# US 2019/0153735 A1 · Construction anchoring apparatus

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2019/0153735 A1
- Document ID: US20190153735A1
- Status: Published application
- Kind: A1
- Application number: 16/253,058
- Filed: 2019-01-21
- Published: 2019-05-23
- Earliest claimed: 2016-08-29
- Assignees: Anchor Ring Solutions, LLC
- Applicants: Anchor Ring Solutions, LLC
- Inventors: Charles Mayer; Michael J. Tomack; John P. Marra, JR.; Joseph Fugallo, III
- Web page: https://patentgrep.com/patent/US20190153735A1

## CPC

- E04G 21/3276: {Arrangements on buildings for connecting safety-lines (fastening devices for devices for lowering persons from buildings A62B1/04)}
- E04B 1/4142: {with transverse hook- or loop-receiving parts (E04B1/415 takes precedence)}
- E04B 2001/4192: {attached to concrete reinforcing elements, e.g. rods or wires}
- E04C 5/162: {Connectors or means for connecting parts for reinforcements (E04C5/168 takes precedence)}
- E04G: SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04B: GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS (border constructions of opening in walls, floors or ceilings E06B1/00; {electromagnetic shielding H05K9/0001})
- E04C: STRUCTURAL ELEMENTS; BUILDING MATERIALS (for bridges E01D; specially designed for insulation or other protection E04B; elements used as building aids E04G; for mining E21; for tunnels E21D; structural elements with broader range of application than for building engineering F16, particularly F16S)

## Abstract

A construction anchor apparatus has utility as a safety grip for engagement by construction personnel, and, in addition, a support apparatus for supporting and/or holding construction equipment including ductwork, electrical cables, plumbing, etc. The anchor apparatus is used in conjunction with rebar applied in concrete support walls, floors, ceilings, or other structural elements at a construction site.

## Claims

### Claim 1

A method, comprising:
positioning an anchor apparatus at a predetermined location to a structural element within a construction site;
securing a main module of the anchor apparatus to the structural element at the predetermined location;
passing rebar through openings in opposed walls of the main module;
coupling a support to a length of rebar extending through the main module; and
permitting the length of rebar to move within the openings of the main module in response to manipulation of the support.

### Claim 2 (depends on 1)

The method according to claim 1 wherein the main module defines a longitudinal axis and wherein permitting the length of rebar includes permitting reciprocal movement of the length of rebar within the openings along the longitudinal axis.

### Claim 3 (depends on 2)

The method according to claim 2 including utilizing the support to facilitate movement of construction personnel about the construction site.

### Claim 4 (depends on 2)

The method according to claim 2 including utilizing the support to support construction equipment or a safety net.

### Claim 5 (depends on 2)

The method according to claim 2 wherein the main module includes a rebar mount disposed on each wall of the opposed walls in general alignment with respective openings in the opposed walls and wherein passing the rebar includes advancing the rebar through rebar receiving apertures of the rebar mounts.

### Claim 6 (depends on 5)

The method according to claim 5 wherein the rebar mounts are mounted for reciprocal longitudinal movement relative to the longitudinal axis of the main module and wherein the rebar mounts longitudinally move during longitudinal movement of the length of rebar.

### Claim 7 (depends on 6)

The method according to claim 6 wherein the openings in the opposed walls of the main module are elongated along the longitudinal axis whereby during, longitudinal movement of the rebar mounts, the length of rebar traverses the openings in the opposed walls.

### Claim 8 (depends on 7)

The method according to claim 7 wherein the main module includes a module mount disposed on each wall of the opposed walls in general alignment with respective openings in the opposed walls and wherein the rebar mounts are coupled to the module mounts, and whereby during longitudinal movement of the rebar mounts, the rebar mounts move relative to the module mounts.

### Claim 9 (depends on 8)

The method according to claim 8 wherein the module mounts each include opposed rails which define internal grooves, and wherein the rebar mounts are received within the internal grooves of the module mounts, the rebar mounts sliding within the internal grooves during longitudinal movement of the rebar mounts.

### Claim 10 (depends on 1)

The method according to claim 1 including mounting an end cap to the main module to enclose an internal chamber defined by the main module.

### Claim 11 (depends on 1)

The method according to claim 1 including embedding the main module within the structural element.

### Claim 12 (depends on 11)

The method according to claim 11 including depositing cement within the main module whereby the main module becomes at least partially embedded within the structural element of the construction site.

### Claim 13 (depends on 1)

The method according to claim 1 wherein the main module includes at least one flange depending outwardly therefrom, and wherein securing the main module includes coupling the flange to the structural element.

### Claim 14 (depends on 1)

The method according to claim 1 wherein coupling the support includes attaching a coupling member to the length of rebar, and securing the support to the coupling member.

### Claim 15 (depends on 14)

The method according to claim 14 including biasing the coupling member outwardly relative to the main module.

### Claim 16 (depends on 1)

The method according to claim 1 including:
positioning a plurality of an anchor apparatuses at respective locations of one or more structural elements within a construction site;
securing a main module of each anchor apparatus to a respective structural element at the respective location;
passing rebar through openings in opposed walls of each main module;
coupling supports to a length of rebar extending through each main module; and
permitting the length of rebar to move within the openings of each main module in response to manipulation of the support.