# US 2019/0244312 A1 · Procedure and system for the calculation of the level of risk in the proximity of the excavation front of an underground work

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2019/0244312 A1
- Document ID: US20190244312A1
- Status: Published application
- Kind: A1
- Application number: 16/341,869
- Filed: 2017-10-16
- Published: 2019-08-08
- Earliest claimed: 2016-10-14
- Assignees: Sws Engineering S.P.A.
- Applicants: Sws Engineering S.P.A.
- Inventors: Andrea Danzi; Gabriele Eccher
- Web page: https://patentgrep.com/patent/US20190244312A1

## CPC

- G06Q 50/08: Construction
- G01V 20/00: Geomodelling in general
- G06Q 10/04: Forecasting or optimisation specially adapted for administrative or management purposes, e.g. linear programming or "cutting stock problem" (market predictions or forecasting for commercial activities G06Q30/0202)
- G06Q 10/0635: Risk analysis of enterprise or organisation activities
- E02D 29/00: {Independent} underground or underwater structures (underground tanks B65D88/76; hydraulic engineering, e.g. sealings or joints, E02B; underground garages E04H6/00; underground air-raid shelters E04H9/12; burial vaults E04H13/00); Retaining walls
- E02D 29/045: Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
- G06Q: INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G01V: GEOPHYSICS; GRAVITATIONAL MEASUREMENTS; DETECTING MASSES OR OBJECTS; TAGS (means for indicating the location of accidentally buried, e.g. snow-buried, persons A63B29/02)
- E02D: FOUNDATIONS; EXCAVATIONS; EMBANKMENTS (specially adapted for hydraulic engineering E02B); UNDERGROUND OR UNDERWATER STRUCTURES {(tunnels, tunnelling, mining E21)}

## Abstract

The system for the calculation of the level of risk in the proximity of the excavation front of an underground work comprises a determination and storage unit for the determination of a plurality of basic parameters needed for the calculation of the level of risk in the proximity of the excavation front of the underground work, starting from a plurality of documents in electronic format, and for the structured storage of the basic parameters inside a database; a definition unit of a plurality of scenarios which could occur in the proximity of an excavation front of the underground work, starting from the basic parameters stored on the database; an application unit, for each of the scenarios generated during the definition phase, of predefined geo-mechanical and hydro-geological models, for the calculation of a series of possible embodiments for each scenario; an aggregation unit for the aggregation of punctual evaluations of the level of risk for each possible embodiment, to obtain a synthesis of the risk calculated in the proximity of the excavation front of the underground work.

## Claims

### Claim 1

A system (S) for the calculation of the level of risk in the proximity of the excavation front of an underground work, wherein it comprises:
at least one determination and storage unit (U1) for the determination of a plurality of basic parameters needed for the calculation of the level of risk in the proximity of the excavation front of said underground work, starting from a plurality of documents (D1, D2) in electronic format, and for the structured storage of said basic parameters inside a database (DB);
at least one definition unit (U2) of a plurality of scenarios which could occur in the proximity of an excavation front of said underground work, starting from said basic parameters stored on said database (DB);
at least one application unit (U3), for each of said scenarios generated during said definition phase, of predefined geo-mechanical and hydro-geological models, for the calculation of a series of possible embodiments (R) for each scenario;
at least one aggregation unit (U4) for the aggregation of punctual evaluations of the level of risk for each possible embodiment (R), to obtain a synthesis of the risk calculated in the proximity of the excavation front of said underground work.

### Claim 2 (depends on 1)

System (S) according to claim 1, wherein said determination and storage unit (U1) comprises collection means (U11) of a plurality of documents (D1, D2) in electronic format.

### Claim 3 (depends on 2)

System (S) according to claim 2, wherein said documents (D1, D2) in electronic format comprise:
“closed format” documents (D1), for which no libraries are available for direct access to the structured data contained in the document itself;
“open format” documents (D2), for which libraries are available for direct access to the structured data contained in the document.

### Claim 4 (depends on 1)

System (S) according to one claim 1, wherein said determination and storage unit (U1) for the determination and storage of the basic parameters comprises extraction means (U12) for extracting the text contained in said documents (D1) in electronic format.

### Claim 5 (depends on 1)

System (S) according to claim 1, wherein said determination and storage unit (U1) for the determination and storage of the basic parameters comprises syntactic analysis means (U13) of said extracted text for the identification of said plurality of basic parameters.

### Claim 6 (depends on 1)

System (S) according to claim 1, wherein said determination and storage unit (U1) comprises normalization means (U14) of said basic parameters.

### Claim 7 (depends on 6)

System (S) according to claim 6, wherein said normalization means (U14) comprise at least one of: cleaning means (U141) of the data, processing means (U142) of the data, aggregation means (U143) of the data.

### Claim 8 (depends on 1)

System (S) according to claim 1, wherein said determination and structured storage unit (U1) comprises field mapping means (U15) between said basic parameters and the tables of said database (DB).

### Claim 9 (depends on 8)

System (S) according to claim 8, wherein said determination and structured storage unit (U1) comprises field mapping means (U16) for mapping between said basic parameters and the fields of the tables of said database (DB).

### Claim 10 (depends on 1)

System (S) according to claim 1, wherein said determination and structured storage unit (U1) comprises loading means (U17) of said basic parameters structured on said database (DB).

### Claim 11 (depends on 1)

System (S) according to claim 1, wherein said application unit (U3) comprises at least one of: at least one analytical module (U31) for the implementation of algorithms, at least one interoperability module (U32) adapted to operate with external libraries (L), at least one automatic learning module (U33).

### Claim 12 (depends on 1)

System (S) according to claim 1, wherein said aggregation unit (U4) comprises at least one of: at least one module (U41) for the representation of synthesis data along analysis dimensions referable to space; at least one module (U42) for the representation of synthesis data according to the analysis dimensions needed for the assessment and management of the risks, at least one module (U43) for the interactive analysis of data organized according to a multi-dimensional model.

### Claim 13

A procedure (P) for the calculation of the level of risk in the proximity of the excavation front of an underground work, comprising at least one of the following phases:
at least one design phase (F1) of an underground work;
at least one construction phase (F2) of said underground work;
at least one maintenance phase (F3) of said underground work;
wherein at least one of said design, construction and maintenance phases (F1, F2, F3) comprises the following phases:
at least one determination phase (F11, F21, F31) of a plurality of basic parameters needed for the calculation of the level of risk in the proximity of the excavation front of said underground work, starting from a plurality of documents (D1, D2) in electronic format;
at least one structured storage phase (F12, F22, F32) of said basic parameters within a database (DB);
at least one definition phase (F13, F23, F33) of a plurality of scenarios which could occur in the proximity of an excavation front of said underground work, starting from said basic parameters stored on said database (DB);
at least one application phase (F14, F24, F34) for each of said scenarios generated during said definition phase (F13, F23, F33), of predefined geo-mechanical and hydro-geological models, for the calculation of a series of possible embodiments for each scenario;
at least one aggregation phase (F15, F25, F35) of punctual evaluations of the level of risk for each possible embodiment, to obtain a synthesis of the risk calculated in the proximity of the excavation front of said underground work.

### Claim 14 (depends on 13)

Procedure according to claim 13, wherein that said determination phase (F11, F12, F13) comprises at least one step of collection of a plurality of documents (D1, D2) in electronic format.

### Claim 15 (depends on 13)

Procedure according to claim 13, wherein said documents (D1, D2) in electronic format comprise:
“closed format” documents (D1), for which no libraries are available for direct access to the structured data contained in the document itself;
“open format” documents (D2), for which libraries are available for direct access to the structured data contained in the document.

### Claim 16 (depends on 13)

Procedure according to claim 13, wherein said determination phase (F11, F12, F13) of the basic parameters comprises at least one extraction step of the text contained in said documents (D1, D2) in electronic format.

### Claim 17 (depends on 16)

Procedure according to claim 16, wherein said determination phase (F11, F12, F13) of the basic parameters comprises at least one syntactic analysis step of said extracted text for the identification of said plurality of basic parameters.

### Claim 18 (depends on 13)

Procedure according to claim 13, wherein said determination phase (F11, F12, F13) comprises at least one normalization step of said basic parameters.

### Claim 19 (depends on 18)

Procedure according to claim 18, wherein said normalization step comprise at least one of: at least one cleaning step of the data, at least one processing step of the data and at least one aggregation step of the data.

### Claim 20 (depends on 13)

Procedure according to claim 13, wherein said structured storage phase (F12, F22, F32) comprises at least one mapping step between said basic parameters and the tables of said database (DB).

### Claim 21 (depends on 20)

Procedure according to claim 20, wherein said structured storage phase (F12, F22, F32) comprises at least one field mapping step for mapping between said basic parameters and the fields of the tables of said database (DB).

### Claim 22 (depends on 21)

Procedure according to claim 21, wherein said structured storage phase (F12, F22, F32) comprises one loading step of said basic parameters structured on said database (DB).