32) mounts to element (20) of the stick, about an axis (33) which is disposed horizontally. The poise of the brick laying and adhesive applying head (32) about the axis (33) is adjusted and is set in use so that the base (811) of a clevis (813) of the robotic arm (36) mounts about a horizontal axis, and the tracker component (130) is disposed uppermost on the brick laying and 110,111 adhesive applying head (32). The brick laying and adhesive applying head (32) applies adhesive to the brick and has a robot that lays the brick. Vision and laser scanning and tracking systems are provided to allow the measurement of as-built slabs, bricks, the monitoring and adjustment of the process and the monitoring of safety zones. The first, or any course of bricks can have the bricks pre machined by the router module (47) so that the top of the course is level once laid.

## Claims

### Claim 1

A brick laying machine incorporated in a vehicle, said machine having a foldable boom, foldable about at least one folding axis, said foldable boom being locatable in a folded stowed position longitudinally along said vehicle, and moveable to unfolded extended positions away from said vehicle; said boom having a near end arranged for pivotal movement about a first horizontal axis located on a turret, said turret being rotatable about a vertical axis; said foldable boom having first conveying apparatus to convey bricks therealong, to a brick laying and adhesive applying head located at a remote end of the foldable boom; and having fluid conveying apparatus to convey adhesive therealong, to an adhesive applicator located in said brick laying and adhesive applying head; said machine having a carousel extending at least partially around said turret near the base thereof, said turret having second conveying apparatus to convey bricks vertically from said carousel to said first conveying apparatus, said carousel being rotatable about a vertical axis to present a brick for access by said second conveying apparatus; said machine having at least one brick machining tool located beside said stowed position and having a loading bay to receive packs of bricks; said machine having programmable brick handling apparatus to convey bricks one by one from said loading bay to said carousel, optionally via said at least one brick machining tool, as pre-programmed.

### Claim 2 (depends on 1)

A brick laying machine as claimed in claim 1 wherein said first conveying apparatus comprises at least one shuttle equipped with a clamp to releasably hold a brick, said shuttle running along a track extending along at least part of said boom.

### Claim 3 (depends on 1)

A brick laying machine as claimed in claim 1 wherein said foldable boom comprises a first boom element and a second boom element pivotable about the at least one folding axis that is spaced from said first horizontal axis, and parallel therewith.

### Claim 4 (depends on 3)

A brick laying machine as claimed in claim 3 wherein each boom element has a shuttle equipped with a clamp to releasably hold a brick, said shuttle running along a track extending along each said boom element.

### Claim 5 (depends on 3)

A brick laying machine as claimed in claim 3 wherein at least one of said first boom element and said second boom element, has further elements arranged in telescoping interconnection.

### Claim 6

(canceled)

### Claim 7

A brick laying machine as claimed in claim wherein each element has a said track and one said shuttle arranged to run along said track, between opposed ends of each said element.

### Claim 8 (depends on 7)

A brick laying machine as claimed in claim 7 wherein said tracks are locatably arranged internally inside said elements, and said shuttles run inside their respective elements.

### Claim 9 (depends on 1)

A brick laying machine as claimed in claim 1 wherein the second conveying apparatus comprises a turret track extending vertically along said turret, said turret track having a shuttle with a turret shuttle clamp to clamp a brick, the shuttle conveying the brick from the carousel to the shuttle in the near end of the foldable boom.

### Claim 10 (depends on 9)

A brick laying machine as claimed in claim 9 wherein the turret supports a brick rotating mechanism having a clamp to clamp a brick presented by said turret shuttle clamp and wherein at least one of:
a. said brick rotating mechanism being provided to rotate a brick so that its longitudinal extent aligns with the longitudinal extent of said first boom element, for presentation to the shuttle in the near end of the foldable boom; and
b. said brick rotating mechanism is mounted about said first horizontal axis.

### Claim 11

(canceled)

### Claim 12 (depends on 1)

A brick laying machine as claimed in claim 1 wherein the carousel has a carousel clamp to clamp a brick received from the programmable brick handling apparatus.

### Claim 13 (depends on 12)

A brick laying machine as claimed in claim 12 wherein the carousel clamp can pivot from a first position in which it receives a brick from the programmable brick handling apparatus to a second position in which it presents the brick to the turret shuttle clamp.

### Claim 14 (depends on 1)

A brick laying machine as claimed in claim 1 wherein said turret, said carousel and said stowed position are located along a central longitudinal axis of said vehicle.

### Claim 15 (depends on 1)

A brick laying machine as claimed in claim 1 wherein said at least one brick machining tool comprises a first brick machining tool including a saw located to one side of the stowed position, and a second brick machining tool including a router located to another side of the stowed position.

### Claim 16 (depends on 15)

A brick laying machine as claimed in claim 15 wherein said first brick machining tool includes a clamp at least one of:
a. located to clamp a brick on a side of a saw cutting blade position; and
b. configured to clamp a brick on each side of a saw cutting blade position.

### Claim 17

(canceled)

### Claim 18 (depends on 15)

A brick laying machine as claimed in claim 15 wherein at least one of said first brick machining tool and said second brick machining tool is contained in an enclosure with a cover providing access for placement and removal of a brick by said programmable brick handling apparatus.

### Claim 19

(canceled)

### Claim 20 (depends on 15)

A brick laying machine as claimed in claim 15 wherein the second brick machining tool at least one of:
a. includes a clamp to clamp a brick, and an orientation assembly to orient the clamped brick in space to present to the router, to route slots and notches in bricks in order to chase cabling, or to mill bricks to a predetermined required height;
b. is mounted on a tri-axis motion assembly for moving the router in any combination of movement in three dimensions; and
c. includes a tool storage magazine spaced away from the clamp and orientation assembly and accessible by said router at a predetermined position of said tri-axis motion assembly, to access or store a routing bit or milling bit.

### Claim 21

(canceled)

### Claim 22

(canceled)

### Claim 23 (depends on 1)

A brick laying machine as claimed in claim 1 wherein said brick laying and adhesive applying head is pivotally mounted for controlled rotation to the remote end of the foldable boom about a second horizontal axis located on a clevis, said brick laying and adhesive applying head including a pivotable clamp to receive and clamp a brick presented by said first conveying apparatus, said pivotable clamp being pivotally mounted about said second horizontal axis; said brick laying and adhesive applying head supporting said adhesive applicator to apply adhesive to a brick presented by said pivotable clamp; said brick laying and adhesive applying head having a brick laying head mounted thereto by a mount located in a position away from said clevis, said brick laying head having a brick laying clamp moveable between a position to receive and clamp a brick held by said pivotable clamp, to a position in which said brick is released and laid.

### Claim 24 (depends on 23)

A brick laying machine as claimed in claim 23 wherein the pivotable clamp is at least one of:
a. mounted for rotation on the distal end of said second boom element; and
b. mounted on a linear sliding mount that has travel extending in a direction linearly through said second horizontal axis and normal thereto.

### Claim 25

(canceled)

### Claim 26 (depends on 1)

A brick laying machine as claimed in claim 1 including a tracker component mounted to said brick laying and adhesive applying head, wherein said brick laying and adhesive applying head has a robotic arm assembly with a brick laying clamp to grip and lay a brick, and said brick laying machine uses a tracker system to measure the position of the tracker component and applies compensating movement to the robotic arm assembly to correct for variance between programmed tracker component position and measured tracker component position.

### Claim 27 (depends on 26)

A brick laying machine as claimed in claim 26 wherein a further tracker component is supported on said brick laying clamp, and said brick laying machine uses a further tracker system to measure the position of the further tracker component and applies further compensating movement to the robotic arm assembly to correct for variance between programmed further tracker component position and measured further tracker component position.