# US 2018/0321646 A1 · Predicting responses of resources to demand response signals and having comfortable demand responses

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2018/0321646 A1
- Document ID: US20180321646A1
- Status: Published application
- Kind: A1
- Application number: 15/969,740
- Filed: 2018-05-02
- Published: 2018-11-08
- Earliest claimed: 2013-07-11
- Assignees: Honeywell International Inc.
- Applicants: Honeywell International Inc.
- Inventors: Edward Koch; David J. McCurnin; Seth Rourke; Nicholas Dalsin
- Web page: https://patentgrep.com/patent/US20180321646A1

## CPC

- G05B 15/02: electric
- H02J 3/00: Circuit arrangements for AC mains or AC distribution networks
- G05B 2219/2642: Domotique, domestic, home control, automation, smart house
- Y02B 70/30: Systems integrating technologies related to power network operation and communication or information technologies for improving the carbon footprint of the management of residential or tertiary loads, i.e. smart grids as climate change mitigation technology in the buildings sector, including also the last stages of power distribution and the control, monitoring or operating management systems at local level
- Y04S 20/20: End-user application control systems
- G05B: CONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS (systems for controlling or regulating non-electric variables G05D; systems for regulating electric or magnetic variables G05F; control devices or systems insofar as characterised by mechanical features only G05G)
- H02J: ELECTRIC POWER NETWORKS; CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- Y02B: CLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
- Y04S: SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS

## Abstract

An approach where a utility/ISO may dispatch demand response (DR) resources in real time without notification of a DR event. DR dispatches may involve sending specific load level commands to power generators that can respond to such commands in a predictable fashion. DR resources do not necessarily have the same level of control or predictability in their load responses. Accuracy of predicting a DR resource's response to a DR signal may be improved by restricting the DR signal to predefined finite values and, for each predefined finite value, have the DR resource continuously report back what its load response will be if one of those signal values is sent as a DR signal. A DR performed against a home may result in discomfort. But there may be a sufficient recovery rate for regaining the setpoint of a thermostat to attain comfort of the home within a reasonable period of time.

## Claims

### Claim 1

A system for adjusting demand on a utility/independent system operator (ISO) comprising:
a demand response management system (DRMS) configured to send demand response (DR) signals to two or more DR resources to affect a load demand on a utility/ISO; and
wherein:
the DRMS selects the DR signals from a set of predefined finite values;
the DRMS is configured to receive a predicted load response to each predefined finite value in the set of predefined finite values from the two or more DR resources;
the DRMS is configured to use predicted load responses received from the two or more DR resources to determine an estimated load shed for each of the two or more DR resources, respectively, if each of the two or more DR resources were to receive a DR signal;
the DRMS is configured to select one or more DR resources for participation in a DR event based on the estimated load shed for each of the two or more DR resources and based on a load shed goal for the DR event; and
the DRMS is configured to send a DR signal to each of the selected one or more DR resources to cause each of the two or more DR resources to change operation and reduce load demand on the utility/ISO.

### Claim 2 (depends on 1)

The system of claim 1, wherein the estimated load shed for each of the two or more DR resources is determined without modeling a DR strategy for each of the two or more DR resources and without modeling a DR load based on past load demand for each of the two or more DR resources.

### Claim 3 (depends on 1)

The system of claim 1, wherein the two or more DR resources continuously report respective predicted load responses to the DRMS.

### Claim 4 (depends on 1)

The system of claim 1, wherein the DRMS is configured to select a single predefined finite level of a DR signal from the set of predefined finite values for all selected one or more DR resources for participation in the DR event.

### Claim 5 (depends on 1)

The system of claim 1, wherein the DRMS is configured to individually select a predefined finite level of a DR signal from the set of predefined finite values for each of the selected one or more DR resources for participation in the DR event.

### Claim 6 (depends on 1)

The system of claim 1, wherein the set of predefined finite values of the DR signal comprises two or more predefined finite values.

### Claim 7 (depends on 1)

The system of claim 1, wherein:
the DRMS is configured to be in constant communication with the two or more DR resources; and
each DR resource of the two or more DR resources continuously reports what a respective load response in units of power will be if the DR resource receives a DR signal.

### Claim 8 (depends on 1)

The system of claim 1, wherein:
a display shows an actual load response versus time for the two or more DR resources receiving a DR signal in the past; and
the display shows a projection for a future.

### Claim 9 (depends on 8)

The system of claim 8, wherein for the future, the projection by the utility/ISO comprises the predicted load responses received from the two or more DR resources.

### Claim 10 (depends on 9)

The system of claim 9, wherein additional DR resources are aggregated for showing actual load response versus time for the additional DR resources in the past and with a projection of load responses for the future.

### Claim 11 (depends on 9)

The system of claim 9, wherein values of the predicted load responses of the two or more DR resources for each signal type are added together resulting in N levels of dispatches.

### Claim 12 (depends on 10)

The system of claim 10, wherein:
there are X number of the two or more DR resources; and
each DR resource can operate at N levels of dispatches resulting in a number of DR signal settings for a DR event on an order of X to a power of N.

### Claim 13

A system for adjusting demand on a utility/independent system operator (ISO) comprising:
a utility/ISO having a communication connection configured to connect with a demand response (DR) resource; and
wherein:
the utility/ISO is configured to send a DR signal via the communication connection from the utility/ISO to the DR resource to change operation of the DR resource;
the utility/ISO is configured to continuously receive a predicted load response from the DR resource if the DR resource were to receive the DR signal; and
the utility/ISO is configured to determine whether to send the DR signal to the DR resource based on the predicted load response received from the DR resource.

### Claim 14 (depends on 13)

The system of claim 13, wherein the utility/ISO is configured to determine whether to send the DR signal to the DR resource without modeling DR strategies of the DR resource.

### Claim 15 (depends on 13)

The system of claim 13, wherein the DR signal is restricted to one predefined finite value of a set of predefined finite values and the DR resource continuously reports back what its load response will be for each of predefined finite value of the set of predefined finite values.

### Claim 16

A demand response and comfort system comprising:
a demand response management system (DRMS) configured to send a demand response (DR) signal to a DR resource, the DR resource having a first degree of comfort; and
wherein:
the DR signal causes a change of the first degree of comfort to a second degree of comfort during a DR event initiated by the DRMS; and
the DR resource has a recovery rate for returning to the first degree of comfort from the second degree of comfort and the DR signal is based on the recovery rate.

### Claim 17 (depends on 16)

The system of claim 16, wherein the recovery rate comprises the first degree of comfort minus the second degree of comfort divided by an amount to time to reduce a difference of the first degree of comfort and the second degree of comfort to zero.

### Claim 18 (depends on 17)

The system of claim 17, wherein:
the first degree of comfort is a temperature as indicated by a thermostat setting at the DR resource; and
the second degree of comfort is a temperature at the DR resource.

### Claim 19 (depends on 17)

The system of claim 17, wherein the recovery rate of a resource is used by the DRMS in shedding a certain amount of energy demand.

### Claim 20 (depends on 17)

The system of claim 17, the DRMS is configured to select the second degree of comfort and the amount of time to reduce the difference of the first degree of comfort and the second degree of comfort to zero.