# US 2017/0285200 A1 · Loading a helical conveyor for underwater seismic exploration

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2017/0285200 A1
- Document ID: US20170285200A1
- Status: Published application
- Kind: A1
- Application number: 15/088,049
- Filed: 2016-03-31
- Published: 2017-10-05
- Earliest claimed: 2016-03-31
- Assignees: Fairfield Industries Incorporated
- Applicants: Fairfield Industries, Inc.
- Inventors: Roger L. Fyffe; Etienne Marc
- Web page: https://patentgrep.com/patent/US20170285200A1

## CPC

- G01V 1/3852: {to the seabed}
- B65G 33/02: for articles
- B65G 67/603: {using devices specially adapted for articles}
- G01V 1/3808: {Seismic data acquisition, e.g. survey design}
- G01V 2210/1427: Sea bed
- G01V: GEOPHYSICS; GRAVITATIONAL MEASUREMENTS; DETECTING MASSES OR OBJECTS; TAGS (means for indicating the location of accidentally buried, e.g. snow-buried, persons A63B29/02)
- B65G: TRANSPORT OR STORAGE DEVICES, e.g. CONVEYORS FOR LOADING OR TIPPING, SHOP CONVEYOR SYSTEMS OR PNEUMATIC TUBE CONVEYORS (packaging B65B; handling thin or filamentary materials, e.g. paper sheets or thread, B65H; cranes B66C; portable mobile or lifting or hauling appliances, e.g. hoists, B66D; devices for lifting or lowering goods for loading or unloading purposes, e.g. fork-lift trucks, B66F9/00; emptying bottles, jars, casks, barrels or similar containers, not otherwise provided for, B67C9/00; delivering or transferring liquids B67D; filling or discharging vessels for liquefied, solidified or compressed gases F17C; pipe-line systems for fluids F17D)

## Abstract

The present disclosure is directed to loading a helical conveyor for underwater seismic exploration. The system includes a case and a first conveyor having a helix structure provided within the case to support one or more ocean bottom seismometer (“OBS”) units. The case can include a first opening at a first end of the first conveyor and a second opening at a second end of the first conveyor. The system can include a base to receive at least a portion of the case. The system can include a second conveyor positioned external to the case that can move an OBS unit into the first opening at the first end of the first conveyor. The first conveyor can receive the OBS unit and direct the OBS unit towards the second opening at the second end of the first conveyor.

## Claims

### Claim 1

A system to deploy ocean bottom seismic (“OBS”) units, comprising:
a case;
a first conveyor provided within the case to support a first one or more OBS units, the first conveyor having a first helix structure;
the case comprising a first opening at a first end of the first conveyor;
the case comprising a second opening at a second end of the first conveyor;
a base to receive at least a portion of the case;
a second conveyor positioned external to the case to support the first one or more OBS units;
the second conveyor constructed to move a first OBS unit of the first one or more OBS units into the first opening at the first end of the first conveyor, and the first conveyor constructed to receive the first OBS unit and direct the first OBS unit towards the second opening at the second end of the first conveyor;
a third conveyor having a second helix structure provided within the case, the third conveyor configured to support a second one or more OBS units; and
a support structure configured to extend through a central axis of the first helix structure of the first conveyor and the second helix structure of the third conveyor.

### Claim 2 (depends on 1)

The system of claim 1, wherein the case comprises a first portion to produce drag to dampen rotation of the case moved through an aqueous medium.

### Claim 3 (depends on 1)

The system of claim 1, comprising:
an elevator configured to position the second conveyor to align the second conveyor with the first opening.

### Claim 4 (depends on 1)

The system of claim 1, comprising:
a first gate configured to close the first opening,
wherein the second conveyor is configured to open the first gate.

### Claim 5 (depends on 1)

The system of claim 1, comprising:
a first gate configured to close the second opening,
wherein the second conveyor is configured to open the first gate to remove the first OBS unit from the helix structure.

### Claim 6 (depends on 1)

The system of claim 1, comprising:
a crane; and
a cable coupled to the crane and the case, the crane configured to raise, lower, or support the case via the cable.

### Claim 7 (depends on 1)

The system of claim 1, comprising:
a crane; and
a cable coupled to the crane and the case, the crane configured to lower the case loaded with the one or more OBS units onto the seabed via the cable.

### Claim 8 (depends on 1)

The system of claim 1, comprising:
a crane;
a cable coupled to the crane and the case, the crane configured to lower the case loaded with the one or more OBS units into the aqueous medium; and
a fin extending from the case, the fin configured to create force as the case moves through the aqueous medium to dampen rotation of the case.

### Claim 9 (depends on 1)

The system of claim 1, comprising:
the base configured to contact the seabed and support the case on the seabed.

### Claim 10 (depends on 1)

The system of claim 1, wherein the helix structure is a first helix structure, and the one or more OBS units is a first one or more OBS units, the system comprising:
a third conveyor having a second helix structure provided within the case, the third conveyor configured to support a second one or more OBS units.

### Claim 11 (depends on 1)

The system of claim 1, wherein the helix structure is a first helix structure, and the one or more OBS units is a first one or more OBS units, the system comprising:
a third conveyor having a second helix structure provided within the case, the third conveyor configured to support a second one or more OBS units;
a third opening of the case at a third end of the second conveyor; and
an elevator configured to raise or lower the second conveyor, the elevator configured to align the second conveyor with the first opening to load the first one or more OBS units onto the first conveyor via the first opening, and align the second conveyor with third opening to load the second one or more OBS units onto the third conveyor via the third opening.

### Claim 12 (depends on 1)

The system of claim 1, wherein the first conveyor is an unpowered gravity conveyor, and the second conveyor is powered.

### Claim 13

A method for deploying ocean bottom seismic (“OBS”) units, comprising:
providing a case;
providing a first conveyor having a helix structure and provided within the case, the first conveyor configured to support one or more OBS units, the case comprising a first opening at a first end of the first conveyor and a second opening at a second end of the first conveyor;
providing a base to hold the case in a substantially vertical position;
providing a second conveyor positioned external to the case and configured to support the one or more OBS units;
loading, via the second conveyor, a first OBS unit of the one or more OBS units into the case via the first opening at the first end of the first conveyor;
directing, via the first conveyor, the first OBS unit received from the second conveyor towards the second opening at the second end of the first conveyor;
providing a third conveyor having a second helix structure within the case, the third conveyor configured to support a second one or more OBS units; and
providing a support structure configured to extend through a central axis of the first helix structure of the first conveyor and the second helix structure of the third conveyor.

### Claim 14 (depends on 13)

The method of claim 13, wherein the case comprises a first portion to produce drag to dampen rotation of the case moved through an aqueous medium.

### Claim 15 (depends on 13)

The method of claim 13, comprising:
aligning, via an elevator, the second conveyor with the first opening.

### Claim 16 (depends on 13)

The method of claim 13, comprising:
opening, via the second conveyor, a first gate closing the first opening.

### Claim 17 (depends on 13)

The method of claim 13, comprising:
opening, via the second conveyor, a first gate closing the first opening; and
removing, via the second conveyor, the first OBS unit from the first conveyor.

### Claim 18 (depends on 13)

The method of claim 13, comprising:
positioning, using a crane coupled to the case via a cable, the case into the aqueous medium.

### Claim 19 (depends on 13)

The method of claim 13, comprising:
positioning, using a crane coupled to the case via a cable, the case onto the seabed, the case comprising the one or more OBS units.

### Claim 20 (depends on 13)

The method of claim 13, comprising:
positioning, using a crane coupled to the case via a cable, the case loaded with the one or more OBS units into the aqueous medium; and
creating, using a fin extending from the case, force as the case moves through the aqueous medium to dampen rotation of the case.

### Claim 21 (depends on 13)

The method of claim 13, comprising:
contacting the seabed with the base; and
supporting, with the base, the case on the seabed.

### Claim 22 (depends on 13)

The method of claim 13, wherein the helix structure is a first helix structure, and the one or more OBS units is a first one or more OBS units, the method comprising:
providing, within the case, a third conveyor having a second helix structure; and
loading a second one or more OBS units onto the third conveyor.