Method for configuring a production plant designed for performing at least one chemical reaction, wherein the production plant has at least one plant module, and a plant module for configuring the production plant, which plant module is chosen from a module database running on a first server system and/or is combined from a component database running on a second server system.
Claims10
A method for configuring a production plant designed for performing at least one chemical reaction,
- the production plant having at least one plant module, and a plant module being selected from a module database running on a first server system and/or being compiled from a component database running on a second server system in order to configure the production plant, and
- the selection and/or compiling of a plant module comprising:
- manual first input of process-specific technical requirements imposed on a plant module to a query mask of the module database and confirmation of the input;
- comparison of the first input with at least one technical parameter of the multiplicity of plant modules, which is stored in the module database and defines a process-specific property of a respective plant module, on the first server system and, in the event of a negative result:
- identification of at least one plant module, the process-specific property of which does not comply with the process-specific technical requirements, in an output mask of the module database;
- identification of at least one part component of the identified plant module which does not comply with the requirements imposed on the plant module, and/or identification of a technical parameter of a series component of the part component of the identified plant module which does not comply with the requirements imposed on the plant module;
- manual and/or automatic second input of process-specific technical requirements for the identified part component and/or of the technical parameter of the series component to a query mask of the component database;
- comparison of the second input with at least one technical parameter of the multiplicity of series components, which is stored in the component database and defines a process-specific property of a respective series component, and, in the event of a positive result:
- identification of at least one series component of a part component, which complies with the process-specific technical requirements, in an output mask of the component database and compiling of the output plant module with the output series component.