# US 2016/0231737 A1 · Planning and engineering method, software tool and system for a process plant

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2016/0231737 A1
- Document ID: US20160231737A1
- Status: Published application
- Kind: A1
- Application number: 15/014,163
- Filed: 2016-02-03
- Published: 2016-08-11
- Earliest claimed: 2015-02-11
- Assignees: Siemens Aktiengesellschaft
- Applicants: Siemens Aktiengesellschaft
- Inventors: Oliver DRUMM; Henning Lenz; Benjamin Lutz; Gerrit Wolf
- Web page: https://patentgrep.com/patent/US20160231737A1

## CPC

- G05B 19/41885: {characterised by modeling, simulation of the manufacturing system}
- G05B 2219/13181: Selection of limited stimuli, inputs for simulation
- G05B 2219/31368: MAP manufacturing automation protocol
- G05B 2219/32423: Task planning
- G05B 2219/35215: Generate optimal nc program variant as function of cost, time, surface, energy
- G05B 2219/40515: Integration of simulation and planning
- Y02P 90/02: Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
- G05B: CONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS (systems for controlling or regulating non-electric variables G05D; systems for regulating electric or magnetic variables G05F; control devices or systems insofar as characterised by mechanical features only G05G)
- Y02P: CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS

## Abstract

A flowchart of a process plant is compiled by linking graphical process objects representing operator-controllable and observable facilities of the plant when planning a process plant, wherein the process in the process plant is simulated with reference to simulation models assigned to the graphical process objects during a simulation phase, where simulation models include energy consumption models that describe the electrical energy consumption of the respective facilities to be described as a function of measurable or known process variables in the plant and hence enable simulation and optimization of the automation with respect to electrical energy consumption and energy efficiency.

## Claims

### Claim 1

A planning and engineering method for a process plant, the method comprising:
linking graphical process objects representing operator-controllable and observable facilities of the process plant to compile a flow chart of the process plant via a plant planning tool during a plant planning phase;
importing the linked graphical process objects of the process plant or a part of the process plant via a simulation tool during a simulation phase and simulating a process in the process plant or a part of the process plant with reference to simulation models assigned to the imported graphical process objects during the simulation phase;
linking icons of function blocks to compile a function chart of the process plant by an engineering tool during an engineering phase, each graphical process object including a corresponding automation function block describing an automation function of the graphical process object; and
loading automation function blocks into automation devices of the plant for implementation;
wherein, for at least a part of the graphical process objects representing electrically operated facilities of the process plant, the assigned simulation models are each supplemented by an energy consumption model describing an electrical energy consumption of an observable facility as a function of measurable or known process variables in the process plant;
wherein the electrical energy consumption of the facilities represented by the imported graphical process objects is simulated in the simulation phase; and
wherein, for graphical process objects for which the assigned simulation models are supplemented by an energy consumption model, a corresponding automation function block is supplemented by an energy consumption function which is derived by specialization from the energy consumption model and is formed to estimate a current electrical energy consumption of the observable facility during its run-time in the process plant.

### Claim 2

A planning and engineering software tool for a process plant, comprising:
a plant planning tool configured to compile a flow chart of the plant by linking graphical process objects representing operator-controllable and observable facilities of the plant during a process plant planning phase;
a simulation tool configured to import the linked graphical process objects of the process plant or of a part of the process plant during a simulation phase and configured to simulate a process in the process plant or the part of the process plant with reference to simulation models assigned to the imported graphical process objects during the simulation phase; and
an engineering tool configured to compile a function chart of the plant by linking icons of function blocks during an engineering phase, an automation function block describing the automation function of the graphical process object corresponding to each graphical process object and being further formed to load the automation function blocks into automation devices of the process plant for implementation;
wherein, for at least a part of the graphical process objects representing electrically operated observable facilities of the process plant, the assigned simulation models are each supplemented by an energy consumption model describing an electrical energy consumption of an observable facility as a function of measurable or known process variables in the plant;
wherein the simulation tool is further configured to simulate the electrical energy consumption of the observable facilities represented by the imported graphical process objects during the simulation phase; and
wherein, for process objects for which the assigned simulation models are supplemented by an energy consumption model, a corresponding automation function block is supplemented by an energy consumption function representing a specialization of the energy consumption model and which is formed to estimate an current electrical energy consumption of the observable facility during its run-time in the process plant.

### Claim 3

A planning and engineering system for a process plant, wherein the planning and engineering system is configured to:
link graphical process objects representing operator-controllable and observable facilities of the plant to compile a flowchart of the process plant during a process plant planning phase;
simulate a process in the process plant or a part of the process plant with reference to simulation models assigned to the graphical process objects during a simulation phase; and
compile a function chart of the plant by linking icons of function blocks during an engineering phase, an automation function block describing the automation function of a graphical process object corresponding to each graphical process object and to load the automation function blocks into automation devices of the plant for implementation;
wherein, for at least a part of the graphical process objects representing electrically operated facilities of the process plant, the assigned simulation models are each supplemented by an energy consumption model describing an electrical energy consumption of an observable facility as a function of measurable or known process variables in the process plant;
wherein the planning and engineering system is further configured to simulate an electrical energy consumption of the observable facilities represented by the imported graphical process objects during the simulation phase; and
wherein, for graphical process objects for which the assigned simulation models are supplemented by an energy consumption model, the corresponding automation function block is supplemented by an energy consumption function representing a specialization of the energy consumption model and which is formed to estimate a current electrical energy consumption of the observable facility during its run-time in the process plant.

### Claim 4 (depends on 3)

An automation system for a process plant having the planning and engineering system as claimed in claim 3.

### Claim 5 (depends on 4)

The automation system as claimed in claim 4, wherein the automation function blocks loaded into the automation devices use the energy consumption function to determine the current electrical energy consumption of the observable facilities during the operation of the process plant.

### Claim 6 (depends on 5)

The automation system as claimed in claim 5, wherein the automation system is configured to perform condition monitoring of the plant by correlations between automation behavior and the determined current electrical energy consumption.

### Claim 7 (depends on 1)

A planning and engineering method of claim 1, wherein the method compiles a function block for an automation device.

### Claim 8 (depends on 2)

The planning and engineering software tool for the process plant of claim 2, wherein the planning and engineering software tool compiles a function block for an automation device.

### Claim 9 (depends on 3)

The planning and engineering system for the process plant of claim 3, wherein the planning and engineering system compiles a function block for an automation device.