# US 2017/0284031 A1 · Subgrade Peat Stabilisation System for Railway

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2017/0284031 A1
- Document ID: US20170284031A1
- Status: Published application
- Kind: A1
- Application number: 15/427,311
- Filed: 2017-02-08
- Published: 2017-10-05
- Earliest claimed: 2016-03-31
- Assignees: TBT Engineering Limited
- Applicants: TBT Engineering Limited
- Inventors: Gordon C. Maki
- Web page: https://patentgrep.com/patent/US20170284031A1

## CPC

- E01B 1/008: {Drainage of track}
- E01B 27/02: Placing the ballast; Making ballastway; Redistributing ballasting material; Machines or devices therefor; Levelling means
- E02D 3/10: by watering, draining, de-aerating or blasting, e.g. by installing sand or wick drains (E02D3/11 takes precedence; soil-penetrating vibrators with auxiliary watering E02D3/054; drainage of soil in general E02B11/00)
- E01B: PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS (derailing or rerailing blocks on track, track brakes or retarders B61K)
- E02D: FOUNDATIONS; EXCAVATIONS; EMBANKMENTS (specially adapted for hydraulic engineering E02B); UNDERGROUND OR UNDERWATER STRUCTURES {(tunnels, tunnelling, mining E21)}

## Abstract

A ground stabilisation system is used for stabilising a subgrade region which includes a peat layer under a railway having rails supported across rail ties on a ballast layer over the subgrade region. The system uses a plurality of drain members submerged in an upright orientation within the peat layer of the subgrade region in which each drain member has a hollow interior and a plurality of openings therein which allow communication of fluid from the peat layer surrounding the drain member into the hollow interior of the drain member so as to be arranged to reduce fluid pressure in the peat layer when the peat layer undergoes dynamic loading from a passing train. Each drain member is a semi-rigid pipe having an axial stiffness greater than a dynamic stiffness of the peat layer to reduce loading on the peat layer under dynamic loading from a passing train.

## Claims

### Claim 1

A ground stabilisation system for a railway having rails supported across rail ties on a ballast layer over a subgrade region which includes a peat layer, the system comprising:
a plurality of drain members submerged in an upright orientation within the peat layer of the subgrade region;
each drain member including a hollow interior and a plurality of openings therein which allow communication of fluid from the peat layer surrounding the drain member into the hollow interior of the drain member so as to be arranged to reduce fluid pressure in the peat layer when the peat layer undergoes dynamic loading from a passing train.

### Claim 2 (depends on 1)

The system according to claim 1 wherein a top end of each drain member is spaced below an elevation of the rail ties.

### Claim 3 (depends on 1)

The system according to claim 1 further comprising ballast material spanning between a top end of each drain member and an elevation of the rail ties.

### Claim 4 (depends on 1)

The system according to claim 1 wherein a top end of each drain member terminates within a fill layer above the peat layer.

### Claim 5 (depends on 1)

The system according to claim 1 wherein a bottom end of each drain member terminates within a soil layer below the peat layer.

### Claim 6 (depends on 1)

The system according to claim 1 wherein each drain member spans a full height of the peat layer.

### Claim 7 (depends on 1)

The system according to claim 1 wherein each drain member comprises a semi-rigid pipe.

### Claim 8 (depends on 7)

The system according to claim 7 wherein the semi-rigid pipe has a stiffness in an axial direction which is greater than a dynamic stiffness of the peat layer so as to be arranged to reduce loading on the peat layer when the peat layer undergoes dynamic loading from a passing train.

### Claim 9 (depends on 7)

The system according to claim 7 wherein the semi-rigid pipe comprises corrugated plastic pipe.

### Claim 10 (depends on 1)

The system according to claim 1 wherein the drain members are more permeable than the peat layer.

### Claim 11 (depends on 1)

The system according to claim 1 wherein a horizontal spacing between adjacent drain members is less than a length of a longest drainage path of peat in the peat layer to a nearest permeable boundary of the peat layer.

### Claim 12 (depends on 1)

The system according to claim 1 further comprising aggregate fill occupying the hollow interior of each drain member.

### Claim 13 (depends on 1)

The system according to claim 1 further comprising a filter material spanning over the openings in each drain member, the filter material having a smaller aperture size than a size of the openings.

### Claim 14 (depends on 13)

The system according to claim 13 wherein the filter material comprises a sheet which fully surrounds each drain member.

### Claim 15 (depends on 1)

The system according to claim 1 further comprising a reinforcing mesh fully surrounding each drain member.

### Claim 16

A method of stabilising a railway having rails supported across rail ties on a ballast layer over a subgrade region which includes a peat layer, the method comprising:
providing a plurality of elongate drain members each including a hollow interior and a plurality of openings therein; and
submerging the drain members in an upright orientation within the peat layer of the subgrade region such that fluid can readily pass through the openings in the drain members from the peat layer surrounding the drain member into the hollow interior of the drain members.

### Claim 17 (depends on 16)

The method according to claim 16 including horizontally spacing the drain members relative to one another by a horizontal spacing which is less than a length of a longest drainage path of peat in the peat layer to a nearest permeable boundary of the peat layer.

### Claim 18 (depends on 16)

The method according to claim 16 including inserting the drain members downwardly into the ground through spaces between adjacent ones of the rail ties.

### Claim 19 (depends on 16)

The method according to claim 16 including associating a plurality of drain members with each rail tie in a first region to be stabilized, and gradually reducing the number of drain members associated with each rail tie with increasing distance along the rails from the first region.

### Claim 20 (depends on 16)

The method according to claim 16 including maintaining the drain members in a condition which is more permeable than a permeability of peat in the peat layer.