# US 2018/0018743 A1 · Method for constructing a predictive model

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2018/0018743 A1
- Document ID: US20180018743A1
- Status: Published application
- Kind: A1
- Application number: 15/647,299
- Filed: 2017-07-12
- Published: 2018-01-18
- Earliest claimed: 2016-07-18
- Assignees: Schneider Electric Industries SAS
- Applicants: Schneider Electric Industries SAS
- Inventors: Michel CLEMENCE; Philippe DESCHAMPS; Yves CHOLLOT; Clementine BENOIT
- Web page: https://patentgrep.com/patent/US20180018743A1

## CPC

- G06Q 50/06: Energy or water supply
- G06F 30/20: Design optimisation, verification or simulation (optimisation, verification or simulation of circuit designs G06F30/30)
- G06Q 10/06375: {Prediction of business process outcome or impact based on a proposed change}
- H02J 3/00: Circuit arrangements for AC mains or AC distribution networks
- H02J 2103/30: Simulating, planning, modelling, reliability check or computer assisted design [CAD] of electric power networks
- H03J 3/14: Visual indication, e.g. magic eye
- Y02E 60/00: Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation
- Y04S 40/20: Information technology specific aspects, e.g. CAD, simulation, modelling, system security
- G06Q: INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06F: ELECTRIC DIGITAL DATA PROCESSING (computer systems based on specific computational models G06N)
- H02J: ELECTRIC POWER NETWORKS; CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H03J: TUNING RESONANT CIRCUITS; SELECTING RESONANT CIRCUITS
- Y02E: REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y04S: SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS

## Abstract

A method for constructing a predictive model of a change of state of an electrical distribution network, the electrical distribution network including a node supplying power to loads connected by way of a distribution line, the method including: a. a step of measuring the variation, during a first time period, of a physical quantity A at the main node, and of a physical quantity B at measuring points of the network; and b. a step of correlating the quantity A and the quantity B measured in step a., so that knowledge of the physical quantity A at the main node allows the value of the physical quantity B at the plurality of measuring points of the network to be predicted.

## Claims

### Claim 1

A method for constructing a model predictive of a change of state of an electrical distribution network, the predictive model being designed to implement a dynamic regulation of said network, the electrical distribution network comprising a main node supplying current to a plurality of loads that are connected to said main node via at least one distribution line, the method comprising:
a) a step of measuring the variation, over a first time period, of at least one physical quantity A at the main node, and of at least one physical quantity B at a plurality of measuring points of the network;
b) a step, executed by a computer, of correlating the at least one quantity A and the at least one quantity B that were measured in step a., so that knowledge of at least one physical quantity A at the main node allows the value of the at least one physical quantity B at the plurality of measuring points of the network to be predicted.

### Claim 2 (depends on 1)

The method according to claim 1, wherein the correlation step b comprises a machine learning algorithm according to a support vector machine method.

### Claim 3 (depends on 1)

The method according to claim 1, wherein the physical quantity A comprises at least one of the physical quantities chosen from the group consisting of voltage, current intensity, active power, and reactive power.

### Claim 4 (depends on 1)

The method according to claim 1, wherein the physical quantity B is a voltage.

### Claim 5 (depends on 1)

The method according to claim 1, wherein the measurement step a is carried out by a plurality of sensors located at the main node and at the plurality of measuring points.

### Claim 6 (depends on 1)

The method according to claim 1, wherein the electrical distribution network comprises decentralized production sources, wherein the decentralized production sources comprise renewable energy sources.

### Claim 7 (depends on 1)

The method according to claim 1, wherein the duration of the first time period is shorter than a month.

### Claim 8 (depends on 1)

The method according to claim 1, wherein at least one distribution line is branched and comprises a plurality of terminals constituting points for measuring the physical quantity B.

### Claim 9 (depends on 1)

The method according to claim 1, wherein the electrical distribution network comprises three phases and a neutral, the steps a and b being executed on the three phases and the neutral.

### Claim 10 (depends on 1)

The method for dynamically regulating an electrical distribution network comprising a main node supplying current to a plurality of loads that are connected to said main node via at least one distribution line, the value of at least one physical quantity B at a plurality of points of the electrical distribution network being correlated with the value of a physical quantity A at the main node according to the predictive model constructed according to claim 1,
the method comprising the regulation of at least one physical quantity A so as to keep the value of the at least one physical quantity B within a range of predetermined values.

### Claim 10 (depends on 10)

The method according to claim 10, wherein the electrical distribution network is interfaced with a power supply network at the main node via a transformer station.

### Claim 11 (depends on 11)

The method according to claim 11, wherein the adjustment of the physical quantity A is carried out by the transformer station.

### Claim 12 (depends on 11)

The method according to claim 11, wherein the adjustment of the physical quantity A is carried out by the transformer station.

### Claim 13 (depends on 12)

The method according to claim 12, wherein the transformer station comprises a regulator that is intended to measure the value of at least one physical quantity A and to predict the value of at least one physical quantity B, said regulator also being suitable for controlling, at the transformer station, the adjustment of the value of the at least one physical quantity A.

### Claim 14 (depends on 10)

The method according to claim 10, wherein the electrical distribution network is an LV network.

### Claim 15 (depends on 10)

The method according to claim 10, wherein the electrical distribution network comprises decentralized production sources, wherein the decentralized production sources comprise renewable energy sources.