Database and a development project system, method, and recording medium
AssigneeInternational Business Machines Corporation
InventorsSwaminathan Balasubramanian, Kenneth Wayne Roberson, Cheranellore Vasudevan
Life of this patent
Estimating the term…
Abstract
A development project method, system, and non-transitory computer readable medium, include a classification circuit configured to classify tasks of a project into a first capability-type executed by a first project development strategy and a second capability-type executed by a second project development strategy, a switch point calculation circuit configured to calculate a switch point based on values stored in the database, the switch point being a time during the project when project development switches between the first project development strategy and the second project development strategy
Claims20
A development project system including a database, comprising:
- a classification circuit configured to classify tasks of a project into a first capability-type executed by a first project development strategy and a second capability-type executed by a second project development strategy;
- and
- a switch point calculation circuit configured to calculate a switch point based on values stored in the database, the switch point being a time during the project when project development switches between the first project development strategy and the second project development strategy.
A non-transitory computer-readable recording medium recording a development project program, the program causing a computer to perform:
- reading values from a database;
- classifying tasks of a project in a first capability-type executed by a first project development strategy and a second capability-type executed by a second project development strategy;
- and
- calculating a switch point based on the values read from the database, the switch point being a time during the project when project development switches between the first project development strategy and the second project development strategy.
A development project method, comprising:
- reading values from a database;
- classifying tasks of a project in a first capability-type executed by a first project development strategy and a second capability-type executed by a second project development strategy;
- and
- calculating a switch point based on the values read from the database, the switch point being a time during the project when project development switches between the first project development strategy and the second project development strategy.
Dependencies are inferred from the claim text.