# US 2017/0292498 A1 · A power plant controller for generating a power reference to wind turbine generators

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2017/0292498 A1
- Document ID: US20170292498A1
- Status: Published application
- Kind: A1
- Application number: 15/039,390
- Filed: 2014-11-07
- Published: 2017-10-12
- Earliest claimed: 2013-11-28
- Assignees: Vestas Wind Systems A/S
- Applicants: Vestas Wind Systems A/S
- Inventors: Jorge Martinez GARCIA; Rasmus LÆRKE; Henrik MØLLER; Kouroush NAYEBI; Rubin PANNI; Chun Meng HENG
- Web page: https://patentgrep.com/patent/US20170292498A1

## CPC

- F03D 7/0284: {in relation to the state of the electric grid}
- F03D 7/047: {characterised by the controller architecture, e.g. multiple processors or data communications}
- F03D 7/048: {controlling wind farms}
- G05B 23/0286: {Modifications to the monitored process, e.g. stopping operation or adapting control}
- H02J 3/0012: characterised by the contingency detection means in AC networks, e.g. using phasor measurement units [PMU], synchrophasors or contingency analysis
- H02J 3/02: using a single network for simultaneous distribution of AC power at different frequencies
- H02J 3/16: by adjustment of reactive power
- H02J 3/18: Arrangements for adjusting, eliminating or compensating reactive power in networks
- H02J 3/381: {Dispersed generators}
- H02J 3/388: Arrangements for the handling of islanding, e.g. for disconnection or for avoiding the disconnection of power
- H02J 3/50: Controlling the sharing of reactive power
- H02J 13/36: specially adapted for protection systems
- F03D 7/042: {by means of an electrical or electronic controller}
- F05B 2270/1033: Power (if explicitly mentioned)
- F05B 2270/337: Electrical grid status parameters, e.g. voltage, frequency or power demand
- G05B 2219/2619: Wind turbines
- H02J 3/001: Arrangements for handling faults or abnormalities, e.g. emergencies or contingencies
- H02J 3/38: Arrangements for feeding a single network from two or more generators or sources in parallel; Arrangements for feeding already energised networks from additional generators or sources in parallel
- H02J 2101/28: Wind energy
- H02J 2105/16: being internal to power sources or power generation plants
- Y02E 10/72: Wind turbines with rotation axis in wind direction
- Y02E 10/76: Power conversion electric or electronic aspects
- Y02E 40/30: Reactive power compensation
- Y02P 70/50: Manufacturing or production processes characterised by the final manufactured product
- Y04S 10/22: Flexible AC transmission systems [FACTS] or power factor or reactive power compensating or correcting units
- F03D: WIND MOTORS
- G05B: CONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS (systems for controlling or regulating non-electric variables G05D; systems for regulating electric or magnetic variables G05F; control devices or systems insofar as characterised by mechanical features only G05G)
- H02J: ELECTRIC POWER NETWORKS; CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- F05B: INDEXING SCHEME RELATING TO WIND, SPRING, WEIGHT, INERTIA OR LIKE MOTORS, TO MACHINES OR ENGINES FOR LIQUIDS COVERED BY SUBCLASSES F03B, F03D AND F03G
- Y02E: REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02P: CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y04S: SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS

## Abstract

The invention relates to a power plant controller for controlling wind turbine generators. More particularly, the invention relates to a method for compensating data obtained from measurements at a connection point to the grid in case of a communication failure where communication of such data is lost or becomes unreliable. The measured data are used in the power plant controller for determining setpoints for controlling the wind turbine generators' production of active and reactive power. In response to detection of a communication fault a new setpoint is determined independently of new measured grid data by reconfiguring parts of the power plant controller.

## Claims

### Claim 1

A power plant controller for generating a setpoint to one or more wind turbine generators connected to an electrical grid, wherein the setpoint relates to a desired amount of power to be produced at least in part by the one or more wind turbine generators, wherein the power plant controller comprises,
a reference control system configured to receive a stream of electrical grid values from a grid meter and to receive an electrical reference value, wherein the reference control system is configured to determine the setpoint on the basis of the electrical reference value and the stream of electrical grid values, and wherein the power plant controller is configured to determine the electrical grid values based on values measured at a grid connection point, and
a fault detector configured to detect a communication fault in the communication of the electrical grid values, wherein
the power plant controller, in response to a detection of the communication fault, is configured to reconfigure the reference control system so that the setpoint is determined independently of the stream of electrical grid values.

### Claim 2 (depends on 1)

A power plant controller according to claim 1, wherein the power plant controller is configured to reconfigure the reference control system by replacing the electrical grid values with one or more alternative values.

### Claim 3 (depends on 2)

A power plant controller according to claim 2, wherein the power plant controller is configured to receive the one or more alternative values from a backup grid meter.

### Claim 4 (depends on 2)

A power plant controller according to claim 2, wherein the power plant controller is configured to determine the one or more alternative values on basis of one or more of the electrical grid values obtained before the detection of the communication fault.

### Claim 5 (depends on 2)

A power plant controller according to claim 2, wherein the power plant controller is configured to determine the one or more alternative values on basis of one or more electrical output values measured from one or more power outputs of the one or more wind turbine generator.

### Claim 6 (depends on 2)

A power plant controller according to claim 2, wherein the power plant controller is configured to determine the one or more alternative values on basis of one or more measured frequency values measured from the power output of one of the one or more wind turbine generators.

### Claim 7 (depends on 2)

A power plant controller according to claim 2, wherein the power plant controller is configured to determine the one or more alternative values on basis of a measured active power produced by the one or more wind turbine generators.

### Claim 8 (depends on 1)

A power plant controller according to claim 1, wherein the power plant controller is configured to reconfigure the reference control system by determining the setpoint solely on basis of the electrical reference input.

### Claim 9 (depends on 1)

A power plant controller according to claim 1, wherein the power plant controller is configured to determine the setpoint solely on basis of the electrical reference input by setting the setpoint equal to the electrical reference input.

### Claim 10 (depends on 1)

A power plant controller according to claim 1, wherein the reference control system is configured to determine:
a first setpoint (Qset1, Qset2) relating to a desired amount of reactive power on basis of a voltage or reactive reference value (Vref, Qref) and a stream of measured voltage and/or reactive power values (Vm, Qm), and/or
a second setpoint (Pset1, Pset2) relating to a desired amount of active power on basis of a power or frequency reference value (Pref, fref) and a stream of measured frequency and/or power values (fm, Pm).

### Claim 11 (depends on 1)

A power plant controller according to claim 1, wherein the power plant controller is configured to reconfigure the reference control system after a first time delay after detection of the communication fault.

### Claim 12 (depends on 1)

A power plant controller according to claim 1, wherein, in response to a detection of no communication fault, the power plant controller is configured to configure the reference control system back into an original state wherein the setpoint is determined dependent on the electrical grid values communicated from the grid meter.

### Claim 13 (depends on 12)

A power plant controller according to claim 12, wherein the power plant controller is configured to configure the reference control system back into an original state after a second time delay, in response to a detection of no communication fault.

### Claim 14 (depends on 1)

A wind power plant connectable to an electrical grid, wherein the wind power plant comprises at least one wind turbine generator, and a power plant controller as claimed in claim 1.

### Claim 15

A method for generating a setpoint to one or more wind turbine generators connected to an electrical grid via a connection line, where the method comprises:
determining the setpoint on basis of an electrical reference value and a stream of determined electrical grid values communicated to a reference control system from a grid meter, where the grid meter is connected to the connection line at a location which enables measurements of electrical quantities present at the grid, and wherein the electrical grid values are determined based on the electrical quantities present at the grid,
detecting a communication fault in the communication of the electrical grid values, and
in response to detecting the communication fault, reconfiguring the reference control system so that the setpoint is determined independently of the stream of electrical grid values.

### Claim 16

At least one computer program product directly loadable into the internal memory of at least one digital computer, comprising software code portions for performing an operation for generating a setpoint to one or more wind turbine generators connected to an electrical grid via a connection line when said at least one product is/are run on said at least one computer, the operation comprising:
determining the setpoint on basis of an electrical reference value and a stream of determined electrical grid values communicated to a reference control system from a grid meter, where the grid meter is connected to the connection line at a location which enables measurements of electrical quantities present at the grid, and wherein the electrical grid values are determined based on the electrical quantities present at the grid,
detecting a communication fault in the communication of the electrical grid values, and
in response to detecting the communication fault, reconfiguring the reference control system so that the setpoint is determined independently of the stream of electrical grid values.