# US 2017/0284200 A1 · Method of moving material

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2017/0284200 A1
- Document ID: US20170284200A1
- Status: Published application
- Kind: A1
- Application number: 15/507,575
- Filed: 2015-08-28
- Published: 2017-10-05
- Earliest claimed: 2014-09-01
- Assignees: Opti-Minez Pty Ltd
- Applicants: Opti-Minez Pty Ltd
- Inventors: David John Hall; Cameron Albert Mitchell Voss; Lachlan Yeldham
- Web page: https://patentgrep.com/patent/US20170284200A1

## CPC

- E21C 47/02: for coal, brown coal, or the like (dredgers or soil-shifting machines in general E02F)
- E02F 3/76: Graders, bulldozers, or the like with scraper plates or ploughshare-like elements (soil-working A01B); Levelling {scarifying} devices {(street cleaning E01H; construction of roads E01C19/00, E01C23/00)}
- E21C 37/00: Other methods or devices for dislodging with or without loading (breaking-down by means inserted in slits E21C27/14)
- E21C 41/00: Methods of underground or surface mining (E21C45/00 takes precedence); Layouts therefor (for peat E21C49/00)
- E21C 41/26: Methods of surface mining (machines for obtaining, or the removal of, materials in open-pit mines E21C47/00); Layouts therefor
- E21C 41/28: for brown or hard coal
- E21F 13/02: {Transport of mined mineral} in galleries
- E21C 41/32: Reclamation of surface-mined areas (machines or methods for treating or working soil for agricultural purposes A01B77/00, A01B79/00; machines for back-filling E02F5/22)
- E21C: MINING OR QUARRYING
- E02F: DREDGING; SOIL-SHIFTING (winning peat E21C49/00)
- E21F: SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS

## Abstract

The invention is directed to a method of strip mining that involves dividing the pit into blocks in a diamond shape arrangement with an angular advancing strike face and removing waste material from each diagonally adjacent block so as to minimize the amount of waste material pushed by dozers and maintain the incline of ramps to gradients of 10% or less so that trucks can take mined ore from the pit.

## Claims

### Claim 1

A method of strip mining to mine an ore seam including
dividing the pit into a plurality of blocks where each block is orientated along a mining strike length in a diamond pattern formation to present an angular advancing strike face;
moving overlying waste material from a first block of said plurality of blocks to access the ore seam wherein the waste material is divided into an upper cut volume and lower cut volume, the upper cut volume is removed out of the pit and the lower cut volume is moved into a first adjacent pit void;
mining the exposed ore seam in the first block;
identifying a second block of the plurality of blocks that is diagonally orientated with respect to the first block and along the mining strike length;
moving an uppercut volume from the second block to the first block and a lower cut volume of the second block to a second adjacent pit void to expose the ore seam; and
mining the exposed ore seam in the second block; wherein the steps of moving waste material and mining the exposed ore as performed with respect to the second block are repeated with the remainder of the plurality of blocks.

### Claim 2 (depends on 1)

A method as claimed in claim 1, wherein the first and second adjacent pit voids are behind the advancing strike face and formed from a previous mining operation.

### Claim 3 (depends on 1)

A method as claimed in claim 1 wherein the method is carried out to move waste material minimal distances and have inclines with a substantially 10% gradient or less.

### Claim 4 (depends on 1)

A method as claimed in claim 1 wherein a front corner of an adjacent block is incorporated into the cut volume to form a roadway to move ore from the pit.

### Claim 5 (depends on 1)

A method as claimed in claim 1 wherein a percentage of dozer and truck and shovel operations usage is dependent on topography and geology including direction and depth of the ore seam.

### Claim 6 (depends on 1)

A method as claimed in claim 1 wherein the diamond pattern has the plurality of blocks orientated at 45 degrees to the advancing strike face but changes to 90 degrees when a dipping angle of the ore seam increases to substantially 10 degrees and higher.

### Claim 7 (depends on 1)

A method as claimed in claim 1 wherein the length of the blocks along the advancing strike face can be extended as a dipping angle of the ore seam increases so as to maintain an inclined ramp with a maximum gradient of substantially 10 degrees.

### Claim 8 (depends on 1)

A method as claimed in claim 1 wherein strategic blasting is used to reduce an amount of waste material to be mechanically excavated, facilitate the dozing by casting material in the direction that the dozers will need to push the material, separating and dealing with the upper and lower layers of material differently, and or directing material to a position that allows the formation of a ramp or bridge to transport excavated material from the pit.

### Claim 9 (depends on 1)

A method as claimed in claim 1 wherein strategic blasting includes placing explosives at two or more locations, arranging the explosives at each location and coordinating a timing of a detonation of the explosives, wherein the two or more locations can be locations at different depths at a work site, spaced locations to effect casting of site faces in different directions and locations that involve a combination of vertical depth and horizontal spacing positioning, wherein the blasting maximizes the casting of the material to facilitate moving the waste material.

### Claim 10 (depends on 1)

A method as claimed in claim 1 wherein the ore seam is a coal seam.